MADHUBAN PARK

by ADWIK DEVELOPERS · Infotech Park (Hinjawadi), Pune

Possession date of MADHUBAN PARK: 30 December 2023, moved from 30 December 2022 (12 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52100018383. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (December 2023) has passed.

What do you want to know about MADHUBAN PARK?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of MADHUBAN PARK has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 30 December 2023

    Extended at the builder's request (MahaRERA application EXT52100013357)

    Reason the builder gave MahaRERA: “DUE TO COVID 19 AND LABOUR SHORTAGE”

Source: MADHUBAN PARK’s extension records on MahaRERA (P52100018383), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on MADHUBAN PARK

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100018383
Status
Lapsed (registration period ended)
Builder
ADWIK DEVELOPERS
Location
Infotech Park (Hinjawadi), Pune · 411057
Project type
Residential / Group Housing
Registered on
26 Oct 2018
Completion date at registration
December 2022
Latest completion date
December 2023
Delay so far
12 months
Homes
54
Towers
2
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of MADHUBAN PARK, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING A100%33%0%0%
BUILDING B100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on MADHUBAN PARK every month.

MADHUBAN PARK: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING A (5 floors) · BUILDING B (5 floors)
  • Land: 1,700 sq m (about 0.4 acres) · sanctioned built-up 2,013 sq m
  • Boundaries filed include: RAKESH BARNE ROAD, UHLAS DHUMAL ROAD

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of MADHUBAN PARK →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

MADHUBAN PARK: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about MADHUBAN PARK

What is the possession date of MADHUBAN PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for MADHUBAN PARK in Infotech Park (Hinjawadi), Pune is 30 December 2023 — 12 months later than 30 December 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for MADHUBAN PARK?

Builders and listing sites often quote an earlier "target" date for handover. The completion date MADHUBAN PARK's builder has filed on MahaRERA, the official one, is 30 December 2023, already 12 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of MADHUBAN PARK extended?

According to GharKundli's check of MahaRERA records (updated November 2026), MADHUBAN PARK's builder applied to MahaRERA to extend the completion date once: to 30 December 2023, giving the reason "DUE TO COVID 19 AND LABOUR SHORTAGE".

What is the RERA number of MADHUBAN PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of MADHUBAN PARK in Infotech Park (Hinjawadi), Pune is P52100018383.

Is MADHUBAN PARK registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), MADHUBAN PARK is registered as P52100018383 and its status is "Lapsed (registration period ended)".

What is the construction status of MADHUBAN PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), MADHUBAN PARK's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work ranges from 33% to 100% across 2 towers. GharKundli's full report compares construction progress with the deadline.

Does MADHUBAN PARK have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is MADHUBAN PARK safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), MADHUBAN PARK is registered on MahaRERA as P52100018383, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if MADHUBAN PARK's possession date changes?

The latest dates are on MADHUBAN PARK's MahaRERA page (P52100018383). GharKundli's Kundli Watch sends a free WhatsApp update on MADHUBAN PARK every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does MADHUBAN PARK have?

According to GharKundli's check of MahaRERA records (updated November 2026), MADHUBAN PARK has 2 buildings filed: BUILDING A with 5 floors; BUILDING B with 5 floors.

How big is the land of MADHUBAN PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), MADHUBAN PARK stands on 1,700 sq m of land (about 0.4 acres), with 2,013 sq m of sanctioned built-up area.

Where can I read reviews of MADHUBAN PARK?

Google Maps has reviews of MADHUBAN PARK written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is MADHUBAN PARK?

MADHUBAN PARK by ADWIK DEVELOPERS is in Infotech Park (Hinjawadi), Pune (pincode 411057), Maharashtra, and is registered on MahaRERA as P52100018383, per GharKundli's check of MahaRERA records. Its boundaries filed there include RAKESH BARNE ROAD, UHLAS DHUMAL ROAD.

How many homes are in MADHUBAN PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), MADHUBAN PARK has 54 homes in 2 towers registered on MahaRERA.

When was MADHUBAN PARK registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), MADHUBAN PARK was registered on MahaRERA on 26 October 2018. GharKundli did not find a title report on the land on file there.

Are there court cases on MADHUBAN PARK?

No court cases are listed for MADHUBAN PARK on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of MADHUBAN PARK?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ADWIK DEVELOPERS.