Bhalla CHSL Jupiter - Venus
by Chetna Global · Kurla, MumbaiAlso near Mulund West, Sion, Off Dmart
Possession date of Bhalla CHSL Jupiter - Venus: 30 April 2027, moved from 31 December 2019 (84 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800000906, and currently active. Its completion date has moved from December 2019 to April 2027: 84 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Bhalla CHSL Jupiter - Venus?
How the possession date of Bhalla CHSL Jupiter - Venus has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT51800005677)
Reason the builder gave MahaRERA: “WE REQUEST TO EXTEND OUR COMPLETION DATE TO 30TH DEC 2020”
30 March 2023
Extended at the builder's request (MahaRERA application EXT51800012236)
Reason the builder gave MahaRERA: “covid - 19”
31 December 2024
Extended at the builder's request (MahaRERA application EXT51800017483)
Reason the builder gave MahaRERA: “The project was delayed for reasons beyond our control on account of various unforeseen events.”
31 December 2025
Extended at the builder's request (MahaRERA application EXT51800027664)
Reason the builder gave MahaRERA:
“The primary reason for the delay is the underperformance of the appointed contractor, M/s. Nirvana Home Realty Elite LLP. Despite our repeated efforts to address performance issues, the contractor was unable to allocate sufficient resources…” Read the full reason
“The primary reason for the delay is the underperformance of the appointed contractor, M/s. Nirvana Home Realty Elite LLP. Despite our repeated efforts to address performance issues, the contractor was unable to allocate sufficient resources, including labour and materials, to ensure the timely completion of the work. As a result, there were significant delays in the construction process. After repeated warnings and discussions, it became evident that the contractor was not in a position to meet the project requirements. Consequently, we made the decision to terminate the contract with M/s.…”31 December 2026
Extended at the builder's request (MahaRERA application EA12052620906)
Reason the builder gave MahaRERA:
“The project has been substantially completed; however, the Occupation Certificate (OC) is pending due to administrative delays beyond the Promoter’s control despite timely submission of all required documents and continuous follow-up with t…” Read the full reason
“The project has been substantially completed; however, the Occupation Certificate (OC) is pending due to administrative delays beyond the Promoter’s control despite timely submission of all required documents and continuous follow-up with the authorities. Hence, we request the Authority to kindly grant an extension of the project registration till 31/12/2026 for obtaining the OC and completing the statutory compliances.”30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Bhalla CHSL Jupiter - Venus’s extension records on MahaRERA (P51800000906), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Bhalla CHSL Jupiter - Venus
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800000906
- Status
- Registered and active
- Builder
- Chetna Global
- Location
- Kurla, Mumbai · 400080
- Project type
- Residential / Group Housing
- Registered on
- 25 Jul 2017
- Completion date at registration
- December 2019
- Latest completion date
- April 2027
- Delay so far
- 84 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 52
- Sold or booked
- 96%
- Towers
- 2
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Bhalla CHSL Jupiter - Venus, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Jupiter | 100% | 100% | 95% | 10% |
| Venus B Wing | 100% | 100% | 53% | 10% |
Commencement certificate (CC), as filed on MahaRERA
- Jupiter: covers 18 floors
- Venus B Wing: covers 17 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Bhalla CHSL Jupiter - Venus every month.
Bhalla CHSL Jupiter - Venus: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 496 – 763 | 25 |
| 3 BHK | 915 – 1,126 | 15 |
| 4 BHK | 1,302 – 1,400 | 12 |
| Shops | 540 – 605 | 2 |
- Buildings: Jupiter (22 floors, 29 units) · Venus B Wing (21 floors, 25 units)
- Land: 1,617 sq m (about 0.4 acres) · sanctioned built-up 3,783 sq m
- Boundaries filed include: Lala Devidayal Road, Layout Road, Meghal Industrial Estate
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Chetana Enterprises - NX (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 78 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of Bhalla CHSL Jupiter - Venus →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Bhalla CHSL Jupiter - Venus: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Bhalla CHSL Jupiter - Venus
What is the possession date of Bhalla CHSL Jupiter - Venus?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Bhalla CHSL Jupiter - Venus in Kurla, Mumbai is 30 April 2027 — 84 months later than 31 December 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Bhalla CHSL Jupiter - Venus?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Bhalla CHSL Jupiter - Venus's builder has filed on MahaRERA, the official one, is 30 April 2027, already 84 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Bhalla CHSL Jupiter - Venus extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhalla CHSL Jupiter - Venus's builder applied to MahaRERA to extend the completion date 5 times: to 30 December 2020, giving the reason "WE REQUEST TO EXTEND OUR COMPLETION DATE TO 30TH DEC 2020"; to 30 March 2023, giving the reason "covid - 19"; to 31 December 2024, giving the reason "The project was delayed for reasons beyond our control on account of various unforeseen events."; to 31 December 2025, giving the reason "The primary reason for the delay is the underperformance of the appointed contractor, M/s. Nirvana Home Realty Elite LLP. Despite our repeated efforts to address performance issues, the contractor was unable to allocate sufficient resources, including labour and materials, to ensure the timely completion of the work. As a result, there were significant delays in the construction process. After repeated warnings and discussions, it became evident that the contractor was not in a position to meet the project requirements. Consequently, we made the decision to terminate the contract with M/s.…"; to 31 December 2026, giving the reason "The project has been substantially completed; however, the Occupation Certificate (OC) is pending due to administrative delays beyond the Promoter’s control despite timely submission of all required documents and continuous follow-up with the authorities. Hence, we request the Authority to kindly grant an extension of the project registration till 31/12/2026 for obtaining the OC and completing the statutory compliances.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Bhalla CHSL Jupiter - Venus?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Bhalla CHSL Jupiter - Venus in Kurla, Mumbai is P51800000906.
Is Bhalla CHSL Jupiter - Venus registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhalla CHSL Jupiter - Venus is registered as P51800000906 and its status is "Registered and active".
What is the construction status of Bhalla CHSL Jupiter - Venus?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhalla CHSL Jupiter - Venus's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Bhalla CHSL Jupiter - Venus have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Bhalla CHSL Jupiter - Venus safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhalla CHSL Jupiter - Venus is registered on MahaRERA as P51800000906, its completion date has moved 84 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Bhalla CHSL Jupiter - Venus's possession date changes?
The latest dates are on Bhalla CHSL Jupiter - Venus's MahaRERA page (P51800000906). GharKundli's Kundli Watch sends a free WhatsApp update on Bhalla CHSL Jupiter - Venus every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Bhalla CHSL Jupiter - Venus have?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhalla CHSL Jupiter - Venus has 2 buildings filed: Jupiter with 22 floors and 29 units; Venus B Wing with 21 floors and 25 units.
What are the flat sizes (carpet area) in Bhalla CHSL Jupiter - Venus?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Bhalla CHSL Jupiter - Venus: 2 BHK: 496 to 763 sq ft carpet (25 homes); 3 BHK: 915 to 1126 sq ft carpet (15 homes); 4 BHK: 1302 to 1400 sq ft carpet (12 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How big is the land of Bhalla CHSL Jupiter - Venus?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhalla CHSL Jupiter - Venus stands on 1,617 sq m of land (about 0.4 acres), with 3,783 sq m of sanctioned built-up area.
What is the track record of Bhalla CHSL Jupiter - Venus's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Chetana Enterprises - NX (a group of 2 linked companies) has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 still being built, 1 past the promised date (typically 78 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Bhalla CHSL Jupiter - Venus?
Google Maps has reviews of Bhalla CHSL Jupiter - Venus written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Bhalla CHSL Jupiter - Venus?
Bhalla CHSL Jupiter - Venus by Chetna Global is in Kurla, Mumbai (pincode 400080), near Mulund West, Sion, Off Dmart, Maharashtra, and is registered on MahaRERA as P51800000906, per GharKundli's check of MahaRERA records. Its boundaries filed there include Lala Devidayal Road, Layout Road, Meghal Industrial Estate.
How many homes are in Bhalla CHSL Jupiter - Venus?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhalla CHSL Jupiter - Venus has 52 homes in 2 towers registered on MahaRERA, and 96% of them are sold or booked.
When was Bhalla CHSL Jupiter - Venus registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Bhalla CHSL Jupiter - Venus was registered on MahaRERA on 25 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Bhalla CHSL Jupiter - Venus?
No court cases are listed for Bhalla CHSL Jupiter - Venus on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Bhalla CHSL Jupiter - Venus?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Chetna Global.
Check it yourself on MahaRERA
- How to check the possession date of Bhalla CHSL Jupiter - Venus
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Mumbai Suburban →
Other projects in Kurla
- Kalyan Kutir Co-operative Housing Society Limited
- AMBARISH CHS LTD
- UNITED ELICAS
- ANUPAM VILLA CHSL
- SANJARY APARTMENTS
- Kohinoor City Residential Phase 2 Block 2
- ICONIC RESIDENCY
- ELITE BLISS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.