Nirvana Bougainvilla
by Kishor Otarmal Jain · Usale, Raigarh
Possession date of Nirvana Bougainvilla: 31 December 2027, moved from 31 December 2025 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000050750, and currently active. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Nirvana Bougainvilla?
How the possession date of Nirvana Bougainvilla has moved
31 December 2025
Completion date given when the project was registered
31 December 2027
Extended at the builder's request (MahaRERA application EA08042620583)
Reason the builder gave MahaRERA: “The delay was due to a shortage of manpower and insufficient financial resources.”
Source: Nirvana Bougainvilla’s extension records on MahaRERA (P52000050750), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Nirvana Bougainvilla
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the December 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000050750
- Status
- Registered and active
- Builder
- Kishor Otarmal Jain
- Location
- Usale, Raigarh · 410205
- Project type
- Plotted
- Registered on
- 28 Apr 2023
- Completion date at registration
- December 2025
- Latest completion date
- December 2027
- Delay so far
- 24 months
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Title report on file
- Not found
Nirvana Bougainvilla: buildings, flats and land, as filed on MahaRERA
- Land: 12,129 sq m (about 3.0 acres) · sanctioned built-up 12,129 sq m · recreational space 4,390 sq m
The builder’s record and reviews
Kishor Otermal Jain has 4 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 still being built, 1 past the promised date (typically 10 months late); 2 lapsed. 6 complaints on MahaRERA across 2 projects.
Read Google reviews of Nirvana Bougainvilla →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Nirvana Bougainvilla: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Nirvana Bougainvilla
What is the possession date of Nirvana Bougainvilla?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Nirvana Bougainvilla in Usale, Raigarh is 31 December 2027 — 24 months later than 31 December 2025, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Nirvana Bougainvilla?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Nirvana Bougainvilla's builder has filed on MahaRERA, the official one, is 31 December 2027, already 24 months later than the 31 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Nirvana Bougainvilla extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Nirvana Bougainvilla's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "The delay was due to a shortage of manpower and insufficient financial resources.".
What is the RERA number of Nirvana Bougainvilla?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Nirvana Bougainvilla in Usale, Raigarh is P52000050750.
Is Nirvana Bougainvilla registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Nirvana Bougainvilla is registered as P52000050750 and its status is "Registered and active".
What is the construction status of Nirvana Bougainvilla?
According to GharKundli's check of MahaRERA records (updated October 2026), Nirvana Bougainvilla's status on MahaRERA is "Registered and active". GharKundli's full report compares construction progress with the deadline.
Does Nirvana Bougainvilla have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Nirvana Bougainvilla safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Nirvana Bougainvilla is registered on MahaRERA as P52000050750, its completion date has moved 24 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Nirvana Bougainvilla's possession date changes?
The latest dates are on Nirvana Bougainvilla's MahaRERA page (P52000050750). GharKundli's Kundli Watch sends a free WhatsApp update on Nirvana Bougainvilla every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How big is the land of Nirvana Bougainvilla?
According to GharKundli's check of MahaRERA records (updated October 2026), Nirvana Bougainvilla stands on 12,129 sq m of land (about 3.0 acres), with 12,129 sq m of sanctioned built-up area and 4,390 sq m of recreational open space.
What is the track record of Nirvana Bougainvilla's builder?
According to GharKundli's check of MahaRERA records (updated October 2026), Kishor Otermal Jain has 4 projects on MahaRERA since 2017, this one included. Of the 3 GharKundli has checked: 1 still being built, 1 past the promised date (typically 10 months late); 2 lapsed. 6 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Nirvana Bougainvilla?
Google Maps has reviews of Nirvana Bougainvilla written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Nirvana Bougainvilla?
Nirvana Bougainvilla by Kishor Otarmal Jain is in Usale, Raigarh (pincode 410205), Maharashtra, and is registered on MahaRERA as P52000050750, per GharKundli's check of MahaRERA records.
When was Nirvana Bougainvilla registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Nirvana Bougainvilla was registered on MahaRERA on 28 April 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on Nirvana Bougainvilla?
No court cases are listed for Nirvana Bougainvilla on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Nirvana Bougainvilla?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Kishor Otarmal Jain.
Check it yourself on MahaRERA
- How to check the possession date of Nirvana Bougainvilla
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Raigad →
Other projects in Sudhagad
- City Of Music Phase I
- City Of Music Phase III
- SHUBHAM RESIDENCY
- Pali Hills Phase III
- Pali Hill City Phase II
- RE CASA
- TECTONA HILLS
- City Of Music Phase II
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.