by Sumit Chetna Ventures · Malad East, MumbaiAlso near Kurar Village, Dindoshi, Goregaon East

Possession: Sharda Sahaniwas is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800002134. Status: Completed. 1 complaint is listed against it on MahaRERA.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Sharda Sahaniwas?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Sharda Sahaniwas has moved

  1. 31 March 2018

    Completion date given when the project was registered

  2. 30 September 2018

    Extended at the builder's request (MahaRERA application EXT51800000197)

    Reason the builder gave MahaRERA: “Building is duly completed in all senses, as per compliances determined by MHADA and MCGM .And we are awaiting Final MHADA NOC, upon receiving which, we will apply for Occupation Certificate”

Source: Sharda Sahaniwas’s extension records on MahaRERA (P51800002134), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Sharda Sahaniwas

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 1 complaint, and how it ended
  • Construction pace against the September 2018 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800002134
Status
Completed
Builder
Sumit Chetna Ventures
Location
Malad East, Mumbai · 400097
Project type
Residential / Group Housing
Registered on
31 Jul 2017
Completion date at registration
March 2018
Latest completion date
September 2018
Delay so far
6 months
Homes
53
Towers
1
Complaints on MahaRERA
1
Court cases listed
0
Title report on file
Not found

Construction progress of Sharda Sahaniwas, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Sharda Sahaniwas B Wing100%100%100%90%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Sharda Sahaniwas every month.

Sharda Sahaniwas: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Sumit Garden Grove Construction (a group of 5 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 4 finished, 1 within the promised date and 3 needed more time (typically 5 months); 1 still being built, 1 past the promised date (typically 46 months late). 1 complaint on MahaRERA across 1 project.

Read Google reviews of Sharda Sahaniwas →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Sharda Sahaniwas: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Sharda Sahaniwas

What is the possession date of Sharda Sahaniwas?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Sharda Sahaniwas in Malad East, Mumbai is 30 September 2018 — 6 months later than 31 March 2018, the date given at registration.

Is the builder's possession date different from the MahaRERA date for Sharda Sahaniwas?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Sharda Sahaniwas's builder has filed on MahaRERA, the official one, is 30 September 2018, already 6 months later than the 31 March 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Sharda Sahaniwas extended?

According to GharKundli's check of MahaRERA records (updated November 2026), Sharda Sahaniwas's builder applied to MahaRERA to extend the completion date once: to 30 September 2018, giving the reason "Building is duly completed in all senses, as per compliances determined by MHADA and MCGM .And we are awaiting Final MHADA NOC, upon receiving which, we will apply for Occupation Certificate".

What is the RERA number of Sharda Sahaniwas?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Sharda Sahaniwas in Malad East, Mumbai is P51800002134.

Is Sharda Sahaniwas registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sharda Sahaniwas is registered as P51800002134 and its status is "Completed".

What is the construction status of Sharda Sahaniwas?

According to GharKundli's check of MahaRERA records (updated November 2026), Sharda Sahaniwas's status on MahaRERA is "Completed". As filed by the builder, slab work on Sharda Sahaniwas B Wing is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does Sharda Sahaniwas have complaints on MahaRERA?

1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.

Is Sharda Sahaniwas safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Sharda Sahaniwas is registered on MahaRERA as P51800002134, its MahaRERA status is "Completed", its completion date has moved 6 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Sharda Sahaniwas's possession date changes?

The latest dates are on Sharda Sahaniwas's MahaRERA page (P51800002134). GharKundli's Kundli Watch sends a free WhatsApp update on Sharda Sahaniwas every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Sharda Sahaniwas have?

According to GharKundli's check of MahaRERA records (updated November 2026), Sharda Sahaniwas has one building filed: Sharda Sahaniwas B Wing with 20 floors.

How big is the land of Sharda Sahaniwas?

According to GharKundli's check of MahaRERA records (updated November 2026), Sharda Sahaniwas stands on 1,396 sq m of land (about 0.3 acres), with 5,654 sq m of sanctioned built-up area.

What is the track record of Sharda Sahaniwas's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Sumit Garden Grove Construction (a group of 5 linked companies) has 5 projects on MahaRERA since 2017, this one included. Of the 5 GharKundli has checked: 4 finished, 1 within the promised date and 3 needed more time (typically 5 months); 1 still being built, 1 past the promised date (typically 46 months late). 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Sharda Sahaniwas?

Google Maps has reviews of Sharda Sahaniwas written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Sharda Sahaniwas?

Sharda Sahaniwas by Sumit Chetna Ventures is in Malad East, Mumbai (pincode 400097), near Kurar Village, Dindoshi, Goregaon East, Maharashtra, and is registered on MahaRERA as P51800002134, per GharKundli's check of MahaRERA records.

How many homes are in Sharda Sahaniwas?

According to GharKundli's check of MahaRERA records (updated November 2026), Sharda Sahaniwas has 53 homes in 1 tower registered on MahaRERA.

When was Sharda Sahaniwas registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Sharda Sahaniwas was registered on MahaRERA on 31 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Sharda Sahaniwas?

No court cases are listed for Sharda Sahaniwas on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Sharda Sahaniwas?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Sumit Chetna Ventures.