by Prime Abhishek Buildcon · Pushpak, Raigarh

Possession date of Prime Pearl: 31 December 2026, moved from 31 December 2024 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52000045806, and currently active. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Prime Pearl?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Prime Pearl has moved

  1. 31 December 2024

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EA22072621832)

    Reason the builder gave MahaRERA:
    “The project completion timeline has been impacted due to ongoing coordination with various statutory authorities and the time involved in obtaining requisite approvals and compliances. Further, certain minor finishing and allied works are p…” Read the full reason“The project completion timeline has been impacted due to ongoing coordination with various statutory authorities and the time involved in obtaining requisite approvals and compliances. Further, certain minor finishing and allied works are presently in progress, and the Occupancy Certificate (OC) from the competent authority is awaited. In view of the above, additional time is required to complete the remaining works and fulfill all regulatory formalities. Given the circumstances, we kindly request an extension until 31-12-2026, to complete the project and fulfill all regulatory requirements”

Source: Prime Pearl’s extension records on MahaRERA (P52000045806), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Prime Pearl

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the December 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52000045806
Status
Registered and active
Builder
Prime Abhishek Buildcon
Location
Pushpak, Raigarh · 410206
Project type
Others
Registered on
15 Jun 2022
Completion date at registration
December 2024
Latest completion date
December 2026
Delay so far
24 months
Homes
25
Sold or booked
93%
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of Prime Pearl, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Prime Pearl100%100%80%0%

Commencement certificate (CC), as filed on MahaRERA

  • Prime Pearl: covers 5 (Ground + 4 upper floors)

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Prime Pearl every month.

Prime Pearl: buildings, flats and land, as filed on MahaRERA

  • Buildings: Prime Pearl (5 floors, 28 units)
  • Land: 380 sq m (about 0.1 acres) · sanctioned built-up 569 sq m

The builder’s record and reviews

Prime Abhishek Buildcon (a group of 2 linked companies) has 5 projects on MahaRERA since 2022, this one included. Of the 4 GharKundli has checked: 4 still being built, 4 past the promised date (typically 22 months late). 5 complaints on MahaRERA across 3 projects.

Read Google reviews of Prime Pearl →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Prime Pearl: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Prime Pearl

What is the possession date of Prime Pearl?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Prime Pearl in Pushpak, Raigarh is 31 December 2026 — 24 months later than 31 December 2024, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Prime Pearl?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Prime Pearl's builder has filed on MahaRERA, the official one, is 31 December 2026, already 24 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Prime Pearl extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Prime Pearl's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "The project completion timeline has been impacted due to ongoing coordination with various statutory authorities and the time involved in obtaining requisite approvals and compliances. Further, certain minor finishing and allied works are presently in progress, and the Occupancy Certificate (OC) from the competent authority is awaited. In view of the above, additional time is required to complete the remaining works and fulfill all regulatory formalities. Given the circumstances, we kindly request an extension until 31-12-2026, to complete the project and fulfill all regulatory requirements".

What is the RERA number of Prime Pearl?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Prime Pearl in Pushpak, Raigarh is P52000045806.

Is Prime Pearl registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Prime Pearl is registered as P52000045806 and its status is "Registered and active".

What is the construction status of Prime Pearl?

According to GharKundli's check of MahaRERA records (updated October 2026), Prime Pearl's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Prime Pearl is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.

Does Prime Pearl have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Prime Pearl safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Prime Pearl is registered on MahaRERA as P52000045806, its completion date has moved 24 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Prime Pearl's possession date changes?

The latest dates are on Prime Pearl's MahaRERA page (P52000045806). GharKundli's Kundli Watch sends a free WhatsApp update on Prime Pearl every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Prime Pearl have?

According to GharKundli's check of MahaRERA records (updated October 2026), Prime Pearl has one building filed: Prime Pearl with 5 floors and 28 units.

How big is the land of Prime Pearl?

According to GharKundli's check of MahaRERA records (updated October 2026), Prime Pearl stands on 380 sq m of land (about 0.1 acres), with 569 sq m of sanctioned built-up area.

What is the track record of Prime Pearl's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Prime Abhishek Buildcon (a group of 2 linked companies) has 5 projects on MahaRERA since 2022, this one included. Of the 4 GharKundli has checked: 4 still being built, 4 past the promised date (typically 22 months late). 5 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Prime Pearl?

Google Maps has reviews of Prime Pearl written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Prime Pearl?

Prime Pearl by Prime Abhishek Buildcon is in Pushpak, Raigarh (pincode 410206), Maharashtra, and is registered on MahaRERA as P52000045806, per GharKundli's check of MahaRERA records.

How many homes are in Prime Pearl?

According to GharKundli's check of MahaRERA records (updated October 2026), Prime Pearl has 25 homes in 1 tower registered on MahaRERA, and 93% of them are sold or booked.

When was Prime Pearl registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Prime Pearl was registered on MahaRERA on 15 June 2022. GharKundli did not find a title report on the land on file there.

Are there court cases on Prime Pearl?

No court cases are listed for Prime Pearl on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Prime Pearl?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Prime Abhishek Buildcon, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2026 in Raigad →

Other projects in Pushpak

All 2,664 projects in Panvel (410206) →

Other projects by Prime Abhishek Buildcon

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.