Harmony Residency
by Harmony Realtors · Dronagiri, Raigarh
Possession date of Harmony Residency: 31 July 2027, moved from 31 March 2026 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52000054988, and currently active. Its completion date has moved from March 2026 to July 2027: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Harmony Residency?
How the possession date of Harmony Residency has moved
31 March 2026
Completion date given when the project was registered
31 March 2027
Extended at the builder's request (MahaRERA application EA12022619812)
Reason the builder gave MahaRERA:
“The project construction is substantially completed and only minor finishing works remain. However, the application for Occupancy Certificate (OC) is currently pending due to delay in approvals from the concerned local authority. Since the…” Read the full reason
“The project construction is substantially completed and only minor finishing works remain. However, the application for Occupancy Certificate (OC) is currently pending due to delay in approvals from the concerned local authority. Since the issuance of OC is essential for project completion and handover, additional time is required to obtain the same. The delay is purely administrative and beyond the control of the promoter. Therefore, an extension is sought to complete the remaining minor works and secure the Occupancy Certificate in compliance with RERA provisions. Given the circumstances,…”31 July 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Harmony Residency’s extension records on MahaRERA (P52000054988), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Harmony Residency
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52000054988
- Status
- Registered and active
- Builder
- Harmony Realtors
- Location
- Dronagiri, Raigarh · 400702
- Project type
- Residential / Group Housing
- Registered on
- 21 Feb 2024
- Completion date at registration
- March 2026
- Latest completion date
- July 2027
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 56
- Sold or booked
- 20%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Harmony Residency, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A-Wing and B-Wing | 100% | 100% | 37.25% | 6.66% |
Commencement certificate (CC), as filed on MahaRERA
- A-Wing and B-Wing: covers 8 (G + 7)
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Harmony Residency every month.
Harmony Residency: buildings, flats and land, as filed on MahaRERA
- Buildings: A-Wing and B-Wing (8 floors, 56 units)
- Car parking: 8 open
- Land: 600 sq m (about 0.1 acres) · sanctioned built-up 2,361 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Harmony Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Harmony Residency: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Harmony Residency
What is the possession date of Harmony Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Harmony Residency in Dronagiri, Raigarh is 31 July 2027 — 12 months later than 31 March 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Harmony Residency?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Harmony Residency's builder has filed on MahaRERA, the official one, is 31 July 2027, already 12 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Harmony Residency extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Harmony Residency's builder applied to MahaRERA to extend the completion date once: to 31 March 2027, giving the reason "The project construction is substantially completed and only minor finishing works remain. However, the application for Occupancy Certificate (OC) is currently pending due to delay in approvals from the concerned local authority. Since the issuance of OC is essential for project completion and handover, additional time is required to obtain the same. The delay is purely administrative and beyond the control of the promoter. Therefore, an extension is sought to complete the remaining minor works and secure the Occupancy Certificate in compliance with RERA provisions. Given the circumstances,…". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Harmony Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Harmony Residency in Dronagiri, Raigarh is P52000054988.
Is Harmony Residency registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Harmony Residency is registered as P52000054988 and its status is "Registered and active".
What is the construction status of Harmony Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Harmony Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work on A-Wing and B-Wing is 100% done and internal work 37.25%. GharKundli's full report compares construction progress with the deadline.
Does Harmony Residency have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Harmony Residency safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Harmony Residency is registered on MahaRERA as P52000054988, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Harmony Residency's possession date changes?
The latest dates are on Harmony Residency's MahaRERA page (P52000054988). GharKundli's Kundli Watch sends a free WhatsApp update on Harmony Residency every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Harmony Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), Harmony Residency has one building filed: A-Wing and B-Wing with 8 floors and 56 units.
How much parking does Harmony Residency have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 8 open car parking spaces for Harmony Residency.
How big is the land of Harmony Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Harmony Residency stands on 600 sq m of land (about 0.1 acres), with 2,361 sq m of sanctioned built-up area.
Where can I read reviews of Harmony Residency?
Google Maps has reviews of Harmony Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Harmony Residency?
Harmony Residency by Harmony Realtors is in Dronagiri, Raigarh (pincode 400702), Maharashtra, and is registered on MahaRERA as P52000054988, per GharKundli's check of MahaRERA records.
How many homes are in Harmony Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), Harmony Residency has 56 homes in 1 tower registered on MahaRERA, and 20% of them are sold or booked.
When was Harmony Residency registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Harmony Residency was registered on MahaRERA on 21 February 2024. GharKundli did not find a title report on the land on file there.
Are there court cases on Harmony Residency?
No court cases are listed for Harmony Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Harmony Residency?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Harmony Realtors.
Check it yourself on MahaRERA
- How to check the possession date of Harmony Residency
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Raigad →
Other projects in Dronagiri
- Kreston Tower
- Surana Vista
- Sky Natraj
- DHANASHREE APARTMENT
- Ashtavinayak Co op Hsg Society Ltd
- Surana Harmony
- Ambika Residency
- Manzil Amor
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.