19 GRAND WEST - C WING and D WING
by Shivam Development Ventures LLP · Thergaon, Pune 411033Also near Chinchwadgaon
What’s in the report? →Possession date of 19 GRAND WEST - C WING and D WING (MahaRERA P52100031024): 31 December 2024, and it has already passed. It has 205 homes. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100031024. Status: Lapsed (registration period ended).
Source: MahaRERA website — records for P52100031024, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
The latest completion date on MahaRERA (December 2024) has passed.
What do you want to know about 19 GRAND WEST - C WING and D WING?
Completion date nikal chuki hai. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
GharKundli’s full report on 19 GRAND WEST - C WING and D WING
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100031024
- Status
- Lapsed (registration period ended)
- Builder
- Shivam Development Ventures LLP
- Location
- Thergaon, Pune · 411033
- Project type
- Residential / Group Housing
- Registered on
- 1 Oct 2021
- Completion date at registration
- December 2024
- Homes
- 205
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 2
Construction progress of 19 GRAND WEST - C WING and D WING, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| 19 Grand West - C Wing | 100% | 100% | 100% | 100% |
| 19 Grand West - D Wing | 100% | 100% | 100% | 100% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on 19 GRAND WEST - C WING and D WING every 1–2 months.
19 GRAND WEST - C WING and D WING: buildings, flats and land, as filed on MahaRERA
- Buildings: 19 Grand West - C Wing (21 floors) · 19 Grand West - D Wing (20 floors)
- Land: 5,037 sq m (about 1.2 acres) · sanctioned built-up 14,972 sq m · recreational space 505 sq m
- Boundaries filed include: CHINCHWAD ROAD
- Land, as filed: 23/2/1/3 P and 23/2/1/4 P
- Map: Get directions
The builder’s record and reviews
Shivam Developers (a group of 2 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 17 months); 2 still being built, none past the promised date yet; 2 lapsed. No complaints on MahaRERA.
Read Google reviews of 19 GRAND WEST - C WING and D WING →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
19 GRAND WEST - C WING and D WING: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about 19 GRAND WEST - C WING and D WING
What is the possession date of 19 GRAND WEST - C WING and D WING?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for 19 GRAND WEST - C WING and D WING in Thergaon, Pune is 31 December 2024. That date has already passed.
Is the builder's possession date different from the MahaRERA date for 19 GRAND WEST - C WING and D WING?
Builders and listing sites often quote an earlier "target" date for handover. The completion date 19 GRAND WEST - C WING and D WING's builder has filed on MahaRERA, the official one, is 31 December 2024, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of 19 GRAND WEST - C WING and D WING?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of 19 GRAND WEST - C WING and D WING in Thergaon, Pune is P52100031024.
Is 19 GRAND WEST - C WING and D WING registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), 19 GRAND WEST - C WING and D WING is registered as P52100031024 and its status is "Lapsed (registration period ended)".
What is the current construction status of 19 GRAND WEST - C WING and D WING? How much work is done?
According to GharKundli's check of MahaRERA records (updated November 2026), 19 GRAND WEST - C WING and D WING's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work is 100% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does 19 GRAND WEST - C WING and D WING have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is 19 GRAND WEST - C WING and D WING safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), 19 GRAND WEST - C WING and D WING is registered on MahaRERA as P52100031024, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in 19 GRAND WEST - C WING and D WING?
19 GRAND WEST - C WING and D WING isn't marked completed on MahaRERA, so until the occupancy certificate is issued GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in 19 GRAND WEST - C WING and D WING?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in 19 GRAND WEST - C WING and D WING: gharkundli.com/tools/property-cost-calculator
Has 19 GRAND WEST - C WING and D WING received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated November 2026), 19 GRAND WEST - C WING and D WING isn't completed: its MahaRERA status is "Lapsed (registration period ended)", with 31 December 2024 as the latest completion date filed on MahaRERA, and that date has passed. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
What does "lapsed" mean for 19 GRAND WEST - C WING and D WING?
According to GharKundli's check of MahaRERA records (updated November 2026), 19 GRAND WEST - C WING and D WING's registration shows as lapsed on MahaRERA. Lapsed means the completion date on MahaRERA (31 December 2024) passed without the project being marked complete or the registration being extended. Before paying anything, ask the builder in writing whether an extension has been applied for.
Has 19 GRAND WEST - C WING and D WING uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), no title report for 19 GRAND WEST - C WING and D WING was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if 19 GRAND WEST - C WING and D WING's possession date changes?
The latest dates are on 19 GRAND WEST - C WING and D WING's MahaRERA page (P52100031024). GharKundli's Kundli Watch sends a free WhatsApp update on 19 GRAND WEST - C WING and D WING every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does 19 GRAND WEST - C WING and D WING have?
According to GharKundli's check of MahaRERA records (updated November 2026), 19 GRAND WEST - C WING and D WING has 2 buildings filed: 19 Grand West - C Wing with 21 floors; 19 Grand West - D Wing with 20 floors.
How big is the land of 19 GRAND WEST - C WING and D WING?
According to GharKundli's check of MahaRERA records (updated November 2026), 19 GRAND WEST - C WING and D WING stands on 5,037 sq m of land (about 1.2 acres), with 14,972 sq m of sanctioned built-up area and 505 sq m of recreational open space.
What is the track record of 19 GRAND WEST - C WING and D WING's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Shivam Developers (a group of 2 linked companies) has 7 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 3 finished, 1 within the promised date and 2 needed more time (typically 17 months); 2 still being built, none past the promised date yet; 2 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.
What are the reviews of 19 GRAND WEST - C WING and D WING?
Google Maps has reviews of 19 GRAND WEST - C WING and D WING written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of 19 GRAND WEST - C WING and D WING?
19 GRAND WEST - C WING and D WING by Shivam Development Ventures LLP is in Thergaon, Pune, pincode 411033 (near Chinchwadgaon), Maharashtra, and is registered on MahaRERA as P52100031024, per GharKundli's check of MahaRERA records. Its boundaries filed there include CHINCHWAD ROAD. Its land is filed as 23/2/1/3 P and 23/2/1/4 P. GharKundli lists all 613 MahaRERA projects in Chinchwadgaon (411033).
How many flats are in 19 GRAND WEST - C WING and D WING?
According to GharKundli's check of MahaRERA records (updated November 2026), 19 GRAND WEST - C WING and D WING has 205 homes in 2 towers registered on MahaRERA.
When was 19 GRAND WEST - C WING and D WING registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), 19 GRAND WEST - C WING and D WING was registered on MahaRERA on 1 October 2021. GharKundli did not find a title report on the land on file there.
Does 19 GRAND WEST - C WING and D WING have any legal issues or court cases?
No court cases are listed for 19 GRAND WEST - C WING and D WING on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder / developer of 19 GRAND WEST - C WING and D WING?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Shivam Development Ventures LLP, which has 2 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of 19 GRAND WEST - C WING and D WING
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Chinchwadgaon (411033)
- Nirman Serenopolis
- Millennium Samriddhi
- Rohan Harita Phase 4
- West World
- Raman Stellar
- Ganga Amber PH II
- Kohinoor Uptown Avenue
- Aishwaryam Insignia
Other projects by Shivam Development Ventures LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.