SHREE KRISHNA RESIDENCY
by shree krishna builders and developers · mahim village, Palghar
Possession date of SHREE KRISHNA RESIDENCY: 30 June 2024, moved from 31 December 2019 (54 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself
Registered on MahaRERA under P99000006341. Status: Lapsed (registration period ended).
Source: GharKundli’s check of MahaRERA records, November 2026.
The latest completion date on MahaRERA (June 2024) has passed.
What do you want to know about SHREE KRISHNA RESIDENCY?
How the possession date of SHREE KRISHNA RESIDENCY has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT99000003996)
Reason the builder gave MahaRERA: “DELAY IN RECEIPT FROM THE CUSTOMER”
30 June 2024
Extended at the builder's request (MahaRERA application EXT99000012343)
Reason the builder gave MahaRERA: “THE PROMOTED HAD APPLIED FOR OCCUPATION CERTIFICATE AND AWAITING FOR ITS APPROVAL”
Source: SHREE KRISHNA RESIDENCY’s extension records on MahaRERA (P99000006341), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on SHREE KRISHNA RESIDENCY
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the June 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P99000006341
- Status
- Lapsed (registration period ended)
- Builder
- shree krishna builders and developers
- Location
- mahim village, Palghar · 401404
- Project type
- Residential / Group Housing
- Registered on
- 14 Aug 2017
- Completion date at registration
- December 2019
- Latest completion date
- June 2024
- Delay so far
- 54 months
- Homes
- 28
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of SHREE KRISHNA RESIDENCY, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SHREE KRISHNA RESIDENCY | 100% | 100% | 25% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on SHREE KRISHNA RESIDENCY every month.
SHREE KRISHNA RESIDENCY: buildings, flats and land, as filed on MahaRERA
- Buildings: SHREE KRISHNA RESIDENCY (6 floors)
- Land: 1,276 sq m (about 0.3 acres) · sanctioned built-up 1,276 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of SHREE KRISHNA RESIDENCY →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
SHREE KRISHNA RESIDENCY: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about SHREE KRISHNA RESIDENCY
What is the possession date of SHREE KRISHNA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for SHREE KRISHNA RESIDENCY in mahim village, Palghar is 30 June 2024 — 54 months later than 31 December 2019, the date given at registration. That date has already passed.
Is the builder's possession date different from the MahaRERA date for SHREE KRISHNA RESIDENCY?
Builders and listing sites often quote an earlier "target" date for handover. The completion date SHREE KRISHNA RESIDENCY's builder has filed on MahaRERA, the official one, is 30 June 2024, already 54 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of SHREE KRISHNA RESIDENCY extended?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE KRISHNA RESIDENCY's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2020, giving the reason "DELAY IN RECEIPT FROM THE CUSTOMER"; to 30 June 2024, giving the reason "THE PROMOTED HAD APPLIED FOR OCCUPATION CERTIFICATE AND AWAITING FOR ITS APPROVAL".
What is the RERA number of SHREE KRISHNA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of SHREE KRISHNA RESIDENCY in mahim village, Palghar is P99000006341.
Is SHREE KRISHNA RESIDENCY registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE KRISHNA RESIDENCY is registered as P99000006341 and its status is "Lapsed (registration period ended)".
What is the construction status of SHREE KRISHNA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE KRISHNA RESIDENCY's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on SHREE KRISHNA RESIDENCY is 100% done and internal work 25%. GharKundli's full report compares construction progress with the deadline.
Does SHREE KRISHNA RESIDENCY have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is SHREE KRISHNA RESIDENCY safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE KRISHNA RESIDENCY is registered on MahaRERA as P99000006341, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 54 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if SHREE KRISHNA RESIDENCY's possession date changes?
The latest dates are on SHREE KRISHNA RESIDENCY's MahaRERA page (P99000006341). GharKundli's Kundli Watch sends a free WhatsApp update on SHREE KRISHNA RESIDENCY every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does SHREE KRISHNA RESIDENCY have?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE KRISHNA RESIDENCY has one building filed: SHREE KRISHNA RESIDENCY with 6 floors.
How big is the land of SHREE KRISHNA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE KRISHNA RESIDENCY stands on 1,276 sq m of land (about 0.3 acres), with 1,276 sq m of sanctioned built-up area.
Where can I read reviews of SHREE KRISHNA RESIDENCY?
Google Maps has reviews of SHREE KRISHNA RESIDENCY written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is SHREE KRISHNA RESIDENCY?
SHREE KRISHNA RESIDENCY by shree krishna builders and developers is in mahim village, Palghar (pincode 401404), Maharashtra, and is registered on MahaRERA as P99000006341, per GharKundli's check of MahaRERA records.
How many homes are in SHREE KRISHNA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE KRISHNA RESIDENCY has 28 homes in 1 tower registered on MahaRERA.
When was SHREE KRISHNA RESIDENCY registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), SHREE KRISHNA RESIDENCY was registered on MahaRERA on 14 August 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on SHREE KRISHNA RESIDENCY?
No court cases are listed for SHREE KRISHNA RESIDENCY on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of SHREE KRISHNA RESIDENCY?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is shree krishna builders and developers.
Check it yourself on MahaRERA
- How to check the possession date of SHREE KRISHNA RESIDENCY
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Palghar
- Elite Residency
- Sunshine Complex
- Rubicon Shinde Heritage
- V SQUARE ARCADE
- KUSUM EKDANT
- PARAMOUNT ENCLAVE PHASE - 2
- SAPPHIRE ENCLAVES BLDG NO 5 TYPE F
- K Bafna Estatess
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.