MITHILA ICON
by N R BUILDERS AND DEVELOEPRS · Roha, Raigarh
Possession date of MITHILA ICON: 31 March 2027, moved from 31 March 2024 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000047982, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about MITHILA ICON?
How the possession date of MITHILA ICON has moved
31 March 2024
Completion date given when the project was registered
31 March 2025
Extended at the builder's request (MahaRERA application EXT52000019429)
Reason the builder gave MahaRERA:
“Our Project site is located at village Varse which is a remote developing area where Roads and infrastructure is still being developed and there is also persistent transportation issues. As there is no proper Road and Infrastructure it was…” Read the full reason
“Our Project site is located at village Varse which is a remote developing area where Roads and infrastructure is still being developed and there is also persistent transportation issues. As there is no proper Road and Infrastructure it was difficult for us to arrange raw materials and man power upto the project location. Due to inadequate material and manpower we could not complete our construction work within in the planned period declared in the Form-B.”31 March 2026
Extended at the builder's request (MahaRERA application EA21072502116)
Reason the builder gave MahaRERA:
“Our Project site is located at village Varse which is a remote developing area where Roads and infrastructure is still being developed and there is also persistent transportation issues. As there is no proper Road and Infrastructure it was…” Read the full reason
“Our Project site is located at village Varse which is a remote developing area where Roads and infrastructure is still being developed and there is also persistent transportation issues. As there is no proper Road and Infrastructure it was difficult for us to arrange raw materials and man power upto the project location. Due to inadequate material and manpower we could not complete our construction work within in the planned period declared in the Form-B.”31 March 2027
Extended at the builder's request (MahaRERA application EA04052620828)
Reason the builder gave MahaRERA:
“Our Project site is located at village Varse which is a remote developing area where Roads and infrastructure is still being developed and there is also persistent transportation issues. As there is no proper Road and Infrastructure it was…” Read the full reason
“Our Project site is located at village Varse which is a remote developing area where Roads and infrastructure is still being developed and there is also persistent transportation issues. As there is no proper Road and Infrastructure it was difficult for us to arrange raw materials and man power upto the project location. Due to inadequate material and manpower we could not complete our construction work within in the planned period declared in the Form-B.”
Source: MITHILA ICON’s extension records on MahaRERA (P52000047982), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on MITHILA ICON
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the March 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000047982
- Status
- Registered and active
- Builder
- N R BUILDERS AND DEVELOEPRS
- Location
- Roha, Raigarh · 402109
- Project type
- Residential / Group Housing
- Registered on
- 2 Dec 2022
- Completion date at registration
- March 2024
- Latest completion date
- March 2027
- Delay so far
- 36 months
- Homes
- 36
- Sold or booked
- 65%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of MITHILA ICON, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| MITHILA ICON | 100% | 100% | 95% | 80% |
Commencement certificate (CC), as filed on MahaRERA
- MITHILA ICON: covers 7 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on MITHILA ICON every month.
MITHILA ICON: buildings, flats and land, as filed on MahaRERA
- Buildings: MITHILA ICON (8 floors, 40 units)
- Land: 700 sq m (about 0.2 acres) · sanctioned built-up 1,568 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of MITHILA ICON →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
MITHILA ICON: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MITHILA ICON
What is the possession date of MITHILA ICON?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for MITHILA ICON in Roha, Raigarh is 31 March 2027 — 36 months later than 31 March 2024, the date given at registration.
Is the builder's possession date different from the MahaRERA date for MITHILA ICON?
Builders and listing sites often quote an earlier "target" date for handover. The completion date MITHILA ICON's builder has filed on MahaRERA, the official one, is 31 March 2027, already 36 months later than the 31 March 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of MITHILA ICON extended?
According to GharKundli's check of MahaRERA records (updated October 2026), MITHILA ICON's builder applied to MahaRERA to extend the completion date 3 times: to 31 March 2025, giving the reason "Our Project site is located at village Varse which is a remote developing area where Roads and infrastructure is still being developed and there is also persistent transportation issues. As there is no proper Road and Infrastructure it was difficult for us to arrange raw materials and man power upto the project location. Due to inadequate material and manpower we could not complete our construction work within in the planned period declared in the Form-B."; to 31 March 2026, giving the reason "Our Project site is located at village Varse which is a remote developing area where Roads and infrastructure is still being developed and there is also persistent transportation issues. As there is no proper Road and Infrastructure it was difficult for us to arrange raw materials and man power upto the project location. Due to inadequate material and manpower we could not complete our construction work within in the planned period declared in the Form-B."; to 31 March 2027, giving the reason "Our Project site is located at village Varse which is a remote developing area where Roads and infrastructure is still being developed and there is also persistent transportation issues. As there is no proper Road and Infrastructure it was difficult for us to arrange raw materials and man power upto the project location. Due to inadequate material and manpower we could not complete our construction work within in the planned period declared in the Form-B.".
What is the RERA number of MITHILA ICON?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of MITHILA ICON in Roha, Raigarh is P52000047982.
Is MITHILA ICON registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MITHILA ICON is registered as P52000047982 and its status is "Registered and active".
What is the construction status of MITHILA ICON?
According to GharKundli's check of MahaRERA records (updated October 2026), MITHILA ICON's status on MahaRERA is "Registered and active". As filed by the builder, slab work on MITHILA ICON is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does MITHILA ICON have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is MITHILA ICON safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), MITHILA ICON is registered on MahaRERA as P52000047982, its completion date has moved 36 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if MITHILA ICON's possession date changes?
The latest dates are on MITHILA ICON's MahaRERA page (P52000047982). GharKundli's Kundli Watch sends a free WhatsApp update on MITHILA ICON every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does MITHILA ICON have?
According to GharKundli's check of MahaRERA records (updated October 2026), MITHILA ICON has one building filed: MITHILA ICON with 8 floors and 40 units.
How big is the land of MITHILA ICON?
According to GharKundli's check of MahaRERA records (updated October 2026), MITHILA ICON stands on 700 sq m of land (about 0.2 acres), with 1,568 sq m of sanctioned built-up area.
Where can I read reviews of MITHILA ICON?
Google Maps has reviews of MITHILA ICON written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is MITHILA ICON?
MITHILA ICON by N R BUILDERS AND DEVELOEPRS is in Roha, Raigarh (pincode 402109), Maharashtra, and is registered on MahaRERA as P52000047982, per GharKundli's check of MahaRERA records.
How many homes are in MITHILA ICON?
According to GharKundli's check of MahaRERA records (updated October 2026), MITHILA ICON has 36 homes in 1 tower registered on MahaRERA, and 65% of them are sold or booked.
When was MITHILA ICON registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), MITHILA ICON was registered on MahaRERA on 2 December 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on MITHILA ICON?
No court cases are listed for MITHILA ICON on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of MITHILA ICON?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is N R BUILDERS AND DEVELOEPRS.
Check it yourself on MahaRERA
- How to check the possession date of MITHILA ICON
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Raigad →
Other projects in pincode 402109
- AK PLATINUM TOWER
- Abhinandan Farms
- RAMESHWARI APARTMENT
- Chandradarshan Enclave Phase II
- SHREE DATTA NARAYAN APARTMENT
- Nooraji Complex
- Vardhaman Apartment Wing B
- ANKIT FIONA PHASE 2
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.