AAI MAULI PARK BUILDING B
by HENDAR LAXMAN MHATRE · Bhiwandi, Thane
Registered on MahaRERA under P51700081073, and currently active. Its completion date has moved from December 2027 to April 2028, 4 months later.
Source: GharKundli’s check of MahaRERA records, October 2026.
GharKundli’s full report on AAI MAULI PARK BUILDING B
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51700081073
- Status
- Registered and active
- Builder
- HENDAR LAXMAN MHATRE
- Location
- Bhiwandi, Thane · 421302
- Project type
- Residential / Group Housing
- Registered on
- 26 Dec 2025
- Completion date at registration
- December 2027
- Latest completion date
- April 2028
- Delay so far
- 4 months
- Homes
- 30
- Sold or booked
- 82%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Kundli Watch
AAI MAULI PARK BUILDING B: buyers & owners
Free. You talk to our team privately — no one sees your number.
How are you connected to this project?
You’ll sign in with your mobile number first, then come straight back here.
Common questions about AAI MAULI PARK BUILDING B
Is AAI MAULI PARK BUILDING B registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), AAI MAULI PARK BUILDING B is registered as P51700081073 and its status is "Registered and active".
Where is AAI MAULI PARK BUILDING B?
AAI MAULI PARK BUILDING B by HENDAR LAXMAN MHATRE is in Bhiwandi, Thane (pincode 421302), Maharashtra, and is registered on MahaRERA as P51700081073, per GharKundli's check of MahaRERA records.
When is possession of AAI MAULI PARK BUILDING B due?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for AAI MAULI PARK BUILDING B in Bhiwandi, Thane is 30 April 2028 — 4 months later than 31 December 2027, the date given at registration.
Does AAI MAULI PARK BUILDING B have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Who is the builder of AAI MAULI PARK BUILDING B?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is HENDAR LAXMAN MHATRE, which has 1 other project registered on MahaRERA.
Other projects in pincode 421302
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.