Possession date of Ravindu: 30 November 2026. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100050148, and currently active. Its completion date is now November 2026, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about Ravindu?
How the possession date of Ravindu has moved
31 July 2026
Completion date given when the project was registered
30 November 2026
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Ravindu’s extension records on MahaRERA (P52100050148), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Ravindu
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the November 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100050148
- Status
- Registered and active
- Builder
- Shubh Ventures
- Location
- Bibwewadi, Pune · 411037
- Project type
- Residential / Group Housing
- Registered on
- 21 Mar 2023
- Completion date at registration
- July 2026
- Latest completion date
- November 2026
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 53
- Sold or booked
- 85%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Ravindu, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Wing A and B | 0% | 0% | 0% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Ravindu every month.
Ravindu: buildings, flats and land, as filed on MahaRERA
- Buildings: Wing A and B (9 floors)
- Land: 1,325 sq m (about 0.3 acres) · sanctioned built-up 2,955 sq m
The builder’s record and reviews
Shri Laxmi Narayan Properties (a group of 2 linked companies) has 10 projects on MahaRERA since 2022, this one included. Of the 10 GharKundli has checked: 3 finished, 2 within the promised date and 1 needed more time (typically 19 months); 6 still being built, none past the promised date yet; 1 lapsed. 1 complaint on MahaRERA across 1 project.
Read Google reviews of Ravindu →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Ravindu: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about Ravindu
What is the possession date of Ravindu?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Ravindu in Bibwewadi, Pune is 30 November 2026, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for Ravindu?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Ravindu's builder has filed on MahaRERA, the official one, is 30 November 2026, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of Ravindu?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Ravindu in Bibwewadi, Pune is P52100050148.
Is Ravindu registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Ravindu is registered as P52100050148 and its status is "Registered and active".
What is the construction status of Ravindu?
According to GharKundli's check of MahaRERA records (updated November 2026), Ravindu's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Wing A and B is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.
Does Ravindu have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is Ravindu safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), Ravindu is registered on MahaRERA as P52100050148, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if Ravindu's possession date changes?
The latest dates are on Ravindu's MahaRERA page (P52100050148). GharKundli's Kundli Watch sends a free WhatsApp update on Ravindu every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Ravindu have?
According to GharKundli's check of MahaRERA records (updated November 2026), Ravindu has one building filed: Wing A and B with 9 floors.
How big is the land of Ravindu?
According to GharKundli's check of MahaRERA records (updated November 2026), Ravindu stands on 1,325 sq m of land (about 0.3 acres), with 2,955 sq m of sanctioned built-up area.
What is the track record of Ravindu's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Shri Laxmi Narayan Properties (a group of 2 linked companies) has 10 projects on MahaRERA since 2022, this one included. Of the 10 GharKundli has checked: 3 finished, 2 within the promised date and 1 needed more time (typically 19 months); 6 still being built, none past the promised date yet; 1 lapsed. 1 complaint on MahaRERA across 1 project. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of Ravindu?
Google Maps has reviews of Ravindu written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is Ravindu?
Ravindu by Shubh Ventures is in Bibwewadi, Pune (pincode 411037), near Theur, Maharashtra, and is registered on MahaRERA as P52100050148, per GharKundli's check of MahaRERA records.
How many homes are in Ravindu?
According to GharKundli's check of MahaRERA records (updated November 2026), Ravindu has 53 homes in 1 tower registered on MahaRERA, and 85% of them are sold or booked.
When was Ravindu registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), Ravindu was registered on MahaRERA on 21 March 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on Ravindu?
No court cases are listed for Ravindu on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of Ravindu?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Shubh Ventures.
Check it yourself on MahaRERA
- How to check the possession date of Ravindu
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Pune →
Other projects in pincode 411037
- WEST VIEW
- Shreeram Shree
- Prathamesh Shreeprabha
- Siddhi Safalya
- Anandi
- GANGADHAM TOWERS COMMERCIAL
- Nirvana
- MANSION
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.