Possession date of LOBPSONS AND TANIA INDUSTRIES: 26 June 2025, moved from 1 May 2018 (85 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P99000008005. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (June 2025) has passed.

What do you want to know about LOBPSONS AND TANIA INDUSTRIES?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of LOBPSONS AND TANIA INDUSTRIES has moved

  1. 1 May 2018

    Completion date given when the project was registered

  2. 7 December 2021

    Extended at the builder's request (MahaRERA application EXT99000002440)

    Reason the builder gave MahaRERA:
    “Due to unstable market conditions there was a very poor reeponse from the buyers. Apparently there were no bookings leading to insuflicient funds to carry out constluction activities. Hence we were unable to complete the project as on that…” Read the full reason“Due to unstable market conditions there was a very poor reeponse from the buyers. Apparently there were no bookings leading to insuflicient funds to carry out constluction activities. Hence we were unable to complete the project as on that date.”
  3. 26 June 2025

    Extended at the builder's request (MahaRERA application EXT99000016940)

    Reason the builder gave MahaRERA: “The project is delayed to the various reason covid 19, lack of finance , delay in material. Hence we request you to grant extension till 26th June 2025”

Source: LOBPSONS AND TANIA INDUSTRIES’s extension records on MahaRERA (P99000008005), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on LOBPSONS AND TANIA INDUSTRIES

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the June 2025 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000008005
Status
Lapsed (registration period ended)
Builder
LOBPSONS & TANIA BUILDERS
Location
Pelhar, Palghar · 401202
Project type
Mixed
Registered on
18 Aug 2017
Completion date at registration
May 2018
Latest completion date
June 2025
Delay so far
85 months
Homes
0
Sold or booked
57%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of LOBPSONS AND TANIA INDUSTRIES, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
LOBPSONS AND TANIA INDUSTRIES100%40%10%0%

Commencement certificate (CC), as filed on MahaRERA

  • LOBPSONS AND TANIA INDUSTRIES: covers 2 (G+1)

Want to know when this changes? Kundli Watch sends a free WhatsApp update on LOBPSONS AND TANIA INDUSTRIES every month.

LOBPSONS AND TANIA INDUSTRIES: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of LOBPSONS AND TANIA INDUSTRIES →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

LOBPSONS AND TANIA INDUSTRIES: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about LOBPSONS AND TANIA INDUSTRIES

What is the possession date of LOBPSONS AND TANIA INDUSTRIES?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for LOBPSONS AND TANIA INDUSTRIES in Pelhar, Palghar is 26 June 2025 — 85 months later than 1 May 2018, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for LOBPSONS AND TANIA INDUSTRIES?

Builders and listing sites often quote an earlier "target" date for handover. The completion date LOBPSONS AND TANIA INDUSTRIES's builder has filed on MahaRERA, the official one, is 26 June 2025, already 85 months later than the 1 May 2018 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of LOBPSONS AND TANIA INDUSTRIES extended?

According to GharKundli's check of MahaRERA records (updated November 2026), LOBPSONS AND TANIA INDUSTRIES's builder applied to MahaRERA to extend the completion date 2 times: to 7 December 2021, giving the reason "Due to unstable market conditions there was a very poor reeponse from the buyers. Apparently there were no bookings leading to insuflicient funds to carry out constluction activities. Hence we were unable to complete the project as on that date."; to 26 June 2025, giving the reason "The project is delayed to the various reason covid 19, lack of finance , delay in material. Hence we request you to grant extension till 26th June 2025".

What is the RERA number of LOBPSONS AND TANIA INDUSTRIES?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of LOBPSONS AND TANIA INDUSTRIES in Pelhar, Palghar is P99000008005.

Is LOBPSONS AND TANIA INDUSTRIES registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), LOBPSONS AND TANIA INDUSTRIES is registered as P99000008005 and its status is "Lapsed (registration period ended)".

What is the construction status of LOBPSONS AND TANIA INDUSTRIES?

According to GharKundli's check of MahaRERA records (updated November 2026), LOBPSONS AND TANIA INDUSTRIES's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on LOBPSONS AND TANIA INDUSTRIES is 40% done and internal work 10%. GharKundli's full report compares construction progress with the deadline.

Does LOBPSONS AND TANIA INDUSTRIES have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is LOBPSONS AND TANIA INDUSTRIES safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), LOBPSONS AND TANIA INDUSTRIES is registered on MahaRERA as P99000008005, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 85 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if LOBPSONS AND TANIA INDUSTRIES's possession date changes?

The latest dates are on LOBPSONS AND TANIA INDUSTRIES's MahaRERA page (P99000008005). GharKundli's Kundli Watch sends a free WhatsApp update on LOBPSONS AND TANIA INDUSTRIES every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does LOBPSONS AND TANIA INDUSTRIES have?

According to GharKundli's check of MahaRERA records (updated November 2026), LOBPSONS AND TANIA INDUSTRIES has one building filed: LOBPSONS AND TANIA INDUSTRIES with 3 floors and 42 units.

How big is the land of LOBPSONS AND TANIA INDUSTRIES?

According to GharKundli's check of MahaRERA records (updated November 2026), LOBPSONS AND TANIA INDUSTRIES stands on 8,040 sq m of land (about 2.0 acres), with 5,398 sq m of sanctioned built-up area and 2,500 sq m of recreational open space.

Where can I read reviews of LOBPSONS AND TANIA INDUSTRIES?

Google Maps has reviews of LOBPSONS AND TANIA INDUSTRIES written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is LOBPSONS AND TANIA INDUSTRIES?

LOBPSONS AND TANIA INDUSTRIES by LOBPSONS & TANIA BUILDERS is in Pelhar, Palghar (pincode 401202), near Vasai West, Diwanman, Chulne, Maharashtra, and is registered on MahaRERA as P99000008005, per GharKundli's check of MahaRERA records.

How many homes are in LOBPSONS AND TANIA INDUSTRIES?

According to GharKundli's check of MahaRERA records (updated November 2026), LOBPSONS AND TANIA INDUSTRIES has 0 homes in 1 tower registered on MahaRERA, and 57% of them are sold or booked.

When was LOBPSONS AND TANIA INDUSTRIES registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), LOBPSONS AND TANIA INDUSTRIES was registered on MahaRERA on 18 August 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on LOBPSONS AND TANIA INDUSTRIES?

No court cases are listed for LOBPSONS AND TANIA INDUSTRIES on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of LOBPSONS AND TANIA INDUSTRIES?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is LOBPSONS & TANIA BUILDERS.

Other projects in Pelhar

All 107 projects in Bassein Road (401202) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.