Prime Opal
by Prime Abhishek Buildcon · Dapoli , Pushpak Node, RaigarhAlso near Pushpak - Dapoli, Pushpak Nagar, Navi Mumbai
Possession date of Prime Opal: 31 December 2026, moved from 31 December 2024 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000048900, and currently active. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Prime Opal?
How the possession date of Prime Opal has moved
31 December 2024
Completion date given when the project was registered
30 June 2025
Extended at the builder's request (MahaRERA application EXT52000027488)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges. Despite these setbacks, we are worki…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 30-06-2025 to complete the project and fulfil all regulatory requirements. We seek your understanding and approval of this request.”30 June 2026
Extended at the builder's request (MahaRERA application EA19012619505)
Reason the builder gave MahaRERA:
“We request a RERA extension due to pending Occupancy Certificate (OC) formalities. The project construction is completed; however, certain statutory inspections, documentation reviews, and approval processes by the designated authorities ar…” Read the full reason
“We request a RERA extension due to pending Occupancy Certificate (OC) formalities. The project construction is completed; however, certain statutory inspections, documentation reviews, and approval processes by the designated authorities are still underway. These procedures are beyond the control of the promoter and require additional time to ensure full compliance with regulatory requirements. Therefore, an extension is sought to complete the OC process and hand over the units lawfully. Given the circumstances, we kindly request an extension until 30-06-2026, to complete the project and fu…”31 December 2026
Extended at the builder's request (MahaRERA application EA20072621802)
Reason the builder gave MahaRERA:
“We hereby request an extension of the project registration period due to the pending issuance of the Occupancy Certificate (OC). While the construction of the project has been completed, certain statutory inspections, documentation verifica…” Read the full reason
“We hereby request an extension of the project registration period due to the pending issuance of the Occupancy Certificate (OC). While the construction of the project has been completed, certain statutory inspections, documentation verifications, and approval procedures by the competent authorities are still in progress. These regulatory processes are beyond our control and require additional time to ensure full compliance with all applicable legal and statutory requirements. The extension is therefore sought solely to facilitate the completion of the OC formalities and enable the lawful ha…”
Source: Prime Opal’s extension records on MahaRERA (P52000048900), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Prime Opal
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000048900
- Status
- Registered and active
- Builder
- Prime Abhishek Buildcon
- Location
- Dapoli , Pushpak Node, Raigarh · 410206
- Project type
- Others
- Registered on
- 24 Jan 2023
- Completion date at registration
- December 2024
- Latest completion date
- December 2026
- Delay so far
- 24 months
- Homes
- 29
- Sold or booked
- 79%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of Prime Opal, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Prime Opal | 100% | 100% | 75% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Prime Opal: covers 7 (G + 6)
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Prime Opal every month.
Prime Opal: buildings, flats and land, as filed on MahaRERA
- Buildings: Prime Opal (7 floors, 33 units)
- Land: 470 sq m (about 0.1 acres) · sanctioned built-up 1,131 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Prime Abhishek Buildcon (a group of 2 linked companies) has 5 projects on MahaRERA since 2022, this one included. Of the 4 GharKundli has checked: 4 still being built, 4 past the promised date (typically 22 months late). 5 complaints on MahaRERA across 3 projects.
Read Google reviews of Prime Opal →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Prime Opal: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Prime Opal
What is the possession date of Prime Opal?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Prime Opal in Dapoli , Pushpak Node, Raigarh is 31 December 2026 — 24 months later than 31 December 2024, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Prime Opal?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Prime Opal's builder has filed on MahaRERA, the official one, is 31 December 2026, already 24 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Prime Opal extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Prime Opal's builder applied to MahaRERA to extend the completion date 3 times: to 30 June 2025, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. We are closely monitoring progress and taking all necessary steps to ensure timely completion. Given the circumstances, we kindly request an extension until 30-06-2025 to complete the project and fulfil all regulatory requirements. We seek your understanding and approval of this request."; to 30 June 2026, giving the reason "We request a RERA extension due to pending Occupancy Certificate (OC) formalities. The project construction is completed; however, certain statutory inspections, documentation reviews, and approval processes by the designated authorities are still underway. These procedures are beyond the control of the promoter and require additional time to ensure full compliance with regulatory requirements. Therefore, an extension is sought to complete the OC process and hand over the units lawfully. Given the circumstances, we kindly request an extension until 30-06-2026, to complete the project and fu…"; to 31 December 2026, giving the reason "We hereby request an extension of the project registration period due to the pending issuance of the Occupancy Certificate (OC). While the construction of the project has been completed, certain statutory inspections, documentation verifications, and approval procedures by the competent authorities are still in progress. These regulatory processes are beyond our control and require additional time to ensure full compliance with all applicable legal and statutory requirements. The extension is therefore sought solely to facilitate the completion of the OC formalities and enable the lawful ha…".
What is the RERA number of Prime Opal?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Prime Opal in Dapoli , Pushpak Node, Raigarh is P52000048900.
Is Prime Opal registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Prime Opal is registered as P52000048900 and its status is "Registered and active".
What is the construction status of Prime Opal?
According to GharKundli's check of MahaRERA records (updated October 2026), Prime Opal's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Prime Opal is 100% done and internal work 75%. GharKundli's full report compares construction progress with the deadline.
Does Prime Opal have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Prime Opal safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Prime Opal is registered on MahaRERA as P52000048900, its completion date has moved 24 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Prime Opal's possession date changes?
The latest dates are on Prime Opal's MahaRERA page (P52000048900). GharKundli's Kundli Watch sends a free WhatsApp update on Prime Opal every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Prime Opal have?
According to GharKundli's check of MahaRERA records (updated October 2026), Prime Opal has one building filed: Prime Opal with 7 floors and 33 units.
How big is the land of Prime Opal?
According to GharKundli's check of MahaRERA records (updated October 2026), Prime Opal stands on 470 sq m of land (about 0.1 acres), with 1,131 sq m of sanctioned built-up area.
What is the track record of Prime Opal's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Prime Abhishek Buildcon (a group of 2 linked companies) has 5 projects on MahaRERA since 2022, this one included. Of the 4 GharKundli has checked: 4 still being built, 4 past the promised date (typically 22 months late). 5 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Prime Opal?
Google Maps has reviews of Prime Opal written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Prime Opal?
Prime Opal by Prime Abhishek Buildcon is in Dapoli , Pushpak Node, Raigarh (pincode 410206), near Pushpak - Dapoli, Pushpak Nagar, Navi Mumbai, Maharashtra, and is registered on MahaRERA as P52000048900, per GharKundli's check of MahaRERA records.
How many homes are in Prime Opal?
According to GharKundli's check of MahaRERA records (updated October 2026), Prime Opal has 29 homes in 1 tower registered on MahaRERA, and 79% of them are sold or booked.
When was Prime Opal registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Prime Opal was registered on MahaRERA on 24 January 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on Prime Opal?
No court cases are listed for Prime Opal on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Prime Opal?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Prime Abhishek Buildcon, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Prime Opal
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Raigad →
Other projects in Panvel
- PRAKASH TOWER
- SAI SIDDHI MADHUBAN
- Sai Nilay
- Shivesh Mahavir
- Crystal Co-Operative Housing Society Limited
- Indiabulls Park 2
- Indiabulls Park 1
- Indiabulls Park 4
Other projects by Prime Abhishek Buildcon
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.