by Dharti Developers · Tathwade, Pune 411033Also near Chinchwad
What’s in the report? →Possession date of Dharti Green (MahaRERA P52100006457): 1 May 2027, moved from 31 March 2019 (98 months later). It has 48 homes, 100% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100006457, and currently active.
Source: MahaRERA website — records for P52100006457, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Dharti Green?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Dharti Green has moved
31 March 2019
Completion date given when the project was registered
30 March 2020
Extended at the builder's request (MahaRERA application EXT52100002441)
Reason the builder gave MahaRERA: “We have applied for completion certificate and also given possession. However the approving authority has kept the file in hold. We are taking necessary steps to close it as soon as possible.”
1 July 2026
Extended at the builder's request (MahaRERA application EXT52100010528)
Reason the builder gave MahaRERA:
“The project is duly completed and possessions are already given. We are not getting completion certificate from the Corporation due to technical difficulties developed by other Promoter. We have taken joint Commencement certificate with oth…” Read the full reason
“The project is duly completed and possessions are already given. We are not getting completion certificate from the Corporation due to technical difficulties developed by other Promoter. We have taken joint Commencement certificate with other developer on the common land. However, the other developer has developed 2 floors additionally without sanction and due to which our project is also not getting Completion certificate despite our construction is legitimately developed as per Sanctioned plan. We are taking many efforts to close the matter as soon as possible but it seems it will take ti…”1 May 2027
Extended at the builder's request
Source: Dharti Green’s extension records on MahaRERA (P52100006457), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Dharti Green
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the May 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100006457
- Status
- Registered and active
- Builder
- Dharti Developers
- Location
- Tathwade, Pune · 411033
- Project type
- Residential / Group Housing
- Registered on
- 14 Aug 2017
- Completion date at registration
- March 2019
- Latest completion date
- May 2027
- Delay so far
- 98 months
- Homes
- 48
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Dharti Green, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Dharti Green | 100% | 100% | 100% | 100% |
Commencement certificate (CC), as filed on MahaRERA
- Dharti Green: covers 7 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Dharti Green every 1–2 months.
Dharti Green: buildings, flats and land, as filed on MahaRERA
- Buildings: Dharti Green (8 floors, 48 units)
- Car parking: 1 covered
- Land: 1,870 sq m (about 0.5 acres) · sanctioned built-up 4,300 sq m
- Land, as filed: S no 56 3 to 56 12 part
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Dharti Green →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Dharti Green: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Dharti Green
What is the possession date of Dharti Green?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Dharti Green in Tathwade, Pune is 1 May 2027 — 98 months later than 31 March 2019, the date given at registration.
The date has already moved 98 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Dharti Green?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Dharti Green's builder has filed on MahaRERA, the official one, is 1 May 2027, already 98 months later than the 31 March 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Dharti Green extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Dharti Green's builder applied to MahaRERA to extend the completion date 3 times: to 30 March 2020, giving the reason "We have applied for completion certificate and also given possession. However the approving authority has kept the file in hold. We are taking necessary steps to close it as soon as possible."; to 1 July 2026, giving the reason "The project is duly completed and possessions are already given. We are not getting completion certificate from the Corporation due to technical difficulties developed by other Promoter. We have taken joint Commencement certificate with other developer on the common land. However, the other developer has developed 2 floors additionally without sanction and due to which our project is also not getting Completion certificate despite our construction is legitimately developed as per Sanctioned plan. We are taking many efforts to close the matter as soon as possible but it seems it will take ti…"; to 1 May 2027.
What is the RERA number of Dharti Green?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Dharti Green in Tathwade, Pune is P52100006457.
Is Dharti Green registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Dharti Green is registered as P52100006457 and its status is "Registered and active".
What is the current construction status of Dharti Green? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Dharti Green's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Dharti Green is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Dharti Green have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Dharti Green safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Dharti Green is registered on MahaRERA as P52100006457, its completion date has moved 98 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Dharti Green?
Dharti Green is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Dharti Green?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Dharti Green: gharkundli.com/tools/property-cost-calculator
Has Dharti Green received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Dharti Green is still under construction, with 1 May 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Dharti Green uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Dharti Green was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Dharti Green's possession date changes?
The latest dates are on Dharti Green's MahaRERA page (P52100006457). GharKundli's Kundli Watch sends a free WhatsApp update on Dharti Green every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Dharti Green have?
According to GharKundli's check of MahaRERA records (updated November 2026), Dharti Green has one building filed: Dharti Green with 8 floors and 48 units.
How much parking does Dharti Green have?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 1 covered car parking spaces for Dharti Green.
How big is the land of Dharti Green?
According to GharKundli's check of MahaRERA records (updated November 2026), Dharti Green stands on 1,870 sq m of land (about 0.5 acres), with 4,300 sq m of sanctioned built-up area.
What are the reviews of Dharti Green?
Google Maps has reviews of Dharti Green written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Dharti Green?
Dharti Green by Dharti Developers is in Tathwade, Pune, pincode 411033 (near Chinchwad), Maharashtra, and is registered on MahaRERA as P52100006457, per GharKundli's check of MahaRERA records. Its land is filed as S no 56 3 to 56 12 part. GharKundli lists all 613 MahaRERA projects in Chinchwadgaon (411033).
How many flats are in Dharti Green, and how many are sold?
According to GharKundli's check of MahaRERA records (updated November 2026), Dharti Green has 48 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was Dharti Green registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Dharti Green was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.
Does Dharti Green have any legal issues or court cases?
No court cases are listed for Dharti Green on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Dharti Green?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Dharti Developers, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Dharti Green
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Pune →
Other projects in Chinchwadgaon (411033)
- Nirman Serenopolis
- Millennium Samriddhi
- Rohan Harita Phase 4
- West World
- Raman Stellar
- Ganga Amber PH II
- Kohinoor Uptown Avenue
- Aishwaryam Insignia
Other projects by Dharti Developers
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.