Mangal Vishwa - Phase 2
by G.T.DEVELOPERS · Kiwale, PuneAlso near Dehu Road Cantt
Possession: Mangal Vishwa - Phase 2 is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100018839. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Mangal Vishwa - Phase 2?
How the possession date of Mangal Vishwa - Phase 2 has moved
30 December 2022
Completion date given when the project was registered
30 December 2023
Extended at the builder's request (MahaRERA application EXT52100013550)
Reason the builder gave MahaRERA:
“As Per a new Article /GR /rule published by Ministry of Defence regarding Red zone in the surrounding area ,the building permission department has put hold on further cases for time being and hence we need to apply for the extension of the…” Read the full reason
“As Per a new Article /GR /rule published by Ministry of Defence regarding Red zone in the surrounding area ,the building permission department has put hold on further cases for time being and hence we need to apply for the extension of the dates for our project ‘Mangal Vishwa Phase 2’ . Detailed description of the same is mentioned in Form E.”
Source: Mangal Vishwa - Phase 2’s extension records on MahaRERA (P52100018839), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Mangal Vishwa - Phase 2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2023 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Mangal Vishwa - Phase 1P52100003611
- MahaRERA registration
- P52100018839
- Status
- Completed
- Builder
- G.T.DEVELOPERS
- Location
- Kiwale, Pune · 412101
- Project type
- Others
- Registered on
- 6 Dec 2018
- Completion date at registration
- December 2022
- Latest completion date
- December 2023
- Delay so far
- 12 months
- Homes
- 89
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of Mangal Vishwa - Phase 2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Building B | 100% | 100% | 100% | 100% |
| Building A | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Mangal Vishwa - Phase 2 every month.
Mangal Vishwa - Phase 2: buildings, flats and land, as filed on MahaRERA
- Buildings: Building B (13 floors) · Building A (13 floors)
- Land: 7,800 sq m (about 1.9 acres) · sanctioned built-up 1,913 sq m · recreational space 736 sq m
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Mangal Vishwa - Phase 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Mangal Vishwa - Phase 2: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Mangal Vishwa - Phase 2
What is the possession date of Mangal Vishwa - Phase 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Mangal Vishwa - Phase 2 in Kiwale, Pune is 30 December 2023 — 12 months later than 30 December 2022, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Mangal Vishwa - Phase 2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Mangal Vishwa - Phase 2's builder has filed on MahaRERA, the official one, is 30 December 2023, already 12 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Mangal Vishwa - Phase 2 extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Mangal Vishwa - Phase 2's builder applied to MahaRERA to extend the completion date once: to 30 December 2023, giving the reason "As Per a new Article /GR /rule published by Ministry of Defence regarding Red zone in the surrounding area ,the building permission department has put hold on further cases for time being and hence we need to apply for the extension of the dates for our project ‘Mangal Vishwa Phase 2’ . Detailed description of the same is mentioned in Form E.".
What is the RERA number of Mangal Vishwa - Phase 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Mangal Vishwa - Phase 2 in Kiwale, Pune is P52100018839.
Is Mangal Vishwa - Phase 2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Mangal Vishwa - Phase 2 is registered as P52100018839 and its status is "Completed".
What is the construction status of Mangal Vishwa - Phase 2?
According to GharKundli's check of MahaRERA records (updated November 2026), Mangal Vishwa - Phase 2's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does Mangal Vishwa - Phase 2 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Mangal Vishwa - Phase 2 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Mangal Vishwa - Phase 2 is registered on MahaRERA as P52100018839, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does Mangal Vishwa - Phase 2 have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Mangal Vishwa - Phase 1 (P52100003611). Check that your agreement names the registration of your own wing.
How can I get updates if Mangal Vishwa - Phase 2's possession date changes?
The latest dates are on Mangal Vishwa - Phase 2's MahaRERA page (P52100018839). GharKundli's Kundli Watch sends a free WhatsApp update on Mangal Vishwa - Phase 2 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Mangal Vishwa - Phase 2 have?
According to GharKundli's check of MahaRERA records (updated November 2026), Mangal Vishwa - Phase 2 has 2 buildings filed: Building B with 13 floors; Building A with 13 floors.
How big is the land of Mangal Vishwa - Phase 2?
According to GharKundli's check of MahaRERA records (updated November 2026), Mangal Vishwa - Phase 2 stands on 7,800 sq m of land (about 1.9 acres), with 1,913 sq m of sanctioned built-up area and 736 sq m of recreational open space.
Where can I read reviews of Mangal Vishwa - Phase 2?
Google Maps has reviews of Mangal Vishwa - Phase 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Mangal Vishwa - Phase 2?
Mangal Vishwa - Phase 2 by G.T.DEVELOPERS is in Kiwale, Pune (pincode 412101), near Dehu Road Cantt, Maharashtra, and is registered on MahaRERA as P52100018839, per GharKundli's check of MahaRERA records.
How many homes are in Mangal Vishwa - Phase 2?
According to GharKundli's check of MahaRERA records (updated November 2026), Mangal Vishwa - Phase 2 has 89 homes in 2 towers registered on MahaRERA.
When was Mangal Vishwa - Phase 2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Mangal Vishwa - Phase 2 was registered on MahaRERA on 6 December 2018. GharKundli did not find a title report on the land on file there.
Are there court cases on Mangal Vishwa - Phase 2?
No court cases are listed for Mangal Vishwa - Phase 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Mangal Vishwa - Phase 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is G.T.DEVELOPERS, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Mangal Vishwa - Phase 2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in pincode 412101
- Kedar Residency
- SHRUTI ANANTA
- SMRUTI GARDEN
- Skyway Elite
- Palm Spring D Wing
- Kesar Kalhaar
- SAI PALLADIUM
- IMPERIAL RESIDENCY
Other projects by G.T.DEVELOPERS
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.