by VEENAA DEVELOPERS PRIVATE LIMITED · Opposite Eklavya School, Palghar

Possession date of Luxury Empire Township Phase I: 31 December 2028, moved from 30 December 2025 (36 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000012256, and currently active. 8 complaints are listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Luxury Empire Township Phase I?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Luxury Empire Township Phase I has moved

  1. 30 December 2025

    Completion date given when the project was registered

  2. 31 December 2028

    Extended at the builder's request (MahaRERA application EA10122518590)

    Reason the builder gave MahaRERA:
    “•The project was originally launched by Goldstar Realtors, who abandoned the work midway, affecting over 150 allottees. •After continuous efforts by the Association of Allottees, our company took over the project for revival and completion.…” Read the full reason“•The project was originally launched by Goldstar Realtors, who abandoned the work midway, affecting over 150 allottees. •After continuous efforts by the Association of Allottees, our company took over the project for revival and completion. •The promoter change under Section 15 was completed in March 2025, after a year-long approval process. •Tripartite Agreements with the Association and individual allottees were executed, providing a realistic completion period of 18–24 months from June 2025, when site work resumed. •Due to the project’s long abandonment, several structures (including pre…”

Source: Luxury Empire Township Phase I’s extension records on MahaRERA (P99000012256), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Luxury Empire Township Phase I

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 8 complaints, and how it ended
  • Construction pace against the December 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000012256
Status
Registered and active
Builder
VEENAA DEVELOPERS PRIVATE LIMITED
Location
Opposite Eklavya School, Palghar · 401501
Project type
Others
Registered on
1 Sep 2017
Completion date at registration
December 2025
Latest completion date
December 2028
Delay so far
36 months
Homes
272
Sold or booked
100%
Towers
14
Complaints on MahaRERA
8
Court cases listed
0
Title report on file
Not found

Construction progress of Luxury Empire Township Phase I, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building No 1 Wing A100%100%100%100%
Building no 1 Wing B100%100%100%100%
Building no 2 Wing A100%85%80%20%
Building no 2 Wing B100%85%80%20%
Building no 2 Wing C100%85%80%20%
Building no 2 Wing D100%85%80%20%
Building no 3 Wing A100%100%100%100%
Building no 1 Wing C100%100%100%100%
Building no 3 Wing B100%100%100%100%
Building no 3 Wing C100%100%100%100%
Building no 4 Wing A100%80%60%10%
Building no 4 Wing B100%80%60%10%
Building no 4 Wing C100%80%60%10%
Building no 4 Wing D100%80%60%10%

Commencement certificate (CC), as filed on MahaRERA

  • Building No 1 Wing A: covers ground + 4 floor
  • Building no 1 Wing B: covers Ground + 4 floor
  • Building no 2 Wing A: covers Ground + 4 floor
  • Building no 2 Wing B: covers Ground + 4 floor
  • Building no 2 Wing C: covers Ground + 4 floor
  • Building no 2 Wing D: covers Ground + 4 floor
  • Building no 3 Wing A: covers ground + 4 floor
  • Building no 1 Wing C: covers Ground + 4 floor
  • Building no 3 Wing B: covers Ground + 4 floor
  • Building no 3 Wing C: covers Ground + 4 floor
  • Building no 4 Wing A: covers Ground + 4 floor
  • Building no 4 Wing B: covers Ground + 4 floor
  • Building no 4 Wing C: covers Ground + 4 floor
  • Building no 4 Wing D: covers Ground + 4 floor

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Luxury Empire Township Phase I every month.

Luxury Empire Township Phase I: buildings, flats and land, as filed on MahaRERA

  • Buildings: Building No 1 Wing A (5 floors, 32 units) · Building no 1 Wing B (5 floors, 22 units) · Building no 2 Wing A (5 floors, 22 units) · Building no 2 Wing B (5 floors, 36 units) · Building no 2 Wing C (5 floors, 25 units) · Building no 2 Wing D (4 floors, 26 units) · Building no 3 Wing A (5 floors, 20 units) · Building no 1 Wing C (5 floors, 21 units) · and 5 more
  • Land: 15,660 sq m (about 3.9 acres) · sanctioned built-up 14,002 sq m · recreational space 1,573 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Luxury Empire Township Phase I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Luxury Empire Township Phase I: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Luxury Empire Township Phase I

What is the possession date of Luxury Empire Township Phase I?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Luxury Empire Township Phase I in Opposite Eklavya School, Palghar is 31 December 2028 — 36 months later than 30 December 2025, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Luxury Empire Township Phase I?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Luxury Empire Township Phase I's builder has filed on MahaRERA, the official one, is 31 December 2028, already 36 months later than the 30 December 2025 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Luxury Empire Township Phase I extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Luxury Empire Township Phase I's builder applied to MahaRERA to extend the completion date once: to 31 December 2028, giving the reason "•The project was originally launched by Goldstar Realtors, who abandoned the work midway, affecting over 150 allottees. •After continuous efforts by the Association of Allottees, our company took over the project for revival and completion. •The promoter change under Section 15 was completed in March 2025, after a year-long approval process. •Tripartite Agreements with the Association and individual allottees were executed, providing a realistic completion period of 18–24 months from June 2025, when site work resumed. •Due to the project’s long abandonment, several structures (including pre…".

What is the RERA number of Luxury Empire Township Phase I?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Luxury Empire Township Phase I in Opposite Eklavya School, Palghar is P99000012256.

Is Luxury Empire Township Phase I registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Luxury Empire Township Phase I is registered as P99000012256 and its status is "Registered and active".

What is the construction status of Luxury Empire Township Phase I?

According to GharKundli's check of MahaRERA records (updated October 2026), Luxury Empire Township Phase I's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 80% to 100% across 14 towers. GharKundli's full report compares construction progress with the deadline.

Does Luxury Empire Township Phase I have complaints on MahaRERA?

8 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Luxury Empire Township Phase I safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Luxury Empire Township Phase I is registered on MahaRERA as P99000012256, its completion date has moved 36 months since registration and 8 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Luxury Empire Township Phase I's possession date changes?

The latest dates are on Luxury Empire Township Phase I's MahaRERA page (P99000012256). GharKundli's Kundli Watch sends a free WhatsApp update on Luxury Empire Township Phase I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Luxury Empire Township Phase I have?

According to GharKundli's check of MahaRERA records (updated October 2026), Luxury Empire Township Phase I has 13 buildings filed: Building No 1 Wing A with 5 floors and 32 units; Building no 1 Wing B with 5 floors and 22 units; Building no 2 Wing A with 5 floors and 22 units; Building no 2 Wing B with 5 floors and 36 units; Building no 2 Wing C with 5 floors and 25 units; Building no 2 Wing D with 4 floors and 26 units; and 7 more.

How big is the land of Luxury Empire Township Phase I?

According to GharKundli's check of MahaRERA records (updated October 2026), Luxury Empire Township Phase I stands on 15,660 sq m of land (about 3.9 acres), with 14,002 sq m of sanctioned built-up area and 1,573 sq m of recreational open space.

Where can I read reviews of Luxury Empire Township Phase I?

Google Maps has reviews of Luxury Empire Township Phase I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 8 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Luxury Empire Township Phase I?

Luxury Empire Township Phase I by VEENAA DEVELOPERS PRIVATE LIMITED is in Opposite Eklavya School, Palghar (pincode 401501), Maharashtra, and is registered on MahaRERA as P99000012256, per GharKundli's check of MahaRERA records.

How many homes are in Luxury Empire Township Phase I?

According to GharKundli's check of MahaRERA records (updated October 2026), Luxury Empire Township Phase I has 272 homes in 14 towers registered on MahaRERA, and 100% of them are sold or booked.

When was Luxury Empire Township Phase I registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Luxury Empire Township Phase I was registered on MahaRERA on 1 September 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Luxury Empire Township Phase I?

No court cases are listed for Luxury Empire Township Phase I on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of Luxury Empire Township Phase I?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is VEENAA DEVELOPERS PRIVATE LIMITED.

All projects with possession due in 2028 in Palghar →

Other projects in Palghar

All 133 projects in Boisar (401501) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.