CHARU VED APARTMENT
by GANDHI ASSOCIATES · Haveli, Pune
Possession date of CHARU VED APARTMENT: 30 June 2023, moved from 31 March 2018 (63 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P52100013036. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (June 2023) has passed.
What do you want to know about CHARU VED APARTMENT?
How the possession date of CHARU VED APARTMENT has moved
31 March 2018
Completion date given when the project was registered
31 March 2020
Extended at the builder's request (MahaRERA application EXT52100001886)
Reason the builder gave MahaRERA:
“Regarding Extension of Registration Date of Project “CHARU VED APARTMENT” Rera Reg. No. P52100013036 Although the delay in the project was in the start of the construction due to the lack of finance and the funds available and also due to t…” Read the full reason
“Regarding Extension of Registration Date of Project “CHARU VED APARTMENT” Rera Reg. No. P52100013036 Although the delay in the project was in the start of the construction due to the lack of finance and the funds available and also due to the delay by the contractors in the completion of the work and as on now the construction is in full flow and the project will be completed on the extended date as assured to the Flat owners and to the RERA officials. The self attested NOC from the flat owners are attached below.”31 December 2022
Extended at the builder's request (MahaRERA application EXT52100008398)
Reason the builder gave MahaRERA:
“RESPECTED SIR, Sir, We/ I Mr. Rushabh Pramod Gandhi Partner of GANDHI ASSOCIATES hereby affirm that the proposed FSI Area has been changed from 821.39 sq.mtr. to 1996.46 sq.mtr. as per the Change in the Authority and Unified Rule in Pune. A…” Read the full reason
“RESPECTED SIR, Sir, We/ I Mr. Rushabh Pramod Gandhi Partner of GANDHI ASSOCIATES hereby affirm that the proposed FSI Area has been changed from 821.39 sq.mtr. to 1996.46 sq.mtr. as per the Change in the Authority and Unified Rule in Pune. As we got the approval of the Plan Sanction on Date 23/11/2021 we need The Completion Date of the further construction to be completed till date 31/12/2022 of Project “CHARU VED APARTMENT””30 June 2023
Revised completion date on MahaRERA
Source: CHARU VED APARTMENT’s extension records on MahaRERA (P52100013036), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on CHARU VED APARTMENT
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100013036
- Status
- Lapsed (registration period ended)
- Builder
- GANDHI ASSOCIATES
- Location
- Haveli, Pune · 411015
- Project type
- Others
- Registered on
- 12 Sep 2017
- Completion date at registration
- March 2018
- Latest completion date
- June 2023
- Delay so far
- 63 months
- Homes
- 44
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of CHARU VED APARTMENT, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| CHARU VED APARTMENT | 100% | 100% | 80% | 90% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on CHARU VED APARTMENT every month.
CHARU VED APARTMENT: buildings, flats and land, as filed on MahaRERA
- Buildings: CHARU VED APARTMENT (12 floors)
- Land: 1,131 sq m (about 0.3 acres) · sanctioned built-up 821 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of CHARU VED APARTMENT →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
CHARU VED APARTMENT: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about CHARU VED APARTMENT
What is the possession date of CHARU VED APARTMENT?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for CHARU VED APARTMENT in Haveli, Pune is 30 June 2023 — 63 months later than 31 March 2018, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for CHARU VED APARTMENT?
Builders and listing sites often quote an earlier "target" date for handover. The completion date CHARU VED APARTMENT's builder has filed on MahaRERA, the official one, is 30 June 2023, already 63 months later than the 31 March 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of CHARU VED APARTMENT extended?
According to GharKundli's check of MahaRERA records (updated November 2026), CHARU VED APARTMENT's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2020, giving the reason "Regarding Extension of Registration Date of Project “CHARU VED APARTMENT” Rera Reg. No. P52100013036 Although the delay in the project was in the start of the construction due to the lack of finance and the funds available and also due to the delay by the contractors in the completion of the work and as on now the construction is in full flow and the project will be completed on the extended date as assured to the Flat owners and to the RERA officials. The self attested NOC from the flat owners are attached below."; to 31 December 2022, giving the reason "RESPECTED SIR, Sir, We/ I Mr. Rushabh Pramod Gandhi Partner of GANDHI ASSOCIATES hereby affirm that the proposed FSI Area has been changed from 821.39 sq.mtr. to 1996.46 sq.mtr. as per the Change in the Authority and Unified Rule in Pune. As we got the approval of the Plan Sanction on Date 23/11/2021 we need The Completion Date of the further construction to be completed till date 31/12/2022 of Project “CHARU VED APARTMENT”".
What is the RERA number of CHARU VED APARTMENT?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of CHARU VED APARTMENT in Haveli, Pune is P52100013036.
Is CHARU VED APARTMENT registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), CHARU VED APARTMENT is registered as P52100013036 and its status is "Lapsed (registration period ended)".
What is the construction status of CHARU VED APARTMENT?
According to GharKundli's check of MahaRERA records (updated November 2026), CHARU VED APARTMENT's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on CHARU VED APARTMENT is 100% done and internal work 80%. GharKundli's full report compares construction progress with the deadline.
Does CHARU VED APARTMENT have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is CHARU VED APARTMENT safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), CHARU VED APARTMENT is registered on MahaRERA as P52100013036, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 63 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if CHARU VED APARTMENT's possession date changes?
The latest dates are on CHARU VED APARTMENT's MahaRERA page (P52100013036). GharKundli's Kundli Watch sends a free WhatsApp update on CHARU VED APARTMENT every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does CHARU VED APARTMENT have?
According to GharKundli's check of MahaRERA records (updated November 2026), CHARU VED APARTMENT has one building filed: CHARU VED APARTMENT with 12 floors.
How big is the land of CHARU VED APARTMENT?
According to GharKundli's check of MahaRERA records (updated November 2026), CHARU VED APARTMENT stands on 1,131 sq m of land (about 0.3 acres), with 821 sq m of sanctioned built-up area.
Where can I read reviews of CHARU VED APARTMENT?
Google Maps has reviews of CHARU VED APARTMENT written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is CHARU VED APARTMENT?
CHARU VED APARTMENT by GANDHI ASSOCIATES is in Haveli, Pune (pincode 411015), Maharashtra, and is registered on MahaRERA as P52100013036, per GharKundli's check of MahaRERA records.
How many homes are in CHARU VED APARTMENT?
According to GharKundli's check of MahaRERA records (updated November 2026), CHARU VED APARTMENT has 44 homes in 1 tower registered on MahaRERA.
When was CHARU VED APARTMENT registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), CHARU VED APARTMENT was registered on MahaRERA on 12 September 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on CHARU VED APARTMENT?
No court cases are listed for CHARU VED APARTMENT on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of CHARU VED APARTMENT?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is GANDHI ASSOCIATES, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of CHARU VED APARTMENT
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Haveli
- Dhvanil Harmony
- Siddheshwar Apartment
- Shubhshree Residency
- Evana Homes
- Prestige Business Hub
- Tathastu Phase II
- WAGHOLI HIGH STREET, BUILDING C
- G S Crown Plazaa
Other projects by GANDHI ASSOCIATES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.