HONEST HEIGHTS

by METRO DEVELOPERS · Pelhar, PalgharAlso near Vasai East IE

Possession date of HONEST HEIGHTS: 30 April 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P99000053639, and currently active. Its completion date is now April 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about HONEST HEIGHTS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of HONEST HEIGHTS has moved

  1. 31 December 2027

    Completion date given when the project was registered

  2. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: HONEST HEIGHTS’s extension records on MahaRERA (P99000053639), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on HONEST HEIGHTS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P99000053639
Status
Registered and active
Builder
METRO DEVELOPERS
Location
Pelhar, Palghar · 401208
Project type
Others
Registered on
21 Nov 2023
Completion date at registration
December 2027
Latest completion date
April 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
28
Sold or booked
72%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of HONEST HEIGHTS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BUILDING NO 7100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • BUILDING NO 7: covers 7 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on HONEST HEIGHTS every month.

HONEST HEIGHTS: buildings, flats and land, as filed on MahaRERA

  • Buildings: BUILDING NO 7 (7 floors, 32 units)
  • Land: 163 sq m (about 0.0 acres) · sanctioned built-up 1,199 sq m · recreational space 16 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of HONEST HEIGHTS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

HONEST HEIGHTS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about HONEST HEIGHTS

What is the possession date of HONEST HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for HONEST HEIGHTS in Pelhar, Palghar is 30 April 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for HONEST HEIGHTS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date HONEST HEIGHTS's builder has filed on MahaRERA, the official one, is 30 April 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of HONEST HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of HONEST HEIGHTS in Pelhar, Palghar is P99000053639.

Is HONEST HEIGHTS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), HONEST HEIGHTS is registered as P99000053639 and its status is "Registered and active".

What is the construction status of HONEST HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), HONEST HEIGHTS's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BUILDING NO 7 is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does HONEST HEIGHTS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is HONEST HEIGHTS safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), HONEST HEIGHTS is registered on MahaRERA as P99000053639, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if HONEST HEIGHTS's possession date changes?

The latest dates are on HONEST HEIGHTS's MahaRERA page (P99000053639). GharKundli's Kundli Watch sends a free WhatsApp update on HONEST HEIGHTS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does HONEST HEIGHTS have?

According to GharKundli's check of MahaRERA records (updated November 2026), HONEST HEIGHTS has one building filed: BUILDING NO 7 with 7 floors and 32 units.

How big is the land of HONEST HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), HONEST HEIGHTS stands on 163 sq m of land (about 0.0 acres), with 1,199 sq m of sanctioned built-up area and 16 sq m of recreational open space.

Where can I read reviews of HONEST HEIGHTS?

Google Maps has reviews of HONEST HEIGHTS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is HONEST HEIGHTS?

HONEST HEIGHTS by METRO DEVELOPERS is in Pelhar, Palghar (pincode 401208), near Vasai East IE, Maharashtra, and is registered on MahaRERA as P99000053639, per GharKundli's check of MahaRERA records.

How many homes are in HONEST HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), HONEST HEIGHTS has 28 homes in 1 tower registered on MahaRERA, and 72% of them are sold or booked.

When was HONEST HEIGHTS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), HONEST HEIGHTS was registered on MahaRERA on 21 November 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on HONEST HEIGHTS?

No court cases are listed for HONEST HEIGHTS on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of HONEST HEIGHTS?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is METRO DEVELOPERS, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2028 in Palghar →

Other projects in pincode 401208

All 245 projects in Vasai East IE (401208) →

Other projects by METRO DEVELOPERS

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.