Anand Park Mamta Heights
by Sachin Shantilal Joshi · Boisar, Palghar
Possession: Anand Park Mamta Heights is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000004112. Status: Completed. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about Anand Park Mamta Heights?
How the possession date of Anand Park Mamta Heights has moved
30 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT99000003953)
Reason the builder gave MahaRERA:
“Respected Sir/Madam We have a ongoing project at Survey No/Gut No. 2 of Village Maan Taluka & Dist: Palghar. Registered with Rera under the Rera Act vide Number . P99000004112 The completion date for this project at time of registration was…” Read the full reason
“Respected Sir/Madam We have a ongoing project at Survey No/Gut No. 2 of Village Maan Taluka & Dist: Palghar. Registered with Rera under the Rera Act vide Number . P99000004112 The completion date for this project at time of registration was given as 30.12.2019.Now after revision in DCR in the region we are now elegible for additional FSI as per the sanctioned DCR and accordingly we have submitted a revised proposal to the collector Palghar ( Planning Authority) for revision in the plans as per prevailing rules and regulations. The requisite Challans payable to GOM for the revision of plans…”30 June 2022
Extended at the builder's request (MahaRERA application EXT99000009899)
Reason the builder gave MahaRERA:
“To, Rera Authority, SUBJECT: EXTENSION OF RERA DATE Sir/ Madam, My Project registered under RERA Reg No: P99000004112 & site situated at Boisar, Maan village, Dist Palghar, project known as Anand Park, had been given a Rera Due till 30/6/20…” Read the full reason
“To, Rera Authority, SUBJECT: EXTENSION OF RERA DATE Sir/ Madam, My Project registered under RERA Reg No: P99000004112 & site situated at Boisar, Maan village, Dist Palghar, project known as Anand Park, had been given a Rera Due till 30/6/2021. My site was working in full swing till the Pandemic, Covid 19 started. Due to the lockdown, we had to stop work for sometime according to the Government guidelines. Thereafter, as per the new guidelines, work started slowly with minimum workers and staff. My office is located at Mumbai and the distance is almost 195 to 200 kilometres from office to si…”30 December 2023
Extended at the builder's request (MahaRERA application EXT99000013202)
Reason the builder gave MahaRERA:
“To, Rera Authority, SUBJECT: EXTENSION OF RERA Sir/ Madam, We have obtained development permission and registered our project of Residential Buildings at Boisar, District Palghar. Project Reg No: P99000004112 in the name of project Anand Pa…” Read the full reason
“To, Rera Authority, SUBJECT: EXTENSION OF RERA Sir/ Madam, We have obtained development permission and registered our project of Residential Buildings at Boisar, District Palghar. Project Reg No: P99000004112 in the name of project Anand Park.The Due Date of Rera Certificate is till 30/12/2022. Our work is in progress as on date. My site was working in full swing before Pandemic, as per the new guidelines work started slowly with minimum workers and staff according to the government guidelines. Building number 1, is almost 100% ready building cleaning & finishing is ongoing. Expected posses…”30 June 2024
Extended at the builder's request (MahaRERA application EXT99000017868)
Reason the builder gave MahaRERA:
“To, Rera Authority, SUBJECT: REVISE EXTENSION DATE OF RERA CERTIFICATE Sir/ Madam, My site is situated at Boisar, District Palghar. Project Reg No: P99000004112. The name of the project is Anand Park. It had been given a Rera Due till 30/12…” Read the full reason
“To, Rera Authority, SUBJECT: REVISE EXTENSION DATE OF RERA CERTIFICATE Sir/ Madam, My site is situated at Boisar, District Palghar. Project Reg No: P99000004112. The name of the project is Anand Park. It had been given a Rera Due till 30/12/2023. As per my RERA submission, my balance FSI is pending. It is also shown on the RERA website. After the Government announced clearance of UDCPR 2020, updated Jan. 2023 , FSI clearance work started by our Architect and we have applied in the government town planning department- palghar in December 2022 and at the same time we also apply in RERA for ex…”30 March 2025
Extended at the builder's request (MahaRERA application EXT99000024215)
Reason the builder gave MahaRERA:
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints.…” Read the full reason
“We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. As of now, 91% of the project is completed. We are in the final stages and will apply for the Occupancy Certificate once the remaining work is finished. We are closely monitoring progress and taking all necessary steps to ensure timely completion. In…”
Source: Anand Park Mamta Heights’s extension records on MahaRERA (P99000004112), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Anand Park Mamta Heights
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the March 2025 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000004112
- Status
- Completed
- Builder
- Sachin Shantilal Joshi
- Location
- Boisar, Palghar · 401501
- Project type
- Residential / Group Housing
- Registered on
- 8 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- March 2025
- Delay so far
- 63 months
- Homes
- 75
- Towers
- 2
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Anand Park Mamta Heights, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building No 1 Dharmi | 100% | 100% | 100% | 0% |
| Building No 2 Zeal | 100% | 100% | 95% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Anand Park Mamta Heights every month.
Anand Park Mamta Heights: buildings, flats and land, as filed on MahaRERA
- Buildings: Building No 1 Dharmi (5 floors) · Building No 2 Zeal (6 floors)
- Land: 2,480 sq m (about 0.6 acres) · sanctioned built-up 1,855 sq m · recreational space 248 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Anand Park Mamta Heights →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Anand Park Mamta Heights: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Anand Park Mamta Heights
What is the possession date of Anand Park Mamta Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Anand Park Mamta Heights in Boisar, Palghar is 30 March 2025 — 63 months later than 30 December 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Anand Park Mamta Heights?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Anand Park Mamta Heights's builder has filed on MahaRERA, the official one, is 30 March 2025, already 63 months later than the 30 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Anand Park Mamta Heights extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Anand Park Mamta Heights's builder applied to MahaRERA to extend the completion date 5 times: to 30 December 2020, giving the reason "Respected Sir/Madam We have a ongoing project at Survey No/Gut No. 2 of Village Maan Taluka & Dist: Palghar. Registered with Rera under the Rera Act vide Number . P99000004112 The completion date for this project at time of registration was given as 30.12.2019.Now after revision in DCR in the region we are now elegible for additional FSI as per the sanctioned DCR and accordingly we have submitted a revised proposal to the collector Palghar ( Planning Authority) for revision in the plans as per prevailing rules and regulations. The requisite Challans payable to GOM for the revision of plans…"; to 30 June 2022, giving the reason "To, Rera Authority, SUBJECT: EXTENSION OF RERA DATE Sir/ Madam, My Project registered under RERA Reg No: P99000004112 & site situated at Boisar, Maan village, Dist Palghar, project known as Anand Park, had been given a Rera Due till 30/6/2021. My site was working in full swing till the Pandemic, Covid 19 started. Due to the lockdown, we had to stop work for sometime according to the Government guidelines. Thereafter, as per the new guidelines, work started slowly with minimum workers and staff. My office is located at Mumbai and the distance is almost 195 to 200 kilometres from office to si…"; to 30 December 2023, giving the reason "To, Rera Authority, SUBJECT: EXTENSION OF RERA Sir/ Madam, We have obtained development permission and registered our project of Residential Buildings at Boisar, District Palghar. Project Reg No: P99000004112 in the name of project Anand Park.The Due Date of Rera Certificate is till 30/12/2022. Our work is in progress as on date. My site was working in full swing before Pandemic, as per the new guidelines work started slowly with minimum workers and staff according to the government guidelines. Building number 1, is almost 100% ready building cleaning & finishing is ongoing. Expected posses…"; to 30 June 2024, giving the reason "To, Rera Authority, SUBJECT: REVISE EXTENSION DATE OF RERA CERTIFICATE Sir/ Madam, My site is situated at Boisar, District Palghar. Project Reg No: P99000004112. The name of the project is Anand Park. It had been given a Rera Due till 30/12/2023. As per my RERA submission, my balance FSI is pending. It is also shown on the RERA website. After the Government announced clearance of UDCPR 2020, updated Jan. 2023 , FSI clearance work started by our Architect and we have applied in the government town planning department- palghar in December 2022 and at the same time we also apply in RERA for ex…"; to 30 March 2025, giving the reason "We apologize for the delay in the completion of the project and the submission of this request. The delay has occurred due to issues with procurement, unforeseen site conditions, coordination challenges and temporary financial constraints. Despite these setbacks, we are working diligently to address these issues and complete the remaining work. As of now, 91% of the project is completed. We are in the final stages and will apply for the Occupancy Certificate once the remaining work is finished. We are closely monitoring progress and taking all necessary steps to ensure timely completion. In…".
What is the RERA number of Anand Park Mamta Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Anand Park Mamta Heights in Boisar, Palghar is P99000004112.
Is Anand Park Mamta Heights registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Anand Park Mamta Heights is registered as P99000004112 and its status is "Completed".
What is the construction status of Anand Park Mamta Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Anand Park Mamta Heights's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Anand Park Mamta Heights have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Anand Park Mamta Heights safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Anand Park Mamta Heights is registered on MahaRERA as P99000004112, its MahaRERA status is "Completed", its completion date has moved 63 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Anand Park Mamta Heights's possession date changes?
The latest dates are on Anand Park Mamta Heights's MahaRERA page (P99000004112). GharKundli's Kundli Watch sends a free WhatsApp update on Anand Park Mamta Heights every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Anand Park Mamta Heights have?
According to GharKundli's check of MahaRERA records (updated October 2026), Anand Park Mamta Heights has 2 buildings filed: Building No 1 Dharmi with 5 floors; Building No 2 Zeal with 6 floors.
How big is the land of Anand Park Mamta Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Anand Park Mamta Heights stands on 2,480 sq m of land (about 0.6 acres), with 1,855 sq m of sanctioned built-up area and 248 sq m of recreational open space.
Where can I read reviews of Anand Park Mamta Heights?
Google Maps has reviews of Anand Park Mamta Heights written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Anand Park Mamta Heights?
Anand Park Mamta Heights by Sachin Shantilal Joshi is in Boisar, Palghar (pincode 401501), Maharashtra, and is registered on MahaRERA as P99000004112, per GharKundli's check of MahaRERA records.
How many homes are in Anand Park Mamta Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), Anand Park Mamta Heights has 75 homes in 2 towers registered on MahaRERA.
When was Anand Park Mamta Heights registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Anand Park Mamta Heights was registered on MahaRERA on 8 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Anand Park Mamta Heights?
No court cases are listed for Anand Park Mamta Heights on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of Anand Park Mamta Heights?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Sachin Shantilal Joshi.
Check it yourself on MahaRERA
- How to check the possession date of Anand Park Mamta Heights
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 401501
- Luxury Empire Township Phase I
- 4TUNE PRIDE
- MAHAVIR SAPPHIRE
- YOSH EMPIRE
- VALUE HOMES
- Shree Aadinath Park
- SHREE GALAXY
- Sai Shraddha Apartment
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.