GANESH SIDDHI PHASE 3
by S B PATIL SPACES AND INFRA PVT LTD · Chikhali, PuneAlso near Rupeenagar, Chinchwad East, Akurdi
Possession date of GANESH SIDDHI PHASE 3: 30 October 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100045411, and currently active. Its completion date is now October 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about GANESH SIDDHI PHASE 3?
How the possession date of GANESH SIDDHI PHASE 3 has moved
30 June 2027
Completion date given when the project was registered
30 October 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: GANESH SIDDHI PHASE 3’s extension records on MahaRERA (P52100045411), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on GANESH SIDDHI PHASE 3
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the October 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- Ganesh Siddhi Phase 5P52100080668 · possession 30 Apr 2030
- MahaRERA registration
- P52100045411
- Status
- Registered and active
- Builder
- S B PATIL SPACES AND INFRA PVT LTD
- Location
- Chikhali, Pune · 411062
- Project type
- Others
- Registered on
- 18 May 2022
- Completion date at registration
- June 2027
- Latest completion date
- October 2027
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 233
- Sold or booked
- 0%
- Towers
- 3
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of GANESH SIDDHI PHASE 3, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| GANESH SIDDHI I WING | 100% | 20% | 0% | 0% |
| GANESH SIDDHI J WING | 100% | 20% | 0% | 0% |
| GANESH SIDDHI K WING | 100% | 20% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on GANESH SIDDHI PHASE 3 every month.
GANESH SIDDHI PHASE 3: buildings, flats and land, as filed on MahaRERA
- Buildings: GANESH SIDDHI I WING (12 floors) · GANESH SIDDHI J WING (12 floors) · GANESH SIDDHI K WING (13 floors)
- Land: 8,900 sq m (about 2.2 acres) · sanctioned built-up 16,595 sq m · recreational space 853 sq m
The builder’s record and reviews
Ganeshconstruction (a group of 3 linked companies) has 22 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 8 still being built, 4 past the promised date (typically 12 months late); 3 lapsed. 2 complaints on MahaRERA across 2 projects.
Read Google reviews of GANESH SIDDHI PHASE 3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
GANESH SIDDHI PHASE 3: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about GANESH SIDDHI PHASE 3
What is the possession date of GANESH SIDDHI PHASE 3?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for GANESH SIDDHI PHASE 3 in Chikhali, Pune is 30 October 2027, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for GANESH SIDDHI PHASE 3?
Builders and listing sites often quote an earlier "target" date for handover. The completion date GANESH SIDDHI PHASE 3's builder has filed on MahaRERA, the official one, is 30 October 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of GANESH SIDDHI PHASE 3?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of GANESH SIDDHI PHASE 3 in Chikhali, Pune is P52100045411.
Is GANESH SIDDHI PHASE 3 registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), GANESH SIDDHI PHASE 3 is registered as P52100045411 and its status is "Registered and active".
What is the construction status of GANESH SIDDHI PHASE 3?
According to GharKundli's check of MahaRERA records (updated November 2026), GANESH SIDDHI PHASE 3's status on MahaRERA is "Registered and active". As filed by the builder, slab work is 20% done across 3 towers. GharKundli's full report compares construction progress with the deadline.
Does GANESH SIDDHI PHASE 3 have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is GANESH SIDDHI PHASE 3 safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), GANESH SIDDHI PHASE 3 is registered on MahaRERA as P52100045411, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does GANESH SIDDHI PHASE 3 have other wings or phases?
Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: Ganesh Siddhi Phase 5 (P52100080668, possession 30 Apr 2030). Check that your agreement names the registration of your own wing.
How can I get updates if GANESH SIDDHI PHASE 3's possession date changes?
The latest dates are on GANESH SIDDHI PHASE 3's MahaRERA page (P52100045411). GharKundli's Kundli Watch sends a free WhatsApp update on GANESH SIDDHI PHASE 3 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does GANESH SIDDHI PHASE 3 have?
According to GharKundli's check of MahaRERA records (updated November 2026), GANESH SIDDHI PHASE 3 has 3 buildings filed: GANESH SIDDHI I WING with 12 floors; GANESH SIDDHI J WING with 12 floors; GANESH SIDDHI K WING with 13 floors.
How big is the land of GANESH SIDDHI PHASE 3?
According to GharKundli's check of MahaRERA records (updated November 2026), GANESH SIDDHI PHASE 3 stands on 8,900 sq m of land (about 2.2 acres), with 16,595 sq m of sanctioned built-up area and 853 sq m of recreational open space.
What is the track record of GANESH SIDDHI PHASE 3's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Ganeshconstruction (a group of 3 linked companies) has 22 projects on MahaRERA since 2017, this one included. Of the 11 GharKundli has checked: 8 still being built, 4 past the promised date (typically 12 months late); 3 lapsed. 2 complaints on MahaRERA across 2 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of GANESH SIDDHI PHASE 3?
Google Maps has reviews of GANESH SIDDHI PHASE 3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is GANESH SIDDHI PHASE 3?
GANESH SIDDHI PHASE 3 by S B PATIL SPACES AND INFRA PVT LTD is in Chikhali, Pune (pincode 411062), near Rupeenagar, Chinchwad East, Akurdi, Maharashtra, and is registered on MahaRERA as P52100045411, per GharKundli's check of MahaRERA records.
How many homes are in GANESH SIDDHI PHASE 3?
According to GharKundli's check of MahaRERA records (updated November 2026), GANESH SIDDHI PHASE 3 has 233 homes in 3 towers registered on MahaRERA, and 0% of them are sold or booked.
When was GANESH SIDDHI PHASE 3 registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), GANESH SIDDHI PHASE 3 was registered on MahaRERA on 18 May 2022. GharKundli did not find a title report on the land on file there.
Are there court cases on GANESH SIDDHI PHASE 3?
No court cases are listed for GANESH SIDDHI PHASE 3 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of GANESH SIDDHI PHASE 3?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is S B PATIL SPACES AND INFRA PVT LTD.
Check it yourself on MahaRERA
- How to check the possession date of GANESH SIDDHI PHASE 3
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Pune →
Other projects in pincode 411062
- SIDDHI NEST A1 A2
- VSG LEGACY ONE
- SAI SUVARNA
- Abhiman Vishwa
- RAGHAV RESERVE
- Mahadev Park
- AKSHA VRUNDAVAN II
- 24KG GOLD RESIDENCY
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.