Vision Ace MHADA

by VISION ACE · Chinchwadgaon, PuneAlso near Tathawade, Wakad

Possession: Vision Ace MHADA is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100026135. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Vision Ace MHADA?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Vision Ace MHADA has moved

  1. 30 October 2022

    Completion date given when the project was registered

  2. 30 October 2023

    Extended at the builder's request (MahaRERA application EXT52100012817)

    Reason the builder gave MahaRERA:
    “In the current pandemic COVID-19, there has been lockdown at certain intervals declared either by the central government (March 2020 to July 2020) or state government (April 15 2021 to May 31 2021). Due to this, there has been a big challen…” Read the full reason“In the current pandemic COVID-19, there has been lockdown at certain intervals declared either by the central government (March 2020 to July 2020) or state government (April 15 2021 to May 31 2021). Due to this, there has been a big challenge for the availability of labour and materials for the construction site. Thus the work of the project has been severally impacted.”

Source: Vision Ace MHADA’s extension records on MahaRERA (P52100026135), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Vision Ace MHADA

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100026135
Status
Completed
Builder
VISION ACE
Location
Chinchwadgaon, Pune · 411033
Project type
Residential / Group Housing
Registered on
21 Aug 2020
Completion date at registration
October 2022
Latest completion date
October 2023
Delay so far
12 months
Homes
47
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of Vision Ace MHADA, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
WING G100%100%50%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Vision Ace MHADA every month.

Vision Ace MHADA: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Jhamtani Realty (a group of 8 linked companies) has 32 projects on MahaRERA since 2020, this one included. Of the 18 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 5 months); 14 still being built, 2 past the promised date (typically 18 months late); 1 lapsed. 14 complaints on MahaRERA across 4 projects.

Read Google reviews of Vision Ace MHADA →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Vision Ace MHADA: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Vision Ace MHADA

What is the possession date of Vision Ace MHADA?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Vision Ace MHADA in Chinchwadgaon, Pune is 30 October 2023 — 12 months later than 30 October 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Vision Ace MHADA?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Vision Ace MHADA's builder has filed on MahaRERA, the official one, is 30 October 2023, already 12 months later than the 30 October 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Vision Ace MHADA extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Vision Ace MHADA's builder applied to MahaRERA to extend the completion date once: to 30 October 2023, giving the reason "In the current pandemic COVID-19, there has been lockdown at certain intervals declared either by the central government (March 2020 to July 2020) or state government (April 15 2021 to May 31 2021). Due to this, there has been a big challenge for the availability of labour and materials for the construction site. Thus the work of the project has been severally impacted.".

What is the RERA number of Vision Ace MHADA?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Vision Ace MHADA in Chinchwadgaon, Pune is P52100026135.

Is Vision Ace MHADA registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Vision Ace MHADA is registered as P52100026135 and its status is "Completed".

What is the construction status of Vision Ace MHADA?

According to GharKundli's check of MahaRERA records (updated November 2026), Vision Ace MHADA's status on MahaRERA is "Completed". As filed by the builder, slab work on WING G is 100% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.

Does Vision Ace MHADA have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Vision Ace MHADA safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Vision Ace MHADA is registered on MahaRERA as P52100026135, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Vision Ace MHADA's possession date changes?

The latest dates are on Vision Ace MHADA's MahaRERA page (P52100026135). GharKundli's Kundli Watch sends a free WhatsApp update on Vision Ace MHADA every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Vision Ace MHADA have?

According to GharKundli's check of MahaRERA records (updated November 2026), Vision Ace MHADA has one building filed: WING G with 13 floors.

How big is the land of Vision Ace MHADA?

According to GharKundli's check of MahaRERA records (updated November 2026), Vision Ace MHADA stands on 1,255 sq m of land (about 0.3 acres), with 2,221 sq m of sanctioned built-up area and 125 sq m of recreational open space.

What is the track record of Vision Ace MHADA's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Jhamtani Realty (a group of 8 linked companies) has 32 projects on MahaRERA since 2020, this one included. Of the 18 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 5 months); 14 still being built, 2 past the promised date (typically 18 months late); 1 lapsed. 14 complaints on MahaRERA across 4 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Vision Ace MHADA?

Google Maps has reviews of Vision Ace MHADA written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Vision Ace MHADA?

Vision Ace MHADA by VISION ACE is in Chinchwadgaon, Pune (pincode 411033), near Tathawade, Wakad, Maharashtra, and is registered on MahaRERA as P52100026135, per GharKundli's check of MahaRERA records.

How many homes are in Vision Ace MHADA?

According to GharKundli's check of MahaRERA records (updated November 2026), Vision Ace MHADA has 47 homes in 1 tower registered on MahaRERA.

When was Vision Ace MHADA registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Vision Ace MHADA was registered on MahaRERA on 21 August 2020. GharKundli did not find a title report on the land on file there.

Are there court cases on Vision Ace MHADA?

No court cases are listed for Vision Ace MHADA on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Vision Ace MHADA?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is VISION ACE, which has 3 other projects registered on MahaRERA.