Skip to content
GharKundli

FOUR SQUARE

by FOUR SQUARE BUILDERS AND DEVELOPERS · Chikhali, PuneAlso near Rupeenagar, Chinchwad East, Akurdi

Possession date of FOUR SQUARE: 24 April 2024, moved from 30 May 2022 (23 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52100022537. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (April 2024) has passed.

What do you want to know about FOUR SQUARE?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of FOUR SQUARE has moved

  1. 30 May 2022

    Completion date given when the project was registered

  2. 30 April 2023

    Extended at the builder's request (MahaRERA application EXT52100012506)

    Reason the builder gave MahaRERA: “No single unit booked and sold till the date also there is revision in the sanction plan dated 15 06 2022 ( witch is enclosed herewith)”
  3. 24 April 2024

    Extended at the builder's request (MahaRERA application EXT52100016476)

    Reason the builder gave MahaRERA: “No sales booking due to which there is delay in the project for the fund arrangements we request honor to extent the project period till the 24/04/2024”

Source: FOUR SQUARE’s extension records on MahaRERA (P52100022537), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on FOUR SQUARE

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100022537
Status
Lapsed (registration period ended)
Builder
FOUR SQUARE BUILDERS AND DEVELOPERS
Location
Chikhali, Pune · 411062
Project type
Others
Registered on
1 Oct 2019
Completion date at registration
May 2022
Latest completion date
April 2024
Delay so far
23 months
Homes
51
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of FOUR SQUARE, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
FOR SQUARE BULIDERS AND DEVELOPERS100%100%100%60%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on FOUR SQUARE every month.

FOUR SQUARE: buildings, flats and land, as filed on MahaRERA

  • Buildings: FOR SQUARE BULIDERS AND DEVELOPERS (7 floors)
  • Land: 1,395 sq m (about 0.3 acres) · sanctioned built-up 1,106 sq m · recreational space 1,395 sq m
  • Boundaries filed include: DEHU ALANDI ROAD

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of FOUR SQUARE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

FOUR SQUARE: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about FOUR SQUARE

What is the possession date of FOUR SQUARE?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for FOUR SQUARE in Chikhali, Pune is 24 April 2024 — 23 months later than 30 May 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for FOUR SQUARE?

Builders and listing sites often quote an earlier "target" date for handover. The completion date FOUR SQUARE's builder has filed on MahaRERA, the official one, is 24 April 2024, already 23 months later than the 30 May 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of FOUR SQUARE extended?

According to GharKundli's check of MahaRERA records (updated November 2026), FOUR SQUARE's builder applied to MahaRERA to extend the completion date 2 times: to 30 April 2023, giving the reason "No single unit booked and sold till the date also there is revision in the sanction plan dated 15 06 2022 ( witch is enclosed herewith)"; to 24 April 2024, giving the reason "No sales booking due to which there is delay in the project for the fund arrangements we request honor to extent the project period till the 24/04/2024".

What is the RERA number of FOUR SQUARE?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of FOUR SQUARE in Chikhali, Pune is P52100022537.

Is FOUR SQUARE registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), FOUR SQUARE is registered as P52100022537 and its status is "Lapsed (registration period ended)".

What is the construction status of FOUR SQUARE?

According to GharKundli's check of MahaRERA records (updated November 2026), FOUR SQUARE's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on FOR SQUARE BULIDERS AND DEVELOPERS is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does FOUR SQUARE have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is FOUR SQUARE safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), FOUR SQUARE is registered on MahaRERA as P52100022537, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 23 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if FOUR SQUARE's possession date changes?

The latest dates are on FOUR SQUARE's MahaRERA page (P52100022537). GharKundli's Kundli Watch sends a free WhatsApp update on FOUR SQUARE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does FOUR SQUARE have?

According to GharKundli's check of MahaRERA records (updated November 2026), FOUR SQUARE has one building filed: FOR SQUARE BULIDERS AND DEVELOPERS with 7 floors.

How big is the land of FOUR SQUARE?

According to GharKundli's check of MahaRERA records (updated November 2026), FOUR SQUARE stands on 1,395 sq m of land (about 0.3 acres), with 1,106 sq m of sanctioned built-up area and 1,395 sq m of recreational open space.

Where can I read reviews of FOUR SQUARE?

Google Maps has reviews of FOUR SQUARE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is FOUR SQUARE?

FOUR SQUARE by FOUR SQUARE BUILDERS AND DEVELOPERS is in Chikhali, Pune (pincode 411062), near Rupeenagar, Chinchwad East, Akurdi, Maharashtra, and is registered on MahaRERA as P52100022537, per GharKundli's check of MahaRERA records. Its boundaries filed there include DEHU ALANDI ROAD.

How many homes are in FOUR SQUARE?

According to GharKundli's check of MahaRERA records (updated November 2026), FOUR SQUARE has 51 homes in 1 tower registered on MahaRERA.

When was FOUR SQUARE registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), FOUR SQUARE was registered on MahaRERA on 1 October 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on FOUR SQUARE?

No court cases are listed for FOUR SQUARE on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of FOUR SQUARE?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is FOUR SQUARE BUILDERS AND DEVELOPERS.

Other projects in pincode 411062

All 112 projects in Chikhali (411062) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.