NAMAN SOLITAIRE

by BAKLIWAL INFRACON PRIVATE LIMITED · Taloja A.V., RaigarhAlso near Koyana Velhe, Koynavele, Panvel

Possession date of NAMAN SOLITAIRE: 30 April 2030. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under PM1270002502344, and currently active. Its completion date is now April 2030, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about NAMAN SOLITAIRE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of NAMAN SOLITAIRE has moved

  1. 31 December 2029

    Completion date given when the project was registered

  2. 30 April 2030

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: NAMAN SOLITAIRE’s extension records on MahaRERA (PM1270002502344), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on NAMAN SOLITAIRE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2030 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
PM1270002502344
Status
Registered and active
Builder
BAKLIWAL INFRACON PRIVATE LIMITED
Location
Taloja A.V., Raigarh · 410208
Project type
Mixed
Registered on
12 Feb 2026
Completion date at registration
December 2029
Latest completion date
April 2030
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
180
Sold or booked
8%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of NAMAN SOLITAIRE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
NAMAN SOLITAIRE90%0%0%0%

Commencement certificate (CC), as filed on MahaRERA

  • NAMAN SOLITAIRE: covers 21 floors

Latest CC order on MahaRERA: dated 09/01/2026.

Want to know when this changes? Kundli Watch sends a free WhatsApp update on NAMAN SOLITAIRE every month.

NAMAN SOLITAIRE: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Bakliwal Infracon (a group of 2 linked companies) has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 4 months); 1 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of NAMAN SOLITAIRE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

NAMAN SOLITAIRE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about NAMAN SOLITAIRE

What is the possession date of NAMAN SOLITAIRE?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for NAMAN SOLITAIRE in Taloja A.V., Raigarh is 30 April 2030, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for NAMAN SOLITAIRE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date NAMAN SOLITAIRE's builder has filed on MahaRERA, the official one, is 30 April 2030, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of NAMAN SOLITAIRE?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of NAMAN SOLITAIRE in Taloja A.V., Raigarh is PM1270002502344.

Is NAMAN SOLITAIRE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), NAMAN SOLITAIRE is registered as PM1270002502344 and its status is "Registered and active".

What is the construction status of NAMAN SOLITAIRE?

According to GharKundli's check of MahaRERA records (updated October 2026), NAMAN SOLITAIRE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on NAMAN SOLITAIRE is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does NAMAN SOLITAIRE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is NAMAN SOLITAIRE safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), NAMAN SOLITAIRE is registered on MahaRERA as PM1270002502344, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if NAMAN SOLITAIRE's possession date changes?

The latest dates are on NAMAN SOLITAIRE's MahaRERA page (PM1270002502344). GharKundli's Kundli Watch sends a free WhatsApp update on NAMAN SOLITAIRE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does NAMAN SOLITAIRE have?

According to GharKundli's check of MahaRERA records (updated October 2026), NAMAN SOLITAIRE has one building filed: NAMAN SOLITAIRE with 21 floors and 197 units.

How much parking does NAMAN SOLITAIRE have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 133 covered car parking spaces for NAMAN SOLITAIRE.

How big is the land of NAMAN SOLITAIRE?

According to GharKundli's check of MahaRERA records (updated October 2026), NAMAN SOLITAIRE stands on 4,150 sq m of land (about 1.0 acres), with 12,472 sq m of sanctioned built-up area.

What is the track record of NAMAN SOLITAIRE's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Bakliwal Infracon (a group of 2 linked companies) has 2 projects on MahaRERA since 2022, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 4 months); 1 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of NAMAN SOLITAIRE?

Google Maps has reviews of NAMAN SOLITAIRE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is NAMAN SOLITAIRE?

NAMAN SOLITAIRE by BAKLIWAL INFRACON PRIVATE LIMITED is in Taloja A.V., Raigarh (pincode 410208), near Koyana Velhe, Koynavele, Panvel, Maharashtra, and is registered on MahaRERA as PM1270002502344, per GharKundli's check of MahaRERA records.

How many homes are in NAMAN SOLITAIRE?

According to GharKundli's check of MahaRERA records (updated October 2026), NAMAN SOLITAIRE has 180 homes in 1 tower registered on MahaRERA, and 8% of them are sold or booked.

When was NAMAN SOLITAIRE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), NAMAN SOLITAIRE was registered on MahaRERA on 12 February 2026. GharKundli did not find a title report on the land on file there.

Are there court cases on NAMAN SOLITAIRE?

No court cases are listed for NAMAN SOLITAIRE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of NAMAN SOLITAIRE?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is BAKLIWAL INFRACON PRIVATE LIMITED.

All projects with possession due in 2030 in Raigad →

Other projects in pincode 410208

All 337 projects in Taloja (410208) →