Abm Homes Phase 2
by ABM ASSOCIATES · Dhanori, Pune 411015Also near Dighi Camp
What’s in the report? →Possession date of Abm Homes Phase 2 (MahaRERA P52100020775): 28 February 2021, and it has already passed. It has 3 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100020775. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P52100020775, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (February 2021) has passed.
What do you want to know about Abm Homes Phase 2?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
GharKundli’s full report on Abm Homes Phase 2
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the February 2021 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- ABM HOMESP52100008869 · possession 30 Mar 2018
- MahaRERA registration
- P52100020775
- Status
- Lapsed (registration period ended)
- Builder
- ABM ASSOCIATES
- Location
- Dhanori, Pune · 411015
- Project type
- Residential / Group Housing
- Registered on
- 9 May 2019
- Completion date at registration
- February 2021
- Latest completion date
- February 2021
- Homes
- 3
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of Abm Homes Phase 2, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING B | 0% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Abm Homes Phase 2 every 1–2 months.
Abm Homes Phase 2: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING B (3 floors)
- Land: 930 sq m (about 0.2 acres) · sanctioned built-up 119 sq m
- Boundaries filed include: LOTUS CO OP HOUSING SOCIETY
- Land, as filed: 19/4
- Map: Get directions
The builder’s record and reviews
ABM Associates has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 lapsed. No complaints on MahaRERA.
Read Google reviews of Abm Homes Phase 2 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Abm Homes Phase 2: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Abm Homes Phase 2
What is the possession date of Abm Homes Phase 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Abm Homes Phase 2 in Dhanori, Pune is 28 February 2021. That date has already passed.
Is the builder's possession date different from the MahaRERA date for Abm Homes Phase 2?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Abm Homes Phase 2's builder has filed on MahaRERA, the official one, is 28 February 2021, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Abm Homes Phase 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Abm Homes Phase 2 in Dhanori, Pune is P52100020775.
Is Abm Homes Phase 2 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Abm Homes Phase 2 is registered as P52100020775 and its status is "Lapsed (registration period ended)".
What is the current construction status of Abm Homes Phase 2? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), Abm Homes Phase 2's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on BUILDING B is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.
Does Abm Homes Phase 2 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Abm Homes Phase 2 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Abm Homes Phase 2 is registered on MahaRERA as P52100020775, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Abm Homes Phase 2?
Abm Homes Phase 2 isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Abm Homes Phase 2?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Abm Homes Phase 2: gharkundli.com/tools/property-cost-calculator
Has Abm Homes Phase 2 received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), Abm Homes Phase 2 isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 28 February 2021 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for Abm Homes Phase 2?
According to GharKundli's check of MahaRERA records (updated November 2026), Abm Homes Phase 2's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (28 February 2021) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has Abm Homes Phase 2 uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Abm Homes Phase 2 was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
Does Abm Homes Phase 2 have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: ABM HOMES (P52100008869, possession 30 Mar 2018). Check that your agreement names the registration of your own wing.
How can I get updates if Abm Homes Phase 2's possession date changes?
The latest dates are on Abm Homes Phase 2's MahaRERA page (P52100020775). GharKundli's Kundli Watch sends a free WhatsApp update on Abm Homes Phase 2 every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Abm Homes Phase 2 have?
According to GharKundli's check of MahaRERA records (updated November 2026), Abm Homes Phase 2 has one building filed: BUILDING B with 3 floors.
How big is the land of Abm Homes Phase 2?
According to GharKundli's check of MahaRERA records (updated November 2026), Abm Homes Phase 2 stands on 930 sq m of land (about 0.2 acres), with 119 sq m of sanctioned built-up area.
What is the track record of Abm Homes Phase 2's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), ABM Associates has 2 projects on MahaRERA since 2017, this one included. Of the 2 GharKundli has checked: 1 finished, all within the promised date; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of Abm Homes Phase 2?
Google Maps has reviews of Abm Homes Phase 2 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Abm Homes Phase 2?
Abm Homes Phase 2 by ABM ASSOCIATES is in Dhanori, Pune, pincode 411015 (near Dighi Camp), Maharashtra, and is registered on MahaRERA as P52100020775, per GharKundli's check of MahaRERA records. Its boundaries filed there include LOTUS CO OP HOUSING SOCIETY. Its land is filed as 19/4. GharKundli lists all 267 MahaRERA projects in Dhanori (411015).
How many flats are in Abm Homes Phase 2?
According to GharKundli's check of MahaRERA records (updated November 2026), Abm Homes Phase 2 has 3 homes in 1 tower registered on MahaRERA.
When was Abm Homes Phase 2 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Abm Homes Phase 2 was registered on MahaRERA on 9 May 2019. GharKundli did not find a title report on the land on file there.
Does Abm Homes Phase 2 have any legal issues or court cases?
No court cases are listed for Abm Homes Phase 2 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of Abm Homes Phase 2?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is ABM ASSOCIATES, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of Abm Homes Phase 2
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Dhanori (411015)
- Vedanta
- Sparkle Enclave
- Della Regency
- Kohinoor Viva Pixel- Phase II
- Ganga Newtown PH 6 F BLDG
- Que 101 Phase I
- Nyati Era III
- Ujwal Tower
Other projects by ABM ASSOCIATES
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.