SUPREME POINT PHASE I
by K K INFRASTRUCUTRE · Panchbatti, PalgharAlso near Palghar East, navali village, Vevoor
Possession: SUPREME POINT PHASE I is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P99000002058. Status: Completed.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about SUPREME POINT PHASE I?
How the possession date of SUPREME POINT PHASE I has moved
30 April 2018
Completion date given when the project was registered
29 November 2018
Extended at the builder's request (MahaRERA application EXT99000010993)
Reason the builder gave MahaRERA:
“WE HAD APPLIED FOR OC PRIOR TO COMPLETION DATE 30/04/2018 BUT WE RECEIVED OC IN NOVEMBER 2018 . WE HAD GIVEN POSSESSION TO THE CUSTOMERS ON TIME AS PER OUR COMMITTMENTS. THE SAID CUSTOMERS HAVE TAKEN PEACEFUL POSSESSION AFTER THEIR FULL SAT…” Read the full reason
“WE HAD APPLIED FOR OC PRIOR TO COMPLETION DATE 30/04/2018 BUT WE RECEIVED OC IN NOVEMBER 2018 . WE HAD GIVEN POSSESSION TO THE CUSTOMERS ON TIME AS PER OUR COMMITTMENTS. THE SAID CUSTOMERS HAVE TAKEN PEACEFUL POSSESSION AFTER THEIR FULL SATISFACTION. 90 % INVENTORY WAS SOLD OUT BEFORE COMPLETION OF THE PROJECT. AS PER PAYMENT CLEARANCE POSESSION WERE DELIVERED TO THE CUSTOMERS.”
Source: SUPREME POINT PHASE I’s extension records on MahaRERA (P99000002058), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SUPREME POINT PHASE I
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the November 2018 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- SUPREME POINT PHASE IIP99000020456
- MahaRERA registration
- P99000002058
- Status
- Completed
- Builder
- K K INFRASTRUCUTRE
- Location
- Panchbatti, Palghar · 401404
- Project type
- Others
- Registered on
- 31 Jul 2017
- Completion date at registration
- April 2018
- Latest completion date
- November 2018
- Delay so far
- 7 months
- Homes
- 36
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of SUPREME POINT PHASE I, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SP - 2 B /TYPE | 100% | 100% | 100% | 100% |
| SP - 3 D -TYPE | 100% | 100% | 100% | 100% |
| SP -1 D -1 TYPE | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SUPREME POINT PHASE I every month.
SUPREME POINT PHASE I: buildings, flats and land, as filed on MahaRERA
- Buildings: SP - 2 B /TYPE (5 floors) · SP - 3 D -TYPE (3 floors) · SP -1 D -1 TYPE (3 floors)
- Land: 2,545 sq m (about 0.6 acres) · sanctioned built-up 1,909 sq m · recreational space 1,006 sq m
- Boundaries filed include: NAVALI VILLAGE ROAD
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
K K Infrastrucutre (a group of 3 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 9 months); 2 still being built, none past the promised date yet. No complaints on MahaRERA.
Read Google reviews of SUPREME POINT PHASE I →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SUPREME POINT PHASE I: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SUPREME POINT PHASE I
What is the possession date of SUPREME POINT PHASE I?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SUPREME POINT PHASE I in Panchbatti, Palghar is 29 November 2018 — 7 months later than 30 April 2018, the date given at registration.
Is the builder's possession date different from the MahaRERA date for SUPREME POINT PHASE I?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SUPREME POINT PHASE I's builder has filed on MahaRERA, the official one, is 29 November 2018, already 7 months later than the 30 April 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SUPREME POINT PHASE I extended?
According to GharKundli's check of MahaRERA records (updated November 2026), SUPREME POINT PHASE I's builder applied to MahaRERA to extend the completion date once: to 29 November 2018, giving the reason "WE HAD APPLIED FOR OC PRIOR TO COMPLETION DATE 30/04/2018 BUT WE RECEIVED OC IN NOVEMBER 2018 . WE HAD GIVEN POSSESSION TO THE CUSTOMERS ON TIME AS PER OUR COMMITTMENTS. THE SAID CUSTOMERS HAVE TAKEN PEACEFUL POSSESSION AFTER THEIR FULL SATISFACTION. 90 % INVENTORY WAS SOLD OUT BEFORE COMPLETION OF THE PROJECT. AS PER PAYMENT CLEARANCE POSESSION WERE DELIVERED TO THE CUSTOMERS.".
What is the RERA number of SUPREME POINT PHASE I?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SUPREME POINT PHASE I in Panchbatti, Palghar is P99000002058.
Is SUPREME POINT PHASE I registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SUPREME POINT PHASE I is registered as P99000002058 and its status is "Completed".
What is the construction status of SUPREME POINT PHASE I?
According to GharKundli's check of MahaRERA records (updated November 2026), SUPREME POINT PHASE I's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does SUPREME POINT PHASE I have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is SUPREME POINT PHASE I safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SUPREME POINT PHASE I is registered on MahaRERA as P99000002058, its MahaRERA status is "Completed", its completion date has moved 7 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does SUPREME POINT PHASE I have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: SUPREME POINT PHASE II (P99000020456). Check that your agreement names the registration of your own wing.
How can I get updates if SUPREME POINT PHASE I's possession date changes?
The latest dates are on SUPREME POINT PHASE I's MahaRERA page (P99000002058). GharKundli's Kundli Watch sends a free WhatsApp update on SUPREME POINT PHASE I every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SUPREME POINT PHASE I have?
According to GharKundli's check of MahaRERA records (updated November 2026), SUPREME POINT PHASE I has 3 buildings filed: SP - 2 B /TYPE with 5 floors; SP - 3 D -TYPE with 3 floors; SP -1 D -1 TYPE with 3 floors.
How big is the land of SUPREME POINT PHASE I?
According to GharKundli's check of MahaRERA records (updated November 2026), SUPREME POINT PHASE I stands on 2,545 sq m of land (about 0.6 acres), with 1,909 sq m of sanctioned built-up area and 1,006 sq m of recreational open space.
What is the track record of SUPREME POINT PHASE I's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), K K Infrastrucutre (a group of 3 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 4 GharKundli has checked: 2 finished, 0 within the promised date and 2 needed more time (typically 9 months); 2 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of SUPREME POINT PHASE I?
Google Maps has reviews of SUPREME POINT PHASE I written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SUPREME POINT PHASE I?
SUPREME POINT PHASE I by K K INFRASTRUCUTRE is in Panchbatti, Palghar (pincode 401404), near Palghar East, navali village, Vevoor, Maharashtra, and is registered on MahaRERA as P99000002058, per GharKundli's check of MahaRERA records. Its boundaries filed there include NAVALI VILLAGE ROAD.
How many homes are in SUPREME POINT PHASE I?
According to GharKundli's check of MahaRERA records (updated November 2026), SUPREME POINT PHASE I has 36 homes in 3 towers registered on MahaRERA.
When was SUPREME POINT PHASE I registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SUPREME POINT PHASE I was registered on MahaRERA on 31 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SUPREME POINT PHASE I?
No court cases are listed for SUPREME POINT PHASE I on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SUPREME POINT PHASE I?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is K K INFRASTRUCUTRE, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of SUPREME POINT PHASE I
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Palghar
- Elite Residency
- Sunshine Complex
- V SQUARE ARCADE
- Rubicon Shinde Heritage
- KUSUM EKDANT
- PARAMOUNT ENCLAVE PHASE - 2
- SAPPHIRE ENCLAVES BLDG NO 5 TYPE F
- K Bafna Estatess
Other projects by K K INFRASTRUCUTRE
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.