Avani Residency

by AVANI RESIDENCY · Boisar East, Palghar

Possession date of Avani Residency: 30 April 2027, moved from 30 December 2021 (60 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000006263, and currently active. Its completion date has moved from December 2021 to April 2027: 60 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects. 4 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Avani Residency?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Avani Residency has moved

  1. 30 December 2021

    Completion date given when the project was registered

  2. 31 December 2026

    Extended at the builder's request (MahaRERA application EXT99000019507)

    Reason the builder gave MahaRERA: “The construction was delayed due to shortage of raw material & labour supply due to covid 19 pandemic. The said project will be ready on the requested new timeline.”
  3. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Avani Residency’s extension records on MahaRERA (P99000006263), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Avani Residency

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 4 complaints, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000006263
Status
Registered and active
Builder
AVANI RESIDENCY
Location
Boisar East, Palghar · 401501
Project type
Residential / Group Housing
Registered on
14 Aug 2017
Completion date at registration
December 2021
Latest completion date
April 2027
Delay so far
60 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
54
Sold or booked
87%
Towers
1
Complaints on MahaRERA
4
Court cases listed
0
Title report on file
Not found

Construction progress of Avani Residency, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
AVANI RESIDENCY B-3 WING B C100%100%55%20%

Commencement certificate (CC), as filed on MahaRERA

  • AVANI RESIDENCY B-3 WING B C: covers 2 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Avani Residency every month.

Avani Residency: buildings, flats and land, as filed on MahaRERA

  • Buildings: AVANI RESIDENCY B-3 WING B C (2 floors, 54 units)
  • Land: 1,086 sq m (about 0.3 acres) · sanctioned built-up 1,345 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Avani Residency →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Avani Residency: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Avani Residency

What is the possession date of Avani Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Avani Residency in Boisar East, Palghar is 30 April 2027 — 60 months later than 30 December 2021, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Avani Residency?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Avani Residency's builder has filed on MahaRERA, the official one, is 30 April 2027, already 60 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Avani Residency extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Avani Residency's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "The construction was delayed due to shortage of raw material & labour supply due to covid 19 pandemic. The said project will be ready on the requested new timeline.". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Avani Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Avani Residency in Boisar East, Palghar is P99000006263.

Is Avani Residency registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Avani Residency is registered as P99000006263 and its status is "Registered and active".

What is the construction status of Avani Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), Avani Residency's status on MahaRERA is "Registered and active". As filed by the builder, slab work on AVANI RESIDENCY B-3 WING B C is 100% done and internal work 55%. GharKundli's full report compares construction progress with the deadline.

Does Avani Residency have complaints on MahaRERA?

4 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Avani Residency safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Avani Residency is registered on MahaRERA as P99000006263, its completion date has moved 60 months since registration and 4 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Avani Residency's possession date changes?

The latest dates are on Avani Residency's MahaRERA page (P99000006263). GharKundli's Kundli Watch sends a free WhatsApp update on Avani Residency every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Avani Residency have?

According to GharKundli's check of MahaRERA records (updated October 2026), Avani Residency has one building filed: AVANI RESIDENCY B-3 WING B C with 2 floors and 54 units.

How big is the land of Avani Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), Avani Residency stands on 1,086 sq m of land (about 0.3 acres), with 1,345 sq m of sanctioned built-up area.

Where can I read reviews of Avani Residency?

Google Maps has reviews of Avani Residency written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 4 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Avani Residency?

Avani Residency by AVANI RESIDENCY is in Boisar East, Palghar (pincode 401501), Maharashtra, and is registered on MahaRERA as P99000006263, per GharKundli's check of MahaRERA records.

How many homes are in Avani Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), Avani Residency has 54 homes in 1 tower registered on MahaRERA, and 87% of them are sold or booked.

When was Avani Residency registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Avani Residency was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Avani Residency?

No court cases are listed for Avani Residency on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Avani Residency?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is AVANI RESIDENCY.

All projects with possession due in 2027 in Palghar →

Other projects in pincode 401501

All 126 projects in Boisar (401501) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.