What’s in the report? →

Possession date of Iconic Residency (MahaRERA P51800020830): 31 July 2026, moved from 30 March 2024 (24 months later), and it has already passed. It has 66 homes (1 BHK, 2 BHK and 3 BHK, 354–866 sq ft carpet), 76% sold or booked. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800020830. Status: Lapsed (registration period ended). Its completion date has moved from March 2024 to July 2026: 24 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: MahaRERA website — records for P51800020830, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

The latest completion date on MahaRERA (July 2026) has passed.

What do you want to know about Iconic Residency?

Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Iconic Residency has moved

  1. 30 March 2024

    Completion date given when the project was registered

  2. 29 March 2025

    Extended at the builder's request (MahaRERA application EXT51800017463)

    Reason the builder gave MahaRERA: “As per attachment”
  3. 31 March 2026

    Extended at the builder's request (MahaRERA application EA07102518056)

    Reason the builder gave MahaRERA:
    “5. The reason for the delay is pace of sales being lower than expected and thereby affecting the cash flows of the project. Lower than expected cash flows has in turn affected the pace of construction of the project thereby making it imposs…” Read the full reason“5. The reason for the delay is pace of sales being lower than expected and thereby affecting the cash flows of the project. Lower than expected cash flows has in turn affected the pace of construction of the project thereby making it impossible to meet the scheduled due date 29/03/2025. 6. Due to low pace of sale in the project, the applicant landed into the financial difficulties which spiraled the event of stoppage of construction work at the construction site. 7. We say that we have deployed dedicated competent and experienced sales team which is putting their best efforts to speed up th…”
  4. 31 July 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Iconic Residency’s extension records on MahaRERA (P51800020830), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Iconic Residency

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800020830
Status
Lapsed (registration period ended)
Builder
S K HOUSING
Location
Kurla, Mumbai · 400070
Project type
Residential / Group Housing
Registered on
15 May 2019
Completion date at registration
March 2024
Latest completion date
July 2026
Delay so far
24 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
66
Sold or booked
76%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Iconic Residency, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ICONIC RESIDENCY100%92%92%65%

Commencement certificate (CC), as filed on MahaRERA

  • ICONIC RESIDENCY: covers 16 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Iconic Residency every 1–2 months.

Iconic Residency: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
3 BHK828 – 86628
2 BHK354 – 75327
1 BHK35411
Shops196 – 4286
Office Space131 – 5702
  • Buildings: ICONIC RESIDENCY (16 floors, 74 units)
  • Land: 1,574 sq m (about 0.4 acres) · sanctioned built-up 1,305 sq m
  • Boundaries filed include: New Agra Road
  • Land, as filed: CTS NO. 27B PART
  • Map: Get directions

The builder’s record and reviews

S K Construction (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 lapsed. No complaints on MahaRERA.

Read Google reviews of Iconic Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Iconic Residency: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Iconic Residency

What is the possession date of Iconic Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Iconic Residency in Kurla, Mumbai is 31 July 2026 — 24 months later than 30 March 2024, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

The date has already moved 24 months. Will it move again? Check the real pace of construction →

Is the builder's possession date different from the MahaRERA date for Iconic Residency?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Iconic Residency's builder has filed on MahaRERA, the official one, is 31 July 2026, already 24 months later than the 30 March 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Iconic Residency extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Iconic Residency's builder applied to MahaRERA to extend the completion date 2 times: to 29 March 2025, giving the reason "As per attachment"; to 31 March 2026, giving the reason "5. The reason for the delay is pace of sales being lower than expected and thereby affecting the cash flows of the project. Lower than expected cash flows has in turn affected the pace of construction of the project thereby making it impossible to meet the scheduled due date 29/03/2025. 6. Due to low pace of sale in the project, the applicant landed into the financial difficulties which spiraled the event of stoppage of construction work at the construction site. 7. We say that we have deployed dedicated competent and experienced sales team which is putting their best efforts to speed up th…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Iconic Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Iconic Residency in Kurla, Mumbai is P51800020830.

Is Iconic Residency registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Iconic Residency is registered as P51800020830 and its status is "Lapsed (registration period ended)".

What is the current construction status of Iconic Residency? How much work is done?

According to GharKundli's check of MahaRERA records (updated October 2026), Iconic Residency's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on ICONIC RESIDENCY is 92% done and internal work 92%. GharKundli's full report compares construction progress with the deadline.

Does Iconic Residency have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Iconic Residency safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Iconic Residency is registered on MahaRERA as P51800020830, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Iconic Residency?

Iconic Residency isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 60 sq m (about 646 sq ft) in the Mumbai region, and price up to ₹45 lakh. Some flats in Iconic Residency are 354 sq ft carpet, small enough for 1% if the price is ₹45 lakh or less. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.

What is the stamp duty and registration cost for a flat in Iconic Residency?

For a flat in Iconic Residency (Mumbai), stamp duty is 6% of the agreement value, or of the ready reckoner value if that's higher, including 1% Metro Cess. A woman buying in her own name pays 5%. Registration is 1% of the value, capped at ₹30,000. On a ₹1 crore flat that's about ₹6 lakh in stamp duty plus ₹30,000 registration. GharKundli's property cost calculator works it out for your price: gharkundli.com/tools/property-cost-calculator

Has Iconic Residency received its OC? Is it ready to move in?

Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Iconic Residency isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 July 2026 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.

What does "lapsed" mean for Iconic Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), Iconic Residency's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 July 2026) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.

Is Iconic Residency a redevelopment or SRA project?

According to GharKundli's check of MahaRERA records (updated October 2026), Iconic Residency is a redevelopment: 32 of its flats are set aside for existing occupants (rehab), and the rest are for sale.

Has Iconic Residency uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Iconic Residency was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Iconic Residency's possession date changes?

The latest dates are on Iconic Residency's MahaRERA page (P51800020830). GharKundli's Kundli Watch sends a free WhatsApp update on Iconic Residency every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Iconic Residency have?

According to GharKundli's check of MahaRERA records (updated October 2026), Iconic Residency has one building filed: ICONIC RESIDENCY with 16 floors and 74 units.

What are the flat sizes (carpet area) in Iconic Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for Iconic Residency: 3 BHK: 828 to 866 sq ft carpet (28 homes); 2 BHK: 354 to 753 sq ft carpet (27 homes); 1 BHK: 354 sq ft carpet (11 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of Iconic Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), Iconic Residency stands on 1,574 sq m of land (about 0.4 acres), with 1,305 sq m of sanctioned built-up area.

What is the track record of Iconic Residency's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), S K Construction (a group of 3 linked companies) has 3 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 finished, all within the promised date; 2 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Iconic Residency?

Google Maps has reviews of Iconic Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Iconic Residency?

Iconic Residency by S K HOUSING is in Kurla, Mumbai, pincode 400070 (near Nehru Nagar, Vidyanagari), Maharashtra, and is registered on MahaRERA as P51800020830, per GharKundli's check of MahaRERA records. Its boundaries filed there include New Agra Road. Its land is filed as CTS NO. 27B PART. GharKundli lists all 92 MahaRERA projects in Kurla West (400070).

How many flats are in Iconic Residency, and how many are sold?

According to GharKundli's check of MahaRERA records (updated October 2026), Iconic Residency has 66 homes in 1 tower registered on MahaRERA, and 76% of them are sold or booked.

When was Iconic Residency registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Iconic Residency was registered on MahaRERA on 15 May 2019. GharKundli did not find a title report on the land on file there.

Does Iconic Residency have any legal issues or court cases?

No court cases are listed for Iconic Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder / developer of Iconic Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is S K HOUSING.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in Kurla West (400070)

All 92 projects in Kurla West (400070) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.