Essen Aishwaryam Nivaara
by SAI ESSEN PROPERTIES · Chikhali, Pune 412114Also near Newale WastiRegistered on MahaRERA as “AISHWARYAM NIVAARA”
What’s in the report? →Possession date of Essen Aishwaryam Nivaara (MahaRERA P52100016005): 30 June 2022, moved from 30 September 2020 (21 months later), and it has already passed. It has 109 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100016005. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P52100016005, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (June 2022) has passed.
What do you want to know about Essen Aishwaryam Nivaara?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Essen Aishwaryam Nivaara has moved
30 September 2020
Completion date given when the project was registered
31 March 2021
Extended at the builder's request (MahaRERA application EXT52100006328)
Reason the builder gave MahaRERA: “We have currently apllied for NOC's required for procuring the occupation certificate, but we have yet not recieved them.”
31 December 2021
Extended at the builder's request (MahaRERA application EXT52100009438)
Reason the builder gave MahaRERA: “We have applied for completion certificate. Awaiting completion”
30 June 2022
Revised completion date on MahaRERA
Source: Essen Aishwaryam Nivaara’s extension records on MahaRERA (P52100016005), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Essen Aishwaryam Nivaara
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2022 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100016005
- Status
- Lapsed (registration period ended)
- Builder
- SAI ESSEN PROPERTIES
- Location
- Chikhali, Pune · 412114
- Project type
- Others
- Registered on
- 11 Apr 2018
- Completion date at registration
- September 2020
- Latest completion date
- June 2022
- Delay so far
- 21 months
- Homes
- 109
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 3
Construction progress of Essen Aishwaryam Nivaara, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A | 100% | 100% | 100% | 100% |
| B | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Essen Aishwaryam Nivaara every 1–2 months.
Essen Aishwaryam Nivaara: buildings, flats and land, as filed on MahaRERA
- Buildings: A (7 floors)
- Land: 3,500 sq m (about 0.9 acres) · sanctioned built-up 3,499 sq m · recreational space 350 sq m
- Land, as filed: GAT NO. 1294,1303,1304,1307
- Map: the location the builder filed on MahaRERA · Get directions
The builder’s record and reviews
SAI Essen Developers (a group of 10 linked companies) has 26 projects on MahaRERA since 2017, this one included. Of the 26 GharKundli has checked: 14 finished, 10 within the promised date and 4 needed more time (typically 13 months); 9 still being built, 1 past the promised date; 3 lapsed. 7 complaints on MahaRERA across 3 projects.
Read Google reviews of Essen Aishwaryam Nivaara →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Essen Aishwaryam Nivaara: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Essen Aishwaryam Nivaara
What is the possession date of Essen Aishwaryam Nivaara?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Essen Aishwaryam Nivaara in Chikhali, Pune is 30 June 2022 — 21 months later than 30 September 2020, the date given at registration. That date has already passed.
The date has already moved 21 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Essen Aishwaryam Nivaara?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Essen Aishwaryam Nivaara's builder has filed on MahaRERA, the official one, is 30 June 2022, already 21 months later than the 30 September 2020 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Essen Aishwaryam Nivaara extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Essen Aishwaryam Nivaara's builder applied to MahaRERA to extend the completion date 2 times: to 31 March 2021, giving the reason "We have currently apllied for NOC's required for procuring the occupation certificate, but we have yet not recieved them."; to 31 December 2021, giving the reason "We have applied for completion certificate. Awaiting completion".
What is the RERA number of Essen Aishwaryam Nivaara?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Essen Aishwaryam Nivaara in Chikhali, Pune is P52100016005.
Is Essen Aishwaryam Nivaara registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Essen Aishwaryam Nivaara is registered as P52100016005 and its status is "Lapsed (registration period ended)".
What is the current construction status of Essen Aishwaryam Nivaara? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Essen Aishwaryam Nivaara's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Essen Aishwaryam Nivaara have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Essen Aishwaryam Nivaara safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Essen Aishwaryam Nivaara is registered on MahaRERA as P52100016005, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 21 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Essen Aishwaryam Nivaara?
Essen Aishwaryam Nivaara isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Essen Aishwaryam Nivaara?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Essen Aishwaryam Nivaara: gharkundli.com/tools/property-cost-calculator
Has Essen Aishwaryam Nivaara received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Essen Aishwaryam Nivaara isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 30 June 2022 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Essen Aishwaryam Nivaara?
According to GharKundli's check of MahaRERA records (updated November 2026), Essen Aishwaryam Nivaara's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (30 June 2022) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Essen Aishwaryam Nivaara uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Essen Aishwaryam Nivaara was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Essen Aishwaryam Nivaara's possession date changes?
The latest dates are on Essen Aishwaryam Nivaara's MahaRERA page (P52100016005). GharKundli's Kundli Watch sends a free WhatsApp update on Essen Aishwaryam Nivaara every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Essen Aishwaryam Nivaara have?
According to GharKundli's check of MahaRERA records (updated November 2026), Essen Aishwaryam Nivaara has one building filed: A with 7 floors.
How big is the land of Essen Aishwaryam Nivaara?
According to GharKundli's check of MahaRERA records (updated November 2026), Essen Aishwaryam Nivaara stands on 3,500 sq m of land (about 0.9 acres), with 3,499 sq m of sanctioned built-up area and 350 sq m of recreational open space.
What is the track record of Essen Aishwaryam Nivaara's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), SAI Essen Developers (a group of 10 linked companies) has 26 projects on MahaRERA since 2017, this one included. Of the 26 GharKundli has checked: 14 finished, 10 within the promised date and 4 needed more time (typically 13 months); 9 still being built, 1 past the promised date; 3 lapsed. 7 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.
What are the reviews of Essen Aishwaryam Nivaara?
Google Maps has reviews of Essen Aishwaryam Nivaara written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Essen Aishwaryam Nivaara?
Essen Aishwaryam Nivaara by SAI ESSEN PROPERTIES is in Chikhali, Pune, pincode 412114 (near Newale Wasti), Maharashtra, and is registered on MahaRERA as P52100016005, per GharKundli's check of MahaRERA records. Its land is filed as GAT NO. 1294,1303,1304,1307.
How many flats are in Essen Aishwaryam Nivaara?
According to GharKundli's check of MahaRERA records (updated November 2026), Essen Aishwaryam Nivaara has 109 homes in 2 towers registered on MahaRERA.
When was Essen Aishwaryam Nivaara registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Essen Aishwaryam Nivaara was registered on MahaRERA on 11 April 2018. GharKundli did not find a title report on the land on file there.
Does Essen Aishwaryam Nivaara have any legal issues or court cases?
No court cases are listed for Essen Aishwaryam Nivaara on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Essen Aishwaryam Nivaara?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is SAI ESSEN PROPERTIES, which has 3 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Essen Aishwaryam Nivaara
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Pincode not filed (412114)
Other projects by SAI ESSEN PROPERTIES
All Pune projects with no pincode on MahaRERA →
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.