EXCEL CELESTIA RESIDENCY
by EXCEL HOUSING · Chakan, Pune
Possession: EXCEL CELESTIA RESIDENCY is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100014266. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about EXCEL CELESTIA RESIDENCY?
How the possession date of EXCEL CELESTIA RESIDENCY has moved
30 December 2021
Completion date given when the project was registered
31 March 2022
Extended at the builder's request (MahaRERA application EXT52100011251)
Reason the builder gave MahaRERA: “due to lock down and lack of material we couldn't complete the project within time, we have already completed 90% construction work of the excel celestia Residency project”
30 September 2022
Extended at the builder's request (MahaRERA application EXT52100012175)
Reason the builder gave MahaRERA:
“Dear sir , As per Rera Authority Guideline we are apply for Project completion date extend upto 31/03/2023 as per Extension under section 7(3) ,Project delay due to Covid-19 Lockdown effect shortage of labour and material till date project…” Read the full reason
“Dear sir , As per Rera Authority Guideline we are apply for Project completion date extend upto 31/03/2023 as per Extension under section 7(3) ,Project delay due to Covid-19 Lockdown effect shortage of labour and material till date project building work upto 90 % completed as per section 7(3) we have taken 51% consent of Sold unit pls consider my request and extend proposed completion date . Thank you”30 December 2023
Extended at the builder's request (MahaRERA application EXT52100015128)
Reason the builder gave MahaRERA: “Due To completion certificate not Received from Corporation”
Source: EXCEL CELESTIA RESIDENCY’s extension records on MahaRERA (P52100014266), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on EXCEL CELESTIA RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100014266
- Status
- Completed
- Builder
- EXCEL HOUSING
- Location
- Chakan, Pune · 410501
- Project type
- Residential / Group Housing
- Registered on
- 17 Nov 2017
- Completion date at registration
- December 2021
- Latest completion date
- December 2023
- Delay so far
- 24 months
- Homes
- 44
- Sold or booked
- 91%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of EXCEL CELESTIA RESIDENCY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| CORONA RESIDENCY D WING | 100% | 100% | 100% | 80% |
Commencement certificate (CC), as filed on MahaRERA
- CORONA RESIDENCY D WING: covers 15 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on EXCEL CELESTIA RESIDENCY every month.
EXCEL CELESTIA RESIDENCY: buildings, flats and land, as filed on MahaRERA
- Buildings: CORONA RESIDENCY D WING (15 floors, 44 units)
- Land: 3,847 sq m (about 1.0 acres) · sanctioned built-up 3,069 sq m · recreational space 619 sq m
The builder’s record and reviews
Excel Housing has 3 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 12 months); 1 still being built, 1 past the promised date (typically 34 months late). 1 complaint on MahaRERA across 1 project.
Read Google reviews of EXCEL CELESTIA RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
EXCEL CELESTIA RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about EXCEL CELESTIA RESIDENCY
What is the possession date of EXCEL CELESTIA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for EXCEL CELESTIA RESIDENCY in Chakan, Pune is 30 December 2023 — 24 months later than 30 December 2021, the date given at registration.
Is the builder's possession date different from the MahaRERA date for EXCEL CELESTIA RESIDENCY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date EXCEL CELESTIA RESIDENCY's builder has filed on MahaRERA, the official one, is 30 December 2023, already 24 months later than the 30 December 2021 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of EXCEL CELESTIA RESIDENCY extended?
According to GharKundli's check of MahaRERA records (updated November 2026), EXCEL CELESTIA RESIDENCY's builder applied to MahaRERA to extend the completion date 3 times: to 31 March 2022, giving the reason "due to lock down and lack of material we couldn't complete the project within time, we have already completed 90% construction work of the excel celestia Residency project"; to 30 September 2022, giving the reason "Dear sir , As per Rera Authority Guideline we are apply for Project completion date extend upto 31/03/2023 as per Extension under section 7(3) ,Project delay due to Covid-19 Lockdown effect shortage of labour and material till date project building work upto 90 % completed as per section 7(3) we have taken 51% consent of Sold unit pls consider my request and extend proposed completion date . Thank you"; to 30 December 2023, giving the reason "Due To completion certificate not Received from Corporation".
What is the RERA number of EXCEL CELESTIA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of EXCEL CELESTIA RESIDENCY in Chakan, Pune is P52100014266.
Is EXCEL CELESTIA RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), EXCEL CELESTIA RESIDENCY is registered as P52100014266 and its status is "Completed".
What is the construction status of EXCEL CELESTIA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), EXCEL CELESTIA RESIDENCY's status on MahaRERA is "Completed". As filed by the builder, slab work on CORONA RESIDENCY D WING is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does EXCEL CELESTIA RESIDENCY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is EXCEL CELESTIA RESIDENCY safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), EXCEL CELESTIA RESIDENCY is registered on MahaRERA as P52100014266, its MahaRERA status is "Completed", its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if EXCEL CELESTIA RESIDENCY's possession date changes?
The latest dates are on EXCEL CELESTIA RESIDENCY's MahaRERA page (P52100014266). GharKundli's Kundli Watch sends a free WhatsApp update on EXCEL CELESTIA RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does EXCEL CELESTIA RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated November 2026), EXCEL CELESTIA RESIDENCY has one building filed: CORONA RESIDENCY D WING with 15 floors and 44 units.
How big is the land of EXCEL CELESTIA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), EXCEL CELESTIA RESIDENCY stands on 3,847 sq m of land (about 1.0 acres), with 3,069 sq m of sanctioned built-up area and 619 sq m of recreational open space.
What is the track record of EXCEL CELESTIA RESIDENCY's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Excel Housing has 3 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, 0 within the promised date and 1 needed more time (typically 12 months); 1 still being built, 1 past the promised date (typically 34 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of EXCEL CELESTIA RESIDENCY?
Google Maps has reviews of EXCEL CELESTIA RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is EXCEL CELESTIA RESIDENCY?
EXCEL CELESTIA RESIDENCY by EXCEL HOUSING is in Chakan, Pune (pincode 410501), Maharashtra, and is registered on MahaRERA as P52100014266, per GharKundli's check of MahaRERA records.
How many homes are in EXCEL CELESTIA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), EXCEL CELESTIA RESIDENCY has 44 homes in 1 tower registered on MahaRERA, and 91% of them are sold or booked.
When was EXCEL CELESTIA RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), EXCEL CELESTIA RESIDENCY was registered on MahaRERA on 17 November 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on EXCEL CELESTIA RESIDENCY?
No court cases are listed for EXCEL CELESTIA RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of EXCEL CELESTIA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is EXCEL HOUSING, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of EXCEL CELESTIA RESIDENCY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 410501
- SIDDHIVINAYAK DREAM HOMES C,D WING
- Mungase Towers
- SARA CITY PLOT E 1
- SARA NILAAY
- Vighnaharta
- Imperial Plaza
- RAJ APOORVAM
- Tathastu Homes
Other projects by EXCEL HOUSING
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.