by RAJGURU DEVELOPERS PRIVATE LIMITED · Mulund West, MumbaiAlso near Mulund East, Bhandup West, Chembur West

Possession date of RAJ ALTEZZA: 31 July 2024, moved from 31 December 2019 (55 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800007125. Status: Lapsed (registration period ended). 13 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (July 2024) has passed.

What do you want to know about RAJ ALTEZZA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of RAJ ALTEZZA has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 December 2020

    Extended at the builder's request (MahaRERA application EXT51800003852)

    Reason the builder gave MahaRERA:
    “1. Majority of our customers were seeking 98% Home Loan Finance. Loans were sanctioned & / or under process for sanction majorly by NBFC’s i.e. Indiabulls, DHFL etc. Since Sept-2018 there has been a liquidity crunch at these NBFC’s hence th…” Read the full reason“1. Majority of our customers were seeking 98% Home Loan Finance. Loans were sanctioned & / or under process for sanction majorly by NBFC’s i.e. Indiabulls, DHFL etc. Since Sept-2018 there has been a liquidity crunch at these NBFC’s hence they are not able to disburse funds which in turn affected our construction progress leading to a virtual halt in construction activities. Further to add to woes: a) Institutions which were earlier funding upto 98% put a cap on funding of upto 90%. This lead to delays in receipt of payments as customers had to make alternate arrangements for the increase in…”
  3. 31 July 2024

    Extended at the builder's request (MahaRERA application EXT51800019051)

    Reason the builder gave MahaRERA:
    “1) In view of COVID-19 pandemic and consequent nation-wide lockdown with effect from March, 2020, reverse migration of labourers to their native places and caused break in supply chain of construction material, the construction activities o…” Read the full reason“1) In view of COVID-19 pandemic and consequent nation-wide lockdown with effect from March, 2020, reverse migration of labourers to their native places and caused break in supply chain of construction material, the construction activities of real estate projects across the country which severely detrimentally impacted all project across the nation and specifically in Mumbai. 2) Eventually, after struggling to find labourers due to the reverse migration attributable to COVID-19. The construction work began, though slowly due to the restrictions imposed in the city of Mumbai. There was imposi…”

Source: RAJ ALTEZZA’s extension records on MahaRERA (P51800007125), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on RAJ ALTEZZA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 13 complaints, and how it ended
  • Construction pace against the July 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800007125
Status
Lapsed (registration period ended)
Builder
RAJGURU DEVELOPERS PRIVATE LIMITED
Location
Mulund West, Mumbai · 400080
Project type
Residential / Group Housing
Registered on
17 Aug 2017
Completion date at registration
December 2019
Latest completion date
July 2024
Delay so far
55 months
Homes
150
Towers
1
Complaints on MahaRERA
13
Court cases listed
0
Appeals at the tribunal
3
Title report on file
Not found

Construction progress of RAJ ALTEZZA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
RAJ ALTEZZA83%83%26%2%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on RAJ ALTEZZA every month.

RAJ ALTEZZA: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of RAJ ALTEZZA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

RAJ ALTEZZA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about RAJ ALTEZZA

What is the possession date of RAJ ALTEZZA?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for RAJ ALTEZZA in Mulund West, Mumbai is 31 July 2024 — 55 months later than 31 December 2019, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for RAJ ALTEZZA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date RAJ ALTEZZA's builder has filed on MahaRERA, the official one, is 31 July 2024, already 55 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of RAJ ALTEZZA extended?

According to GharKundli's check of MahaRERA records (updated October 2026), RAJ ALTEZZA's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2020, giving the reason "1. Majority of our customers were seeking 98% Home Loan Finance. Loans were sanctioned & / or under process for sanction majorly by NBFC’s i.e. Indiabulls, DHFL etc. Since Sept-2018 there has been a liquidity crunch at these NBFC’s hence they are not able to disburse funds which in turn affected our construction progress leading to a virtual halt in construction activities. Further to add to woes: a) Institutions which were earlier funding upto 98% put a cap on funding of upto 90%. This lead to delays in receipt of payments as customers had to make alternate arrangements for the increase in…"; to 31 July 2024, giving the reason "1) In view of COVID-19 pandemic and consequent nation-wide lockdown with effect from March, 2020, reverse migration of labourers to their native places and caused break in supply chain of construction material, the construction activities of real estate projects across the country which severely detrimentally impacted all project across the nation and specifically in Mumbai. 2) Eventually, after struggling to find labourers due to the reverse migration attributable to COVID-19. The construction work began, though slowly due to the restrictions imposed in the city of Mumbai. There was imposi…".

What is the RERA number of RAJ ALTEZZA?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of RAJ ALTEZZA in Mulund West, Mumbai is P51800007125.

Is RAJ ALTEZZA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), RAJ ALTEZZA is registered as P51800007125 and its status is "Lapsed (registration period ended)". On MahaRERA's own list: On MahaRERA's insolvency (NCLT) list. MahaRERA lists this project among those before the National Company Law Tribunal (NCLT), the insolvency court. Its list shows no completion certificate (Form 4) uploaded. Ask the builder, in writing, about the case before paying anything.

What is the construction status of RAJ ALTEZZA?

According to GharKundli's check of MahaRERA records (updated October 2026), RAJ ALTEZZA's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on RAJ ALTEZZA is 83% done and internal work 26%. GharKundli's full report compares construction progress with the deadline.

Does RAJ ALTEZZA have complaints on MahaRERA?

13 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is RAJ ALTEZZA safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), RAJ ALTEZZA is registered on MahaRERA as P51800007125, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 55 months since registration, 13 complaints are listed against it and it is on MahaRERA's list "On MahaRERA's insolvency (NCLT) list". GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if RAJ ALTEZZA's possession date changes?

The latest dates are on RAJ ALTEZZA's MahaRERA page (P51800007125). GharKundli's Kundli Watch sends a free WhatsApp update on RAJ ALTEZZA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does RAJ ALTEZZA have?

According to GharKundli's check of MahaRERA records (updated October 2026), RAJ ALTEZZA has one building filed: RAJ ALTEZZA with 33 floors.

How big is the land of RAJ ALTEZZA?

According to GharKundli's check of MahaRERA records (updated October 2026), RAJ ALTEZZA stands on 3,010 sq m of land (about 0.7 acres), with 8,393 sq m of sanctioned built-up area.

Where can I read reviews of RAJ ALTEZZA?

Google Maps has reviews of RAJ ALTEZZA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 13 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is RAJ ALTEZZA?

RAJ ALTEZZA by RAJGURU DEVELOPERS PRIVATE LIMITED is in Mulund West, Mumbai (pincode 400080), near Mulund East, Bhandup West, Chembur West, Maharashtra, and is registered on MahaRERA as P51800007125, per GharKundli's check of MahaRERA records. Its boundaries filed there include CENTRAL RAILWAY.

How many homes are in RAJ ALTEZZA?

According to GharKundli's check of MahaRERA records (updated October 2026), RAJ ALTEZZA has 150 homes in 1 tower registered on MahaRERA.

When was RAJ ALTEZZA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), RAJ ALTEZZA was registered on MahaRERA on 17 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on RAJ ALTEZZA?

No court cases are listed for RAJ ALTEZZA on MahaRERA, and 3 appeals at the tribunal, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of RAJ ALTEZZA?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is RAJGURU DEVELOPERS PRIVATE LIMITED.

Other projects in pincode 400080

All 303 projects in Mulund West (400080) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.