SAUBHAGYAM
by TODAY GLOBAL PROPERTIES (Jindal) · Ongc Complexpanvel, RaigarhAlso near Kamboi
Possession date of SAUBHAGYAM: 30 April 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000053782, and currently active. Its completion date is now April 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SAUBHAGYAM?
How the possession date of SAUBHAGYAM has moved
31 December 2028
Completion date given when the project was registered
30 April 2029
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: SAUBHAGYAM’s extension records on MahaRERA (P52000053782), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SAUBHAGYAM
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the April 2029 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- SAUBHAGYAM PHASE IIP52000077460 · possession 30 Jan 2030
- MahaRERA registration
- P52000053782
- Status
- Registered and active
- Builder
- TODAY GLOBAL PROPERTIES
- Location
- Ongc Complexpanvel, Raigarh · 410221
- Project type
- Others
- Registered on
- 28 Nov 2023
- Completion date at registration
- December 2028
- Latest completion date
- April 2029
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 205
- Sold or booked
- 85%
- Towers
- 1
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of SAUBHAGYAM, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SAUBHAGYAM | 100% | 92% | 70% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- SAUBHAGYAM: covers 15 floors
Latest CC order on MahaRERA: dated 22/06/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SAUBHAGYAM every month.
SAUBHAGYAM: buildings, flats and land, as filed on MahaRERA
- Buildings: SAUBHAGYAM (15 floors, 206 units)
- Land: 7,143 sq m (about 1.8 acres) · sanctioned built-up 9,657 sq m · recreational space 706 sq m
The builder’s record and reviews
Today Global Homes (a group of 18 linked companies) has 40 projects on MahaRERA since 2017, this one included. Of the 40 GharKundli has checked: 18 finished, 13 within the promised date and 5 needed more time (typically 6 months); 20 still being built, 2 past the promised date (typically 6 months late); 2 lapsed. 50 complaints on MahaRERA across 10 projects.
Read Google reviews of SAUBHAGYAM →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SAUBHAGYAM: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SAUBHAGYAM
What is the possession date of SAUBHAGYAM?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SAUBHAGYAM in Ongc Complexpanvel, Raigarh is 30 April 2029, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for SAUBHAGYAM?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SAUBHAGYAM's builder has filed on MahaRERA, the official one, is 30 April 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of SAUBHAGYAM?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SAUBHAGYAM in Ongc Complexpanvel, Raigarh is P52000053782.
Is SAUBHAGYAM registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SAUBHAGYAM is registered as P52000053782 and its status is "Registered and active".
What is the construction status of SAUBHAGYAM?
According to GharKundli's check of MahaRERA records (updated November 2026), SAUBHAGYAM's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SAUBHAGYAM is 92% done and internal work 70%. GharKundli's full report compares construction progress with the deadline.
Does SAUBHAGYAM have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is SAUBHAGYAM safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SAUBHAGYAM is registered on MahaRERA as P52000053782, its completion date has not been moved by the builder and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does SAUBHAGYAM have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: SAUBHAGYAM PHASE II (P52000077460, possession 30 Jan 2030). Check that your agreement names the registration of your own wing.
How can I get updates if SAUBHAGYAM's possession date changes?
The latest dates are on SAUBHAGYAM's MahaRERA page (P52000053782). GharKundli's Kundli Watch sends a free WhatsApp update on SAUBHAGYAM every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SAUBHAGYAM have?
According to GharKundli's check of MahaRERA records (updated November 2026), SAUBHAGYAM has one building filed: SAUBHAGYAM with 15 floors and 206 units.
How big is the land of SAUBHAGYAM?
According to GharKundli's check of MahaRERA records (updated November 2026), SAUBHAGYAM stands on 7,143 sq m of land (about 1.8 acres), with 9,657 sq m of sanctioned built-up area and 706 sq m of recreational open space.
What is the track record of SAUBHAGYAM's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Today Global Homes (a group of 18 linked companies) has 40 projects on MahaRERA since 2017, this one included. Of the 40 GharKundli has checked: 18 finished, 13 within the promised date and 5 needed more time (typically 6 months); 20 still being built, 2 past the promised date (typically 6 months late); 2 lapsed. 50 complaints on MahaRERA across 10 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SAUBHAGYAM?
Google Maps has reviews of SAUBHAGYAM written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SAUBHAGYAM?
SAUBHAGYAM by TODAY GLOBAL PROPERTIES (Jindal) is in Ongc Complexpanvel, Raigarh (pincode 410221), near Kamboi, Maharashtra, and is registered on MahaRERA as P52000053782, per GharKundli's check of MahaRERA records.
How many homes are in SAUBHAGYAM?
According to GharKundli's check of MahaRERA records (updated November 2026), SAUBHAGYAM has 205 homes in 1 tower registered on MahaRERA, and 85% of them are sold or booked.
When was SAUBHAGYAM registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SAUBHAGYAM was registered on MahaRERA on 28 November 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on SAUBHAGYAM?
No court cases are listed for SAUBHAGYAM on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SAUBHAGYAM?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is TODAY GLOBAL PROPERTIES, the company Jindal files this project under, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SAUBHAGYAM
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2029 in Raigad →
Other projects in pincode 410221
- ARIHANT ASPIRE PHASE I
- Cityopia Bankers Enclave
- SHREEJI HILLS
- VRINDAVAN CHANDAR HEIGHTS
- SAUBHAGYAM PHASE II
- JAI MALHAR APARTMENT PHASE - III
- BALAJI BLOSSOMS
- Golf Crest, Godrej City, Panvel
Other projects by TODAY GLOBAL PROPERTIES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.