PARVATARA PHASE 2

by Saakshi Constructions · Kiwale, PuneAlso near Dehu Road Cantt

Possession date of PARVATARA PHASE 2: 30 April 2028, moved from 30 December 2022 (60 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100002707, and currently active. Its completion date has moved from December 2022 to April 2028: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about PARVATARA PHASE 2?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of PARVATARA PHASE 2 has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 31 May 2023

    Extended at the builder's request (MahaRERA application EXT52100011324)

    Reason the builder gave MahaRERA: “Revised plan not yet sanctioned. Work not yet commenced. No booking accepted.”
  3. 31 December 2027

    Extended at the builder's request (MahaRERA application EXT52100012194)

    Reason the builder gave MahaRERA:
    “1: We had applied for revised Building Plan Permission of project PARAVATARA Phase 2 which earlier was purely a commercial project and now after fresh revised Building Plan. It is the combination of commercial and Residential Project. 2: Si…” Read the full reason“1: We had applied for revised Building Plan Permission of project PARAVATARA Phase 2 which earlier was purely a commercial project and now after fresh revised Building Plan. It is the combination of commercial and Residential Project. 2: Since the Building plan was revised, we received a revised building work commencement Certificate for PARVATARA PHASE 2 on 15th Dec 2021. 3. After receipt of revised building plan for PARVATARA Phase 2, We have applied for getting revised Environment clearance certificate. We have not yet received the environment clearance till toady 4: Since We have not ye…”
  4. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: PARVATARA PHASE 2’s extension records on MahaRERA (P52100002707), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on PARVATARA PHASE 2

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100002707
Status
Registered and active
Builder
Saakshi Constructions
Location
Kiwale, Pune · 412101
Project type
Others
Registered on
4 Aug 2017
Completion date at registration
December 2022
Latest completion date
April 2028
Delay so far
60 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
90
Sold or booked
81%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of PARVATARA PHASE 2, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING A100%100%77.5%58%

Commencement certificate (CC), as filed on MahaRERA

  • BUILDING A: covers 16 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on PARVATARA PHASE 2 every month.

PARVATARA PHASE 2: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING A (20 floors, 116 units)
  • Car parking: 98 covered
  • Land: 2,050 sq m (about 0.5 acres) · sanctioned built-up 12,931 sq m

The builder’s record and reviews

Saakshi Constructions has 3 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 30 months late). No complaints on MahaRERA.

Read Google reviews of PARVATARA PHASE 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

PARVATARA PHASE 2: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about PARVATARA PHASE 2

What is the possession date of PARVATARA PHASE 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for PARVATARA PHASE 2 in Kiwale, Pune is 30 April 2028 — 60 months later than 30 December 2022, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for PARVATARA PHASE 2?

Builders and listing sites often quote an earlier "target" date for handover. The completion date PARVATARA PHASE 2's builder has filed on MahaRERA, the official one, is 30 April 2028, already 60 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of PARVATARA PHASE 2 extended?

According to GharKundli's check of MahaRERA records (updated November 2026), PARVATARA PHASE 2's builder applied to MahaRERA to extend the completion date 2 times: to 31 May 2023, giving the reason "Revised plan not yet sanctioned. Work not yet commenced. No booking accepted."; to 31 December 2027, giving the reason "1: We had applied for revised Building Plan Permission of project PARAVATARA Phase 2 which earlier was purely a commercial project and now after fresh revised Building Plan. It is the combination of commercial and Residential Project. 2: Since the Building plan was revised, we received a revised building work commencement Certificate for PARVATARA PHASE 2 on 15th Dec 2021. 3. After receipt of revised building plan for PARVATARA Phase 2, We have applied for getting revised Environment clearance certificate. We have not yet received the environment clearance till toady 4: Since We have not ye…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of PARVATARA PHASE 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of PARVATARA PHASE 2 in Kiwale, Pune is P52100002707.

Is PARVATARA PHASE 2 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PARVATARA PHASE 2 is registered as P52100002707 and its status is "Registered and active".

What is the construction status of PARVATARA PHASE 2?

According to GharKundli's check of MahaRERA records (updated November 2026), PARVATARA PHASE 2's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BUILDING A is 100% done and internal work 77.5%. GharKundli's full report compares construction progress with the deadline.

Does PARVATARA PHASE 2 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is PARVATARA PHASE 2 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), PARVATARA PHASE 2 is registered on MahaRERA as P52100002707, its completion date has moved 60 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if PARVATARA PHASE 2's possession date changes?

The latest dates are on PARVATARA PHASE 2's MahaRERA page (P52100002707). GharKundli's Kundli Watch sends a free WhatsApp update on PARVATARA PHASE 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does PARVATARA PHASE 2 have?

According to GharKundli's check of MahaRERA records (updated November 2026), PARVATARA PHASE 2 has one building filed: BUILDING A with 20 floors and 116 units.

How much parking does PARVATARA PHASE 2 have?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 98 covered car parking spaces for PARVATARA PHASE 2.

How big is the land of PARVATARA PHASE 2?

According to GharKundli's check of MahaRERA records (updated November 2026), PARVATARA PHASE 2 stands on 2,050 sq m of land (about 0.5 acres), with 12,931 sq m of sanctioned built-up area.

What is the track record of PARVATARA PHASE 2's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Saakshi Constructions has 3 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 2 still being built, 1 past the promised date (typically 30 months late). No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of PARVATARA PHASE 2?

Google Maps has reviews of PARVATARA PHASE 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is PARVATARA PHASE 2?

PARVATARA PHASE 2 by Saakshi Constructions is in Kiwale, Pune (pincode 412101), near Dehu Road Cantt, Maharashtra, and is registered on MahaRERA as P52100002707, per GharKundli's check of MahaRERA records.

How many homes are in PARVATARA PHASE 2?

According to GharKundli's check of MahaRERA records (updated November 2026), PARVATARA PHASE 2 has 90 homes in 1 tower registered on MahaRERA, and 81% of them are sold or booked.

When was PARVATARA PHASE 2 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), PARVATARA PHASE 2 was registered on MahaRERA on 4 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on PARVATARA PHASE 2?

No court cases are listed for PARVATARA PHASE 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of PARVATARA PHASE 2?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Saakshi Constructions, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2028 in Pune →

Other projects in pincode 412101

All 381 projects in Ravet (412101) →

Other projects by Saakshi Constructions

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.