BLUE BELLS PHASE 1

by CHHAYA ROHIDAS WALHEKAR · Infotech Park (Hinjawadi), Pune

Possession: BLUE BELLS PHASE 1 is marked completed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100029834. Status: Completed.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about BLUE BELLS PHASE 1?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of BLUE BELLS PHASE 1 has moved

  1. 1 March 2022

    Completion date given when the project was registered

  2. 20 September 2022

    Extended at the builder's request (MahaRERA application EXT52100011540)

    Reason the builder gave MahaRERA:
    “Due to second wave of Covid 19 pandemic which started in April 2021, the construction work came to stand still due to non availability of labours and construction on movement of building material etc and this wave especially was more predom…” Read the full reason“Due to second wave of Covid 19 pandemic which started in April 2021, the construction work came to stand still due to non availability of labours and construction on movement of building material etc and this wave especially was more predominant in Maharashtra”
  3. 20 March 2023

    Extended at the builder's request (MahaRERA application EXT52100012566)

    Reason the builder gave MahaRERA:
    “Project work was delayed due to unforeseen reasons, hence we could not complete the project within stipulated time. We intend to complete the project within 20.03.2023 but we do not wish to take any form of risk. Therefore, we are asking fo…” Read the full reason“Project work was delayed due to unforeseen reasons, hence we could not complete the project within stipulated time. We intend to complete the project within 20.03.2023 but we do not wish to take any form of risk. Therefore, we are asking for extension of expiry date for the project from the Authority.”

Source: BLUE BELLS PHASE 1’s extension records on MahaRERA (P52100029834), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on BLUE BELLS PHASE 1

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the March 2023 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100029834
Status
Completed
Builder
CHHAYA ROHIDAS WALHEKAR
Location
Infotech Park (Hinjawadi), Pune · 411057
Project type
Residential / Group Housing
Registered on
8 Jul 2021
Completion date at registration
March 2022
Latest completion date
March 2023
Delay so far
12 months
Homes
9
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of BLUE BELLS PHASE 1, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BLUE BELLS PHASE 1100%100%100%100%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on BLUE BELLS PHASE 1 every month.

BLUE BELLS PHASE 1: buildings, flats and land, as filed on MahaRERA

  • Buildings: BLUE BELLS PHASE 1 (4 floors)
  • Land: 397 sq m (about 0.1 acres) · sanctioned built-up 397 sq m · recreational space 3 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of BLUE BELLS PHASE 1 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

BLUE BELLS PHASE 1: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about BLUE BELLS PHASE 1

What is the possession date of BLUE BELLS PHASE 1?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for BLUE BELLS PHASE 1 in Infotech Park (Hinjawadi), Pune is 20 March 2023 — 12 months later than 1 March 2022, the date given at registration.

Is the builder's possession date different from the MahaRERA date for BLUE BELLS PHASE 1?

Builders and listing sites often quote an earlier "target" date for handover. The completion date BLUE BELLS PHASE 1's builder has filed on MahaRERA, the official one, is 20 March 2023, already 12 months later than the 1 March 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of BLUE BELLS PHASE 1 extended?

According to GharKundli's check of MahaRERA records (updated November 2026), BLUE BELLS PHASE 1's builder applied to MahaRERA to extend the completion date 2 times: to 20 September 2022, giving the reason "Due to second wave of Covid 19 pandemic which started in April 2021, the construction work came to stand still due to non availability of labours and construction on movement of building material etc and this wave especially was more predominant in Maharashtra"; to 20 March 2023, giving the reason "Project work was delayed due to unforeseen reasons, hence we could not complete the project within stipulated time. We intend to complete the project within 20.03.2023 but we do not wish to take any form of risk. Therefore, we are asking for extension of expiry date for the project from the Authority.".

What is the RERA number of BLUE BELLS PHASE 1?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of BLUE BELLS PHASE 1 in Infotech Park (Hinjawadi), Pune is P52100029834.

Is BLUE BELLS PHASE 1 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), BLUE BELLS PHASE 1 is registered as P52100029834 and its status is "Completed".

What is the construction status of BLUE BELLS PHASE 1?

According to GharKundli's check of MahaRERA records (updated November 2026), BLUE BELLS PHASE 1's status on MahaRERA is "Completed". As filed by the builder, slab work on BLUE BELLS PHASE 1 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does BLUE BELLS PHASE 1 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is BLUE BELLS PHASE 1 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), BLUE BELLS PHASE 1 is registered on MahaRERA as P52100029834, its MahaRERA status is "Completed", its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if BLUE BELLS PHASE 1's possession date changes?

The latest dates are on BLUE BELLS PHASE 1's MahaRERA page (P52100029834). GharKundli's Kundli Watch sends a free WhatsApp update on BLUE BELLS PHASE 1 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does BLUE BELLS PHASE 1 have?

According to GharKundli's check of MahaRERA records (updated November 2026), BLUE BELLS PHASE 1 has one building filed: BLUE BELLS PHASE 1 with 4 floors.

How big is the land of BLUE BELLS PHASE 1?

According to GharKundli's check of MahaRERA records (updated November 2026), BLUE BELLS PHASE 1 stands on 397 sq m of land (about 0.1 acres), with 397 sq m of sanctioned built-up area and 3 sq m of recreational open space.

Where can I read reviews of BLUE BELLS PHASE 1?

Google Maps has reviews of BLUE BELLS PHASE 1 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is BLUE BELLS PHASE 1?

BLUE BELLS PHASE 1 by CHHAYA ROHIDAS WALHEKAR is in Infotech Park (Hinjawadi), Pune (pincode 411057), Maharashtra, and is registered on MahaRERA as P52100029834, per GharKundli's check of MahaRERA records.

How many homes are in BLUE BELLS PHASE 1?

According to GharKundli's check of MahaRERA records (updated November 2026), BLUE BELLS PHASE 1 has 9 homes in 1 tower registered on MahaRERA.

When was BLUE BELLS PHASE 1 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), BLUE BELLS PHASE 1 was registered on MahaRERA on 8 July 2021. GharKundli did not find a title report on the land on file there.

Are there court cases on BLUE BELLS PHASE 1?

No court cases are listed for BLUE BELLS PHASE 1 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of BLUE BELLS PHASE 1?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is CHHAYA ROHIDAS WALHEKAR.