by RISHIRAJ DEVELOPERS PRIVATE LIMITED (Pearl) · Dadar West, MumbaiAlso near Matunga, Dadar East, Wadala
Possession: Pearl Crest is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51900002961. Status: Completed. 2 complaints are listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Pearl Crest?
How the possession date of Pearl Crest has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT51900003645)
Reason the builder gave MahaRERA:
“• The construction of 21 slabs of the structure comprising Ground + 21 floors including Block work till 18 floors is complete and finishes and external infrastructure work is in progress. • The site photographs showing progress of the work…” Read the full reason
“• The construction of 21 slabs of the structure comprising Ground + 21 floors including Block work till 18 floors is complete and finishes and external infrastructure work is in progress. • The site photographs showing progress of the work are enclosed along with this application. • The Promoter submits that they have made genuine efforts but the work couldn’t be completed in time due to liquidity crunch, sluggish sales of the project and delayed payments from customers. • The promoter expects that they will be able to complete the balance work in 6-8 months and will need another 2-3 months…”30 December 2021
Revised completion date on MahaRERA
Source: Pearl Crest’s extension records on MahaRERA (P51900002961), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Pearl Crest
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 2 complaints, and how it ended
- Construction pace against the December 2021 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51900002961
- Status
- Completed
- Builder
- RISHIRAJ DEVELOPERS PRIVATE LIMITED
- Location
- Dadar West, Mumbai · 400014
- Project type
- Residential / Group Housing
- Registered on
- 4 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- December 2021
- Delay so far
- 24 months
- Homes
- 24
- Towers
- 1
- Complaints on MahaRERA
- 2
- Court cases listed
- 0
- Appeals at the tribunal
- 1
- Title report on file
- Not found
Construction progress of Pearl Crest, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| PEARL CREST | 100% | 5% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Pearl Crest every month.
Pearl Crest: buildings, flats and land, as filed on MahaRERA
- Buildings: PEARL CREST (28 floors)
- Land: 594 sq m (about 0.1 acres) · sanctioned built-up 2,030 sq m
- Boundaries filed include: Tilak Road
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Pearl Concept Constructions (a group of 5 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 4 finished, 1 within the promised date and 3 needed more time (typically 23 months); 2 still being built, none past the promised date yet. 19 complaints on MahaRERA across 4 projects.
Read Google reviews of Pearl Crest →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Pearl Crest: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Pearl Crest
What is the possession date of Pearl Crest?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Pearl Crest in Dadar West, Mumbai is 30 December 2021 — 24 months later than 31 December 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for Pearl Crest?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Pearl Crest's builder has filed on MahaRERA, the official one, is 30 December 2021, already 24 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Pearl Crest extended?
According to GharKundli's check of MahaRERA records (updated November 2026), Pearl Crest's builder applied to MahaRERA to extend the completion date once: to 30 December 2020, giving the reason "• The construction of 21 slabs of the structure comprising Ground + 21 floors including Block work till 18 floors is complete and finishes and external infrastructure work is in progress. • The site photographs showing progress of the work are enclosed along with this application. • The Promoter submits that they have made genuine efforts but the work couldn’t be completed in time due to liquidity crunch, sluggish sales of the project and delayed payments from customers. • The promoter expects that they will be able to complete the balance work in 6-8 months and will need another 2-3 months…".
What is the RERA number of Pearl Crest?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Pearl Crest in Dadar West, Mumbai is P51900002961.
Is Pearl Crest registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Pearl Crest is registered as P51900002961 and its status is "Completed".
What is the construction status of Pearl Crest?
According to GharKundli's check of MahaRERA records (updated November 2026), Pearl Crest's status on MahaRERA is "Completed". As filed by the builder, slab work on PEARL CREST is 5% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Pearl Crest have complaints on MahaRERA?
2 complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is Pearl Crest safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Pearl Crest is registered on MahaRERA as P51900002961, its MahaRERA status is "Completed", its completion date has moved 24 months since registration and 2 complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Pearl Crest's possession date changes?
The latest dates are on Pearl Crest's MahaRERA page (P51900002961). GharKundli's Kundli Watch sends a free WhatsApp update on Pearl Crest every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Pearl Crest have?
According to GharKundli's check of MahaRERA records (updated November 2026), Pearl Crest has one building filed: PEARL CREST with 28 floors.
How big is the land of Pearl Crest?
According to GharKundli's check of MahaRERA records (updated November 2026), Pearl Crest stands on 594 sq m of land (about 0.1 acres), with 2,030 sq m of sanctioned built-up area.
What is the track record of Pearl Crest's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Pearl Concept Constructions (a group of 5 linked companies) has 6 projects on MahaRERA since 2017, this one included. Of the 6 GharKundli has checked: 4 finished, 1 within the promised date and 3 needed more time (typically 23 months); 2 still being built, none past the promised date yet. 19 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Pearl Crest?
Google Maps has reviews of Pearl Crest written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 2 complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Pearl Crest?
Pearl Crest by RISHIRAJ DEVELOPERS PRIVATE LIMITED (Pearl) is in Dadar West, Mumbai (pincode 400014), near Matunga, Dadar East, Wadala, Maharashtra, and is registered on MahaRERA as P51900002961, per GharKundli's check of MahaRERA records. Its boundaries filed there include Tilak Road.
How many homes are in Pearl Crest?
According to GharKundli's check of MahaRERA records (updated November 2026), Pearl Crest has 24 homes in 1 tower registered on MahaRERA.
When was Pearl Crest registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Pearl Crest was registered on MahaRERA on 4 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on Pearl Crest?
No court cases are listed for Pearl Crest on MahaRERA, and 1 appeal at the tribunal, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of Pearl Crest?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is RISHIRAJ DEVELOPERS PRIVATE LIMITED, the company Pearl files this project under.
Check it yourself on MahaRERA
- How to check the possession date of Pearl Crest
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data