Skip to content
GharKundli

Yashwin SukhNiwas

by GROWISA ADVISORS · Hinjawadi, Pune 411057

What’s in the report? →

Possession: Yashwin SukhNiwas (MahaRERA P52100025982) is marked completed on MahaRERA. No complaints on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100025982. Status: Completed.

Source: MahaRERA website — records for P52100025982, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.

What do you want to know about Yashwin SukhNiwas?

Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.

Ask something else on WhatsAppNo login needed. A real person replies.

Or leave your number, we’ll message you:

GharKundli’s full report on Yashwin SukhNiwas

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the December 2024 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100025982
Status
Completed
Builder
GROWISA ADVISORS
Location
Hinjawadi, Pune · 411057
Project type
Residential / Group Housing
Registered on
7 Aug 2020
Completion date at registration
December 2024
Latest completion date
December 2024
Towers
4
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of Yashwin SukhNiwas, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Building A - upto 13 floors sanctioned100%100%100%100%
Building B - upto 13 floors sanctioned100%100%100%100%
Building C - upto 13 floors sanctioned, 14th floor proposed100%100%100%95%
Building D - upto 13th floors sanctioned, 14th floor propose100%100%100%95%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Yashwin SukhNiwas every 1–2 months.

Yashwin SukhNiwas: buildings, flats and land, as filed on MahaRERA

  • Buildings: Building A - upto 13 floors sanctioned (14 floors) · Building B - upto 13 floors sanctioned (14 floors) · Building C - upto 13 floors sanctioned, 14th floor proposed (15 floors) · Building D - upto 13th floors sanctioned, 14th floor propose (15 floors)
  • Land: 7,264 sq m (about 1.8 acres) · sanctioned built-up 13,003 sq m · recreational space 840 sq m
  • Land, as filed: S.no. 42/1 Part , 43/8/B Part
  • Map: Get directions

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Yashwin SukhNiwas →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Yashwin SukhNiwas: buyers & owners

Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.

Common questions about Yashwin SukhNiwas

What is the possession date of Yashwin SukhNiwas?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Yashwin SukhNiwas in Hinjawadi, Pune is 30 December 2024.

Is the builder's possession date different from the MahaRERA date for Yashwin SukhNiwas?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Yashwin SukhNiwas's builder has filed on MahaRERA, the official one, is 30 December 2024, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Yashwin SukhNiwas?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Yashwin SukhNiwas in Hinjawadi, Pune is P52100025982.

Is Yashwin SukhNiwas registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Yashwin SukhNiwas is registered as P52100025982 and its status is "Completed".

What is the current construction status of Yashwin SukhNiwas? How much work is done?

According to GharKundli's check of MahaRERA records (updated November 2026), Yashwin SukhNiwas's status on MahaRERA is "Completed". As filed by the builder, slab work is 100% done across 4 towers. GharKundli's full report compares construction progress with the deadline.

Does Yashwin SukhNiwas have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Yashwin SukhNiwas safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Yashwin SukhNiwas is registered on MahaRERA as P52100025982, its MahaRERA status is "Completed", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How much GST is payable on a flat in Yashwin SukhNiwas?

According to GharKundli's check of MahaRERA records (updated November 2026), Yashwin SukhNiwas is marked completed on MahaRERA. A flat bought after the occupancy certificate (OC) is issued has no GST, only stamp duty and registration. Ask the builder for the OC date: if your sale is agreed before the OC, GST applies.

What is the stamp duty and registration cost for a flat in Yashwin SukhNiwas?

In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Yashwin SukhNiwas: gharkundli.com/tools/property-cost-calculator

Has Yashwin SukhNiwas received its OC? Is it ready to move in?

According to GharKundli's check of MahaRERA records (updated November 2026), Yashwin SukhNiwas is marked completed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued: ask the builder for a copy and check it covers your building and floor before you pay. What an OC is and why it matters: gharkundli.com/help/occupancy-certificate-oc-maharashtra

When was Yashwin SukhNiwas completed?

According to GharKundli's check of MahaRERA records (updated November 2026), Yashwin SukhNiwas is marked completed on MahaRERA, and the completion date filed there is 30 December 2024. MahaRERA doesn't record the year the building was built: for that, ask for the occupancy certificate (OC) and its date.

Has Yashwin SukhNiwas uploaded its title report on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), no title report for Yashwin SukhNiwas was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.

No title report is on MahaRERA for this project. See which documents are missing →

How can I get updates if Yashwin SukhNiwas's possession date changes?

The latest dates are on Yashwin SukhNiwas's MahaRERA page (P52100025982). GharKundli's Kundli Watch sends a free WhatsApp update on Yashwin SukhNiwas every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Yashwin SukhNiwas have?

According to GharKundli's check of MahaRERA records (updated November 2026), Yashwin SukhNiwas has 4 buildings filed: Building A - upto 13 floors sanctioned with 14 floors; Building B - upto 13 floors sanctioned with 14 floors; Building C - upto 13 floors sanctioned, 14th floor proposed with 15 floors; Building D - upto 13th floors sanctioned, 14th floor propose with 15 floors.

How big is the land of Yashwin SukhNiwas?

According to GharKundli's check of MahaRERA records (updated November 2026), Yashwin SukhNiwas stands on 7,264 sq m of land (about 1.8 acres), with 13,003 sq m of sanctioned built-up area and 840 sq m of recreational open space.

What are the reviews of Yashwin SukhNiwas?

Google Maps has reviews of Yashwin SukhNiwas written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

What is the address and pincode of Yashwin SukhNiwas?

Yashwin SukhNiwas by GROWISA ADVISORS is in Hinjawadi, Pune, pincode 411057, Maharashtra, and is registered on MahaRERA as P52100025982, per GharKundli's check of MahaRERA records. Its land is filed as S.no. 42/1 Part , 43/8/B Part. GharKundli lists all 644 MahaRERA projects in Wakad (411057).

When was Yashwin SukhNiwas registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Yashwin SukhNiwas was registered on MahaRERA on 7 August 2020. GharKundli did not find a title report on the land on file there.

Does Yashwin SukhNiwas have any legal issues or court cases?

No court cases are listed for Yashwin SukhNiwas on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder / developer of Yashwin SukhNiwas?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is GROWISA ADVISORS.

Other projects in Wakad (411057)

All 644 projects in Wakad (411057) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.