Elanza Commercial

by Acme Complex Pvt Ltd · Vile Parle West, MumbaiAlso near Ghatkopar East, Ghatkopar West, Pant Nagar

Possession date of Elanza Commercial: 30 April 2028, moved from 31 December 2019 (96 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P51800001479, and currently active. Its completion date has moved from December 2019 to April 2028: 96 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.

Source: GharKundli’s check of MahaRERA records, October 2026.

What do you want to know about Elanza Commercial?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Elanza Commercial has moved

  1. 31 December 2019

    Completion date given when the project was registered

  2. 30 December 2020

    Extended at the builder's request (MahaRERA application EXT51800003844)

    Reason the builder gave MahaRERA:
    “• It was an on-going project when registered with MahaRERA. • 15 months delay - There was an encroachment in the set-back area which needed to be removed before getting the further approval it took almost 1.5 years to clear the same for tha…” Read the full reason“• It was an on-going project when registered with MahaRERA. • 15 months delay - There was an encroachment in the set-back area which needed to be removed before getting the further approval it took almost 1.5 years to clear the same for that we have filed writ petition bearing WP/2613/2016 on 23/08/2016 which was finally disposed off vide order dated 28/11/2017. • 14 months delay - Inspite of the order as above when the corporation had not complied with order within time, hence we have filed contempt petition against MCGM bearing contempt petition No. CONPWL/126 of 2018 which was filed on 2…”
  3. 31 December 2027

    Extended at the builder's request (MahaRERA application EA23022619965)

    Reason the builder gave MahaRERA:
    “• It was an on-going project when registered with MahaRERA. • 4 months Delay–Unforeseen ground conditions and limited site access or space constraints. •15 months delay - There was an encroachment in the set-back area which needed to be rem…” Read the full reason“• It was an on-going project when registered with MahaRERA. • 4 months Delay–Unforeseen ground conditions and limited site access or space constraints. •15 months delay - There was an encroachment in the set-back area which needed to be removed before getting the further approval it took almost 1.5 years to clear the same for that we have filed writ petition bearing WP/2613/2016 on 23/08/2016 which was finally disposed off vide order dated 28/11/2017. • 14 months delay – Inspite of the order as above when the corporation had not complied with order within time, hence we have filed contempt…”
  4. 30 April 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Elanza Commercial’s extension records on MahaRERA (P51800001479), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Elanza Commercial

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 9 court cases, and how it ended
  • Construction pace against the April 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800001479
Status
Registered and active
Builder
Acme Complex Pvt Ltd
Location
Vile Parle West, Mumbai · 400086
Project type
Commercial
Registered on
28 Jul 2017
Completion date at registration
December 2019
Latest completion date
April 2028
Delay so far
96 months
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
0
Sold or booked
73%
Towers
1
Complaints on MahaRERA
0
Court cases listed
9
Title report on file
Not found
Builder's other MahaRERA projects
1

Construction progress of Elanza Commercial, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
Elanza Commercial100%100%50%25%

Commencement certificate (CC), as filed on MahaRERA

  • Elanza Commercial: covers Ground Floor

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Elanza Commercial every month.

Elanza Commercial: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
Shops257 – 57015

The builder’s record and reviews

Acme Complex (a group of 3 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 23 months); 3 still being built, 3 past the promised date (typically 52 months late); 2 lapsed. 54 complaints on MahaRERA across 5 projects.

Read Google reviews of Elanza Commercial →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Elanza Commercial: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Elanza Commercial

What is the possession date of Elanza Commercial?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Elanza Commercial in Vile Parle West, Mumbai is 30 April 2028 — 96 months later than 31 December 2019, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Elanza Commercial?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Elanza Commercial's builder has filed on MahaRERA, the official one, is 30 April 2028, already 96 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of Elanza Commercial extended?

According to GharKundli's check of MahaRERA records (updated October 2026), Elanza Commercial's builder applied to MahaRERA to extend the completion date 2 times: to 30 December 2020, giving the reason "• It was an on-going project when registered with MahaRERA. • 15 months delay - There was an encroachment in the set-back area which needed to be removed before getting the further approval it took almost 1.5 years to clear the same for that we have filed writ petition bearing WP/2613/2016 on 23/08/2016 which was finally disposed off vide order dated 28/11/2017. • 14 months delay - Inspite of the order as above when the corporation had not complied with order within time, hence we have filed contempt petition against MCGM bearing contempt petition No. CONPWL/126 of 2018 which was filed on 2…"; to 31 December 2027, giving the reason "• It was an on-going project when registered with MahaRERA. • 4 months Delay–Unforeseen ground conditions and limited site access or space constraints. •15 months delay - There was an encroachment in the set-back area which needed to be removed before getting the further approval it took almost 1.5 years to clear the same for that we have filed writ petition bearing WP/2613/2016 on 23/08/2016 which was finally disposed off vide order dated 28/11/2017. • 14 months delay – Inspite of the order as above when the corporation had not complied with order within time, hence we have filed contempt…". MahaRERA also added its automatic 4-month extension for all eligible projects.

What is the RERA number of Elanza Commercial?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Elanza Commercial in Vile Parle West, Mumbai is P51800001479.

Is Elanza Commercial registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Elanza Commercial is registered as P51800001479 and its status is "Registered and active".

What is the construction status of Elanza Commercial?

According to GharKundli's check of MahaRERA records (updated October 2026), Elanza Commercial's status on MahaRERA is "Registered and active". As filed by the builder, slab work on Elanza Commercial is 100% done and internal work 50%. GharKundli's full report compares construction progress with the deadline.

Does Elanza Commercial have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is Elanza Commercial safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), Elanza Commercial is registered on MahaRERA as P51800001479, its completion date has moved 96 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Elanza Commercial's possession date changes?

The latest dates are on Elanza Commercial's MahaRERA page (P51800001479). GharKundli's Kundli Watch sends a free WhatsApp update on Elanza Commercial every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Elanza Commercial have?

According to GharKundli's check of MahaRERA records (updated October 2026), Elanza Commercial has one building filed: Elanza Commercial with 1 floors and 15 units.

How much parking does Elanza Commercial have?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 12 covered car parking spaces for Elanza Commercial.

How big is the land of Elanza Commercial?

According to GharKundli's check of MahaRERA records (updated October 2026), Elanza Commercial stands on 580 sq m of land (about 0.1 acres), with 463 sq m of sanctioned built-up area.

What is the track record of Elanza Commercial's builder?

According to GharKundli's check of MahaRERA records (updated October 2026), Acme Complex (a group of 3 linked companies) has 9 projects on MahaRERA since 2017, this one included. Of the 7 GharKundli has checked: 2 finished, 1 within the promised date and 1 needed more time (typically 23 months); 3 still being built, 3 past the promised date (typically 52 months late); 2 lapsed. 54 complaints on MahaRERA across 5 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Elanza Commercial?

Google Maps has reviews of Elanza Commercial written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Elanza Commercial?

Elanza Commercial by Acme Complex Pvt Ltd is in Vile Parle West, Mumbai (pincode 400086), near Ghatkopar East, Ghatkopar West, Pant Nagar, Maharashtra, and is registered on MahaRERA as P51800001479, per GharKundli's check of MahaRERA records.

How many homes are in Elanza Commercial?

According to GharKundli's check of MahaRERA records (updated October 2026), Elanza Commercial has 0 homes in 1 tower registered on MahaRERA, and 73% of them are sold or booked.

When was Elanza Commercial registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), Elanza Commercial was registered on MahaRERA on 28 July 2017. GharKundli did not find a title report on the land on file there.

Are there court cases on Elanza Commercial?

9 court cases are listed for Elanza Commercial on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Elanza Commercial?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is Acme Complex Pvt Ltd, which has 1 other project registered on MahaRERA.

All projects with possession due in 2028 in Mumbai Suburban →

Other projects in Vile Parle West

All 83 projects in Ghatkopar West (400086) →

Other projects by Acme Complex Pvt Ltd

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.