Khandve Estique Phase I

by KHANDVE PATIL CONSTRUCTIONS · Karve Nagar, Pune 411045Also near Balewadi, Baner, ShivajinagarRegistered on MahaRERA as “ESTIQUE PHASE I”

What’s in the report? →

Possession: Khandve Estique Phase I (MahaRERA P52100002751) is marked completed on MahaRERA. It has 12 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100002751. Status: Completed.

Source: MahaRERA website — records for P52100002751, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Khandve Estique Phase I?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

How the possession date of Khandve Estique Phase I has moved

  1. 31 December 2018

    Completion date given when the project was registered

  2. 31 December 2019

    Extended at the builder's request (MahaRERA application EXT52100001329)

    Reason the builder gave MahaRERA:
    “WE HAD APPLIED FOR VERTICAL EXTENSION OF THE SAME PROJECT AS ESTIQUE PHASE II ( RERA REGISTRATION NUMBER P52100017913 ) . WE NEED EXTENSION AS PER COMPLETION DATE OF VERTICAL PHASE II TO COMPLETE THE PROJECT. SO KINDLY PROCESS OUR PROJECT E…” Read the full reason“WE HAD APPLIED FOR VERTICAL EXTENSION OF THE SAME PROJECT AS ESTIQUE PHASE II ( RERA REGISTRATION NUMBER P52100017913 ) . WE NEED EXTENSION AS PER COMPLETION DATE OF VERTICAL PHASE II TO COMPLETE THE PROJECT. SO KINDLY PROCESS OUR PROJECT EXTENSION.”

Source: Khandve Estique Phase I’s extension records on MahaRERA (P52100002751), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Khandve Estique Phase I

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2019 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100002751
Status
Completed
Builder
KHANDVE PATIL CONSTRUCTIONS
Location
Karve Nagar, Pune · 411045
Project type
Residential / Group Housing
Registered on
4 Aug 2017
Completion date at registration
December 2018
Latest completion date
December 2019
Delay so far
12 months
Homes
12
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of Khandve Estique Phase I, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
ESTIQUE I100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Khandve Estique Phase I every 1–2 months.

Khandve Estique Phase I: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Khandve Patil Constructions has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 9 months); 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.

Read Google reviews of Khandve Estique Phase I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Khandve Estique Phase I: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Khandve Estique Phase I

What is the possession date of Khandve Estique Phase I?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Khandve Estique Phase I in Karve Nagar, Pune is 31 December 2019 — 12 months later than 31 December 2018, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Khandve Estique Phase I?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Khandve Estique Phase I's builder has filed on MahaRERA, the official one, is 31 December 2019, already 12 months later than the 31 December 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Khandve Estique Phase I extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Khandve Estique Phase I's builder applied to MahaRERA to extend the completion date once: to 31 December 2019, giving the reason "WE HAD APPLIED FOR VERTICAL EXTENSION OF THE SAME PROJECT AS ESTIQUE PHASE II ( RERA REGISTRATION NUMBER P52100017913 ) . WE NEED EXTENSION AS PER COMPLETION DATE OF VERTICAL PHASE II TO COMPLETE THE PROJECT. SO KINDLY PROCESS OUR PROJECT EXTENSION.".

What is the RERA number of Khandve Estique Phase I?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Khandve Estique Phase I in Karve Nagar, Pune is P52100002751.

Is Khandve Estique Phase I registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Khandve Estique Phase I is registered as P52100002751 and its status is "Completed".

What is the current construction status of Khandve Estique Phase I? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Khandve Estique Phase I's status on MahaRERA is "Completed". As filed by the builder, slab work on ESTIQUE I is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Khandve Estique Phase I have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Khandve Estique Phase I safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Khandve Estique Phase I is registered on MahaRERA as P52100002751, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Khandve Estique Phase I?

According to GharKundli's check of MahaRERA records (updated November 2026), Khandve Estique Phase I is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Khandve Estique Phase I?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Khandve Estique Phase I: gharkundli.com/tools/property-cost-calculator

Has Khandve Estique Phase I received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Khandve Estique Phase I is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Khandve Estique Phase I completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Khandve Estique Phase I is marked completed on MahaRERA, and the completion date filed there is 31 December 2019. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Khandve Estique Phase I uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Khandve Estique Phase I was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

Does Khandve Estique Phase I have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: ESTIQUE PHASE II (P52100017913, possession 31 Dec 2019). Check that your agreement names the registration of your own wing.

How can I get updates if Khandve Estique Phase I's possession date changes?

The latest dates are on Khandve Estique Phase I's MahaRERA page (P52100002751). GharKundli's Kundli Watch sends a free WhatsApp update on Khandve Estique Phase I every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Khandve Estique Phase I have?

According to GharKundli's check of MahaRERA records (updated November 2026), Khandve Estique Phase I has one building filed: ESTIQUE I with 4 floors.

How big is the land of Khandve Estique Phase I?

According to GharKundli's check of MahaRERA records (updated November 2026), Khandve Estique Phase I stands on 900 sq m of land (about 0.2 acres), with 593 sq m of sanctioned built-up area.

What is the track record of Khandve Estique Phase I's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Khandve Patil Constructions has 4 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 9 months); 1 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

What are the reviews of Khandve Estique Phase I?

Google Maps has reviews of Khandve Estique Phase I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Khandve Estique Phase I?

Khandve Estique Phase I by KHANDVE PATIL CONSTRUCTIONS is in Karve Nagar, Pune, pincode 411045 (near Balewadi, Baner, Shivajinagar), Maharashtra, and is registered on MahaRERA as P52100002751, per GharKundli's check of MahaRERA records. Its land is filed as 127 H.NO. 4 AND 5 , 2. GharKundli lists all 713 MahaRERA projects in Baner (411045).

How many flats are in Khandve Estique Phase I?

According to GharKundli's check of MahaRERA records (updated November 2026), Khandve Estique Phase I has 12 homes in 1 tower registered on MahaRERA.

When was Khandve Estique Phase I registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Khandve Estique Phase I was registered on MahaRERA on 4 August 2017. GharKundli did not find a title report on the land on file there.

Does Khandve Estique Phase I have any legal issues or court cases?

No court cases are listed for Khandve Estique Phase I on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Khandve Estique Phase I?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is KHANDVE PATIL CONSTRUCTIONS, which has 2 other projects registered on MahaRERA.

Other projects in Baner (411045)

All 713 projects in Baner (411045) →

Other projects by KHANDVE PATIL CONSTRUCTIONS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.