Skip to content
GharKundli

Dolphin Vista

by MAHALAXMI ENTERPRISES (Dolphin) · Chikhali, Pune 411062Also near Chinchwad East

What’s in the report? →

Possession: Dolphin Vista (MahaRERA P52100025219) is marked completed on MahaRERA. It has 29 homes. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100025219. Status: Completed.

Source: MahaRERA website — records for P52100025219, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Dolphin Vista?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Dolphin Vista

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2022 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100025219
Status
Completed
Builder
MAHALAXMI ENTERPRISES
Location
Chikhali, Pune · 411062
Project type
Others
Registered on
23 Mar 2020
Completion date at registration
December 2022
Latest completion date
December 2022
Homes
29
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
5

Construction progress of Dolphin Vista, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
DOLPHIN VISTA100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Dolphin Vista every 1–2 months.

Dolphin Vista: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Dolphin Buildcon (a group of 11 linked companies) has 16 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 10 finished, 6 within the promised date and 4 needed more time (typically 10 months); 5 still being built, none past the promised date yet; 1 lapsed. 1 complaint on MahaRERA across 1 project.

Read Google reviews of Dolphin Vista →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Dolphin Vista: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Dolphin Vista

What is the possession date of Dolphin Vista?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Dolphin Vista in Chikhali, Pune is 30 December 2022.

Is the builder's possession date different from the MahaRERA date for Dolphin Vista?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Dolphin Vista's builder has filed on MahaRERA, the official one, is 30 December 2022, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Dolphin Vista?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Dolphin Vista in Chikhali, Pune is P52100025219.

Is Dolphin Vista registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Dolphin Vista is registered as P52100025219 and its status is "Completed".

What is the current construction status of Dolphin Vista? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Dolphin Vista's status on MahaRERA is "Completed". As filed by the builder, slab work on DOLPHIN VISTA is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Dolphin Vista have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Dolphin Vista safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Dolphin Vista is registered on MahaRERA as P52100025219, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Dolphin Vista?

According to GharKundli's check of MahaRERA records (updated November 2026), Dolphin Vista is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Dolphin Vista?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Dolphin Vista: gharkundli.com/tools/property-cost-calculator

Has Dolphin Vista received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Dolphin Vista is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Dolphin Vista completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Dolphin Vista is marked completed on MahaRERA, and the completion date filed there is 30 December 2022. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Dolphin Vista uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Dolphin Vista was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Dolphin Vista's possession date changes?

The latest dates are on Dolphin Vista's MahaRERA page (P52100025219). GharKundli's Kundli Watch sends a free WhatsApp update on Dolphin Vista every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Dolphin Vista have?

According to GharKundli's check of MahaRERA records (updated November 2026), Dolphin Vista has one building filed: DOLPHIN VISTA with 9 floors.

How big is the land of Dolphin Vista?

According to GharKundli's check of MahaRERA records (updated November 2026), Dolphin Vista stands on 1,277 sq m of land (about 0.3 acres), with 2,748 sq m of sanctioned built-up area.

What is the track record of Dolphin Vista's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Dolphin Buildcon (a group of 11 linked companies) has 16 projects on MahaRERA since 2017, this one included. Of the 16 GharKundli has checked: 10 finished, 6 within the promised date and 4 needed more time (typically 10 months); 5 still being built, none past the promised date yet; 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

What are the reviews of Dolphin Vista?

Google Maps has reviews of Dolphin Vista written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Dolphin Vista?

Dolphin Vista by MAHALAXMI ENTERPRISES (Dolphin) is in Chikhali, Pune, pincode 411062 (near Chinchwad East), Maharashtra, and is registered on MahaRERA as P52100025219, per GharKundli's check of MahaRERA records. Its land is filed as CDC-33. GharKundli lists all 193 MahaRERA projects in Chikhali (411062).

How many flats are in Dolphin Vista?

According to GharKundli's check of MahaRERA records (updated November 2026), Dolphin Vista has 29 homes in 1 tower registered on MahaRERA.

When was Dolphin Vista registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Dolphin Vista was registered on MahaRERA on 23 March 2020. GharKundli did not find a title report on the land on file there.

Does Dolphin Vista have any legal issues or court cases?

No court cases are listed for Dolphin Vista on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Dolphin Vista?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MAHALAXMI ENTERPRISES, the company Dolphin files this project under, which has 5 other projects registered on MahaRERA.

Other projects in Chikhali (411062)

All 193 projects in Chikhali (411062) →

Other projects by MAHALAXMI ENTERPRISES

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.