MERLIN ELEMENTA 2.0
by MERLIN BHINGARWALA DEVELOPERS LLP · Tathawade, PuneAlso near Wakad
Possession date of MERLIN ELEMENTA 2.0: 30 April 2028, moved from 31 December 2026 (12 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100050199, and currently active. Its completion date has moved from December 2026 to April 2028: 12 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about MERLIN ELEMENTA 2.0?
How the possession date of MERLIN ELEMENTA 2.0 has moved
31 December 2026
Completion date given when the project was registered
31 December 2027
Extended at the builder's request (MahaRERA application EXT52100017630)
Reason the builder gave MahaRERA: “Due to some internal reasons, construction start date and Launch date of the said project has postponed. Hence we have to extend our Completion date of the said Project”
30 April 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: MERLIN ELEMENTA 2.0’s extension records on MahaRERA (P52100050199), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on MERLIN ELEMENTA 2.0
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 5 court cases, and how it ended
- Construction pace against the April 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100050199
- Status
- Registered and active
- Builder
- MERLIN BHINGARWALA DEVELOPERS LLP
- Location
- Tathawade, Pune · 411033
- Project type
- Residential / Group Housing
- Registered on
- 21 Mar 2023
- Completion date at registration
- December 2026
- Latest completion date
- April 2028
- Delay so far
- 12 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 339
- Sold or booked
- 63%
- Towers
- 4
- Complaints on MahaRERA
- 0
- Court cases listed
- 5
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 1
Construction progress of MERLIN ELEMENTA 2.0, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| A Building | 100% | 93.75% | 47.69% | 30% |
| B Building | 100% | 100% | 77.18% | 40% |
| C Building | 100% | 100% | 76.41% | 40% |
| Commercial Building | 100% | 100% | 100% | 90% |
Commencement certificate (CC), as filed on MahaRERA
- A Building: covers 0 floors
- B Building: covers 0 floors
- C Building: covers 0 floors
- Commercial Building: covers 0 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on MERLIN ELEMENTA 2.0 every month.
MERLIN ELEMENTA 2.0: buildings, flats and land, as filed on MahaRERA
- Buildings: A Building (16 floors, 107 units) · B Building (16 floors, 145 units) · C Building (16 floors, 125 units) · Commercial Building (4 floors, 29 units)
- Car parking: 406 covered, 426 open
- Land: 11,090 sq m (about 2.7 acres) · sanctioned built-up 38,940 sq m
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of MERLIN ELEMENTA 2.0 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
MERLIN ELEMENTA 2.0: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about MERLIN ELEMENTA 2.0
What is the possession date of MERLIN ELEMENTA 2.0?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for MERLIN ELEMENTA 2.0 in Tathawade, Pune is 30 April 2028 — 12 months later than 31 December 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for MERLIN ELEMENTA 2.0?
Builders and listing sites often quote an earlier "target" date for handover. The completion date MERLIN ELEMENTA 2.0's builder has filed on MahaRERA, the official one, is 30 April 2028, already 12 months later than the 31 December 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of MERLIN ELEMENTA 2.0 extended?
According to GharKundli's check of MahaRERA records (updated November 2026), MERLIN ELEMENTA 2.0's builder applied to MahaRERA to extend the completion date once: to 31 December 2027, giving the reason "Due to some internal reasons, construction start date and Launch date of the said project has postponed. Hence we have to extend our Completion date of the said Project". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of MERLIN ELEMENTA 2.0?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of MERLIN ELEMENTA 2.0 in Tathawade, Pune is P52100050199.
Is MERLIN ELEMENTA 2.0 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), MERLIN ELEMENTA 2.0 is registered as P52100050199 and its status is "Registered and active".
What is the construction status of MERLIN ELEMENTA 2.0?
According to GharKundli's check of MahaRERA records (updated November 2026), MERLIN ELEMENTA 2.0's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 93.75% to 100% across 4 towers. GharKundli's full report compares construction progress with the deadline.
Does MERLIN ELEMENTA 2.0 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is MERLIN ELEMENTA 2.0 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), MERLIN ELEMENTA 2.0 is registered on MahaRERA as P52100050199, its completion date has moved 12 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if MERLIN ELEMENTA 2.0's possession date changes?
The latest dates are on MERLIN ELEMENTA 2.0's MahaRERA page (P52100050199). GharKundli's Kundli Watch sends a free WhatsApp update on MERLIN ELEMENTA 2.0 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does MERLIN ELEMENTA 2.0 have?
According to GharKundli's check of MahaRERA records (updated November 2026), MERLIN ELEMENTA 2.0 has 4 buildings filed: A Building with 16 floors and 107 units; B Building with 16 floors and 145 units; C Building with 16 floors and 125 units; Commercial Building with 4 floors and 29 units.
How much parking does MERLIN ELEMENTA 2.0 have?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder has filed 406 covered and 426 open car parking spaces for MERLIN ELEMENTA 2.0.
How big is the land of MERLIN ELEMENTA 2.0?
According to GharKundli's check of MahaRERA records (updated November 2026), MERLIN ELEMENTA 2.0 stands on 11,090 sq m of land (about 2.7 acres), with 38,940 sq m of sanctioned built-up area.
Where can I read reviews of MERLIN ELEMENTA 2.0?
Google Maps has reviews of MERLIN ELEMENTA 2.0 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is MERLIN ELEMENTA 2.0?
MERLIN ELEMENTA 2.0 by MERLIN BHINGARWALA DEVELOPERS LLP is in Tathawade, Pune (pincode 411033), near Wakad, Maharashtra, and is registered on MahaRERA as P52100050199, per GharKundli's check of MahaRERA records.
How many homes are in MERLIN ELEMENTA 2.0?
According to GharKundli's check of MahaRERA records (updated November 2026), MERLIN ELEMENTA 2.0 has 339 homes in 4 towers registered on MahaRERA, and 63% of them are sold or booked.
When was MERLIN ELEMENTA 2.0 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), MERLIN ELEMENTA 2.0 was registered on MahaRERA on 21 March 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on MERLIN ELEMENTA 2.0?
5 court cases are listed for MERLIN ELEMENTA 2.0 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.
Who is the builder of MERLIN ELEMENTA 2.0?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is MERLIN BHINGARWALA DEVELOPERS LLP, which has 1 other project registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of MERLIN ELEMENTA 2.0
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Pune →
Other projects in pincode 411033
- GANGA AMBER PH II
- AISHWARYAM INSIGNIA
- RAMAN STELLAR
- Nirman Serenopolis
- ROHAN HARITA PHASE 4
- Millennium Samriddhi
- KOHINOOR UPTOWN AVENUE
- West World
Other projects by MERLIN BHINGARWALA DEVELOPERS LLP
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.