MahaRERA projects in Dhanori, Pune (411015)
According to GharKundli's check of MahaRERA records, 109 housing projects are registered in pincode 411015 (Dhanori, Pune). 59 are still being built, 19 with possession due by the end of 2027. For 64, the completion date on MahaRERA is later than the one first promised. 35 have at least one complaint filed on MahaRERA.
Pincode 411015 also covers: Dighi, Dhanori Pune, Haveli, Deccan Gymkhana, Vishrantwadi, Dighi Camp.
“Possession due” is the latest completion date the builder has filed on MahaRERA; “first promised” is the date given at registration. Open a project for its full MahaRERA record.
| Project | MahaRERA status | Possession due (MahaRERA) | First promised | Complaints |
|---|---|---|---|---|
| SPARKLE Phase II SKYRISE VENTURES LLP | Active | 30 Oct 2026passed | 30 Jun 2026 | 0 |
| MAPLE GROVE SAIPAN GHUDUBHAI JAMADAR | Active | 30 Dec 2026 | same | 0 |
| MAITRI CHANDRIKA S K PROMOTERS | Active | 31 Dec 2026 | 31 Dec 2025 | 0 |
| SHRI SWAMI SAMARTH RESIDENCY M/S SHRI SWAMI SAMARTH BUILDERS AND DEVELOPERS | Active | 31 Dec 2026 | 31 Mar 2024 | 0 |
| SIDDHAAYA PARK S K REALTY GROUP | Active | 31 Dec 2026 | 31 Dec 2025 | 0 |
| TRIAA VASANTAM CITY CENTER PHASE 1 Triaa Realtors LLP | Active | 31 Dec 2026 | 31 Dec 2024 | 0 |
| Usha Heights Muralidhar Hajare | Active | 31 Dec 2026 | same | 0 |
| Aaiji Crystal Phase II AAIJI DEVELOPERS | Active | 1 Feb 2027 | 1 Apr 2026 | 0 |
| Galaxy Co-operative Housing Society Ltd Yash Developers | Active | 28 Feb 2027 | 31 Oct 2025 | 0 |
| AUSTIN Krishna Venture Skyscraper LLP | Active | 30 Apr 2027 | 31 Dec 2026 | 0 |
| LE SANCY MONAARCH BUILDCON | Active | 30 Apr 2027 | 31 Dec 2026 | 0 |
| Mauli Prastha YASHASHREE PROMOTERS AND BUILDERS | Active | 30 Apr 2027 | 31 Dec 2026 | 0 |
| Palladium Homes-II, B Building RAOJEE CONSTRUCTIONS | Active | 30 Apr 2027 | 31 Dec 2026 | 0 |
| SHUBHANKAR DURVAA PHASE II A Atul Dnyaneshwar Bahirat | Active | 30 Apr 2027 | 30 Jun 2026 | 1 |
| Taneesh Homes Shyamcharan Awadhbihari Pandey | Active | 30 Apr 2027 | 31 Dec 2026 | 0 |
| The Courtyard S K Constructions | Active | 30 Apr 2027 | 31 Mar 2026 | 0 |
| DELLA REGENCY SADANAND PATILBUVA GHULE | Active | 31 Jul 2027 | 31 Mar 2024 | 0 |
| MURLI MANOHAR HEIGHTS PADMANABH ASSOCIATES | Active | 31 Jul 2027 | 30 Sep 2026 | 0 |
| KOHINOOR VIVA PIXEL- PHASE I RISING ASSOCIATES | Active | 30 Sep 2027 | 30 Jun 2026 | 1 |
| Sai Avenue Sairaj Properties | Active | 30 Jan 2028 | 30 Sep 2027 | 0 |
| TIRUPATI SAI SAMRUDDHII TIRUPATI SAI ASSOCIATE | Active | 29 Feb 2028 | 31 Oct 2027 | 0 |
| Signature Corner Adarsh Associates & Developer | Active | 28 Mar 2028 | same | 0 |
| Mayur Kilbil Phase II wing D1 Part V BUNTY REALTORS | Active | 1 Apr 2028 | 1 Dec 2027 | 0 |
| Shreeyash Anuraj Pradnesh Shivaji Deokar | Active | 15 Apr 2028 | 15 Dec 2027 | 0 |
| GANGA NEWTOWN PH 4 D Bldg SHREE BALAJI ASSOCIATES PUNE LLP | Active | 30 Apr 2028 | 30 Jun 2027 | 0 |
| INFINITY SPACES SHUBHNIT BUILDCON | Active | 30 Apr 2028 | 31 Dec 2027 | 0 |
| Nahush Primero Nahush Associates | Active | 30 Apr 2028 | 30 Jun 2021 | 3 |
| Purple Bloom Building B JADHAV DEORE ASSOCIATES | Active | 30 Apr 2028 | 31 Dec 2027 | 0 |
| Shree Saai Forrtune Mrunali Realty LLP | Active | 30 Apr 2028 | 30 Dec 2026 | 0 |
| SHRIRAM NYSA SHRIRAM DEVELOPER | Active | 30 Apr 2028 | 31 Dec 2027 | 0 |
| UJWAL TOWER SHREYAS KORAD ASSOCIATE | Active | 30 Apr 2028 | 31 Dec 2025 | 0 |
| VRUNDAVAN GREENS VRUNDAVAN GREENS | Active | 30 Apr 2028 | 31 Dec 2025 | 0 |
| Chirantan Sankul N N Lele & Associates | Active | 31 Jul 2028 | 31 Mar 2028 | 0 |
| SIDDHIVINAYAK PRIDE YOGESH SANJAY GAIKWAD | Active | 30 Sep 2028 | 31 May 2028 | 0 |
| GANGA NEWTOWN PH 5 E BLDG SHREE BALAJI ASSOCIATES PUNE LLP | Active | 30 Oct 2028 | 30 Jun 2028 | 0 |
| Kohinoor Viva Pixel- Phase II RISING ASSOCIATES | Active | 30 Oct 2028 | 30 Jun 2028 | 0 |
| ArcVista Phase 4 Chaitanya Realty | Active | 30 Dec 2028 | same | 0 |
| Pearl Shree Developers | Active | 31 Dec 2028 | 31 Aug 2028 | 0 |
| Sai Enclave Shreyash Developers | Active | 31 Dec 2028 | same | 0 |
| SPARKLE ENCLAVE KAISAR JAMIL KHAN | Active | 31 Dec 2028 | same | 0 |
| GreenYards-Phase 1 Chaitanya Estate | Active | 29 Apr 2029 | 30 Dec 2027 | 0 |
| A33 BORDER ROAD SOCIETY TANISHKA DEVELOPERS AND BUILDERS | Active | 30 Apr 2029 | 31 Dec 2028 | 0 |
| MANGAL RESIDENCY UDAY DATTATRAY GAIKWAD | Active | 30 Apr 2029 | 31 Dec 2028 | 0 |
| ONE ARETHA - D Triaa Landmarks LLP | Active | 30 Apr 2029 | 31 Dec 2028 | 0 |
| ONE ARETHA PHASE 1 Triaa Landmarks LLP | Active | 30 Apr 2029 | 31 Dec 2028 | 0 |
| Ratnaa Residency Narmada Promoters and Builders | Active | 30 Apr 2029 | 31 Dec 2028 | 0 |
| SAI REGENCY SAI KRUSHNARANG VENTURES | Active | 30 Apr 2029 | 31 Dec 2028 | 0 |
| Tirupati Srushti TIRUPATI TINGRE ASSOCIATES | Active | 30 Apr 2029 | 31 Dec 2028 | 0 |
| NYATI ERA IV NYATI CONSTRUCTION PRIVATE LIMITED | Active | 30 Oct 2029 | 30 Jun 2029 | 1 |
| MOUNTAIN VIEW SUDHAKAR DADSAHEB BHOSALE | Active | 31 Dec 2029 | 31 Jan 2028 | 0 |
59 more projects
- QUE 101 PHASE I · 31 Mar 2030
- PRIMESTAND · 15 Apr 2030
- Aurapolis · 30 Apr 2030
- RADHIKA RADISSON · 30 Apr 2030
- Kamalraj Indradhanu A Building · 31 Jul 2030
- GANGA NEWTOWN PH 6 F BLDG · 31 Dec 2030
- Ajmera Uptown · 31 May 2031
- VEDANTA · 11 Jun 2031
- ArcVista Phase 3 · 30 Dec 2031
- Shree Ganesh Heights · completed
- SUNRISE GRAND · completed
- Kamalraj Prayag · completed
- Shiva Residency · completed
- OXY ETERNO · completed
- NYATI ERA I · completed
- NYATI ERA II · completed
- PARKLANE LIFESEASONS · completed
- Belmont Celosia · completed
- GANGA NEWTOWN PH 3 C Bldg · completed
- Belmont Aster · completed
- Belmont Jasmine · completed
- NYATI ERA III · completed
- TIRUPATI REGALIA PHASE- 3 · completed
- SAI PRASAD · 12 Apr 2022
- GINI BELVISTA - PHASE II · 31 Dec 2024
- AAIJI CASTLE · 31 Mar 2025
- VIVAAN APARTMENTS · 31 May 2025
- Mayur Kilbil Phase II - Wing D1 - Part IV · 29 Dec 2025
- KAMALRAJ PRAYAG C · 31 Dec 2025
- LAXMIVIHAR · 15 Jun 2026
- Gada Elina · 31 Jul 2026
- SAI DHAM · 31 Jul 2026
- AAIJI CRYSTAL PHASE I · 1 Oct 2026
- 29 GOLD COAST PHASE 2 · —
- ANAND AASHRAY · —
- Aurum Vrundavan · —
- CHESTERFIELD WING A AND WING B · —
- Dhanorina · —
- DHANORINA A34 · —
- GANGA NEWTOWN PHASE I · —
- GINI BELVISTA - PHASE I · —
- KAMAL C1 C2 · —
- KUDALE RESIDENCY · —
- Kumar Samruddhi A6 and A7 Building · —
- LIFESTYLE MAGNUM · —
- MANOMAY RESIDENCY · —
- MANTRA MONTANA PHASE 1 · —
- MANTRA MONTANA PHASE 3 · —
- MANTRA MONTANA PHASE 5 · —
- MANTRA MONTANA PHASE 7 · —
- MANTRA MONTANA PHASE 8 · —
- Margashirsha Heights · —
- MUKTANGAN · —
- POLITE CASTELLUM · —
- Sharayu Heights · —
- Shubhankar Durvaa Phase 2 · —
- SURBHI MANGALAM WING C, WING D, WING E, WING F · —
- Vijayalakshmy Residency · —
- VIRAJ HEIGHTS · —
Other areas in Pune
- Alandi Devachi · 450
- Chinchwadgaon · 370
- Wakad · 367
- Baner · 363
- Ravet · 344
- Kothrud · 276
- Wagholi · 230
- N I B M · 210
- Armament · 193
- Kharadi · 188
- Katraj · 186
- Bhugaon · 170
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records. Projects are grouped by the pincode filed on MahaRERA.