56 PARK AVENUE
by KRISHANG INFRA PRIVATE LIMITED · Vile Parle West, MumbaiAlso near Vile Parle East, Andheri, Borivali West
Possession date of 56 PARK AVENUE: 31 December 2026, moved from 31 December 2024 (24 months later). This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800052268, and currently active.
Source: GharKundli’s check of MahaRERA records, October 2026.
What do you want to know about 56 PARK AVENUE?
How the possession date of 56 PARK AVENUE has moved
31 December 2024
Completion date given when the project was registered
31 December 2025
Extended at the builder's request (MahaRERA application EXT51800027353)
Reason the builder gave MahaRERA:
“In light of this development, we intend to utilise the additional FSI as per the new guidelines. To facilitate this process and complete the requisite formalities, we humbly request an extension of I 2 months. This extension will allow us t…” Read the full reason
“In light of this development, we intend to utilise the additional FSI as per the new guidelines. To facilitate this process and complete the requisite formalities, we humbly request an extension of I 2 months. This extension will allow us to: 1. Apply for and secure the additional FSI under the revised DCPR. 2. Complete the remaining construction”31 December 2026
Extended at the builder's request (MahaRERA application EA17022619863)
Reason the builder gave MahaRERA:
“We, Krishang Infra Pvt. Ltd. are the promoters of the real estate project known as "56 Park Avenue, Himanshu Mandar CHSL" bearing Maha RERA Registration No. P51800052268.We would like to respectfully bring to your attention that the project…” Read the full reason
“We, Krishang Infra Pvt. Ltd. are the promoters of the real estate project known as "56 Park Avenue, Himanshu Mandar CHSL" bearing Maha RERA Registration No. P51800052268.We would like to respectfully bring to your attention that the project has encountered certain unforeseen technical challenges that have adversely impacted the originally proposed timelines for completion. We wish to place on record the following reasons for the delay:1. Delay in Statutory Clearances/Utility Approvals The redesigning and revised approvals of the plans had to be procured from BMC, and other government author…”
Source: 56 PARK AVENUE’s extension records on MahaRERA (P51800052268), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on 56 PARK AVENUE
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the December 2026 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800052268
- Status
- Registered and active
- Builder
- KRISHANG INFRA PRIVATE LIMITED
- Location
- Vile Parle West, Mumbai · 400056
- Project type
- Residential / Group Housing
- Registered on
- 9 Aug 2023
- Completion date at registration
- December 2024
- Latest completion date
- December 2026
- Delay so far
- 24 months
- Homes
- 37
- Sold or booked
- 100%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of 56 PARK AVENUE, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| 56 PARK AVENUE | 100% | 100% | 95% | 96% |
Commencement certificate (CC), as filed on MahaRERA
- 56 PARK AVENUE: covers 1ST TO 10 TH FLOORS
Want to know when this changes? Kundli Watch sends a free WhatsApp update on 56 PARK AVENUE every month.
56 PARK AVENUE: buildings, flats and land, as filed on MahaRERA
| Type | Carpet area (sq ft) | Units |
|---|---|---|
| 2 BHK | 404 – 642 | 36 |
| 4 BHK | 1,029 | 1 |
- Buildings: 56 PARK AVENUE (11 floors, 37 units)
- Car parking: 28 covered
- Land: 920 sq m (about 0.2 acres) · sanctioned built-up 1,922 sq m
- Boundaries filed include: Nav Bahar Society
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of 56 PARK AVENUE →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
56 PARK AVENUE: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about 56 PARK AVENUE
What is the possession date of 56 PARK AVENUE?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for 56 PARK AVENUE in Vile Parle West, Mumbai is 31 December 2026 — 24 months later than 31 December 2024, the date given at registration.
Is the builder's possession date different from the MahaRERA date for 56 PARK AVENUE?
Builders and listing sites often quote an earlier "target" date for handover. The completion date 56 PARK AVENUE's builder has filed on MahaRERA, the official one, is 31 December 2026, already 24 months later than the 31 December 2024 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of 56 PARK AVENUE extended?
According to GharKundli's check of MahaRERA records (updated October 2026), 56 PARK AVENUE's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "In light of this development, we intend to utilise the additional FSI as per the new guidelines. To facilitate this process and complete the requisite formalities, we humbly request an extension of I 2 months. This extension will allow us to: 1. Apply for and secure the additional FSI under the revised DCPR. 2. Complete the remaining construction"; to 31 December 2026, giving the reason "We, Krishang Infra Pvt. Ltd. are the promoters of the real estate project known as "56 Park Avenue, Himanshu Mandar CHSL" bearing Maha RERA Registration No. P51800052268.We would like to respectfully bring to your attention that the project has encountered certain unforeseen technical challenges that have adversely impacted the originally proposed timelines for completion. We wish to place on record the following reasons for the delay:1. Delay in Statutory Clearances/Utility Approvals The redesigning and revised approvals of the plans had to be procured from BMC, and other government author…".
What is the RERA number of 56 PARK AVENUE?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of 56 PARK AVENUE in Vile Parle West, Mumbai is P51800052268.
Is 56 PARK AVENUE registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), 56 PARK AVENUE is registered as P51800052268 and its status is "Registered and active".
What is the construction status of 56 PARK AVENUE?
According to GharKundli's check of MahaRERA records (updated October 2026), 56 PARK AVENUE's status on MahaRERA is "Registered and active". As filed by the builder, slab work on 56 PARK AVENUE is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does 56 PARK AVENUE have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is 56 PARK AVENUE safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), 56 PARK AVENUE is registered on MahaRERA as P51800052268, its completion date has moved 24 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if 56 PARK AVENUE's possession date changes?
The latest dates are on 56 PARK AVENUE's MahaRERA page (P51800052268). GharKundli's Kundli Watch sends a free WhatsApp update on 56 PARK AVENUE every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does 56 PARK AVENUE have?
According to GharKundli's check of MahaRERA records (updated October 2026), 56 PARK AVENUE has one building filed: 56 PARK AVENUE with 11 floors and 37 units.
What are the flat sizes (carpet area) in 56 PARK AVENUE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for 56 PARK AVENUE: 2 BHK: 404 to 642 sq ft carpet (36 homes); 4 BHK: 1029 sq ft carpet (1 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.
How much parking does 56 PARK AVENUE have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 28 covered car parking spaces for 56 PARK AVENUE.
How big is the land of 56 PARK AVENUE?
According to GharKundli's check of MahaRERA records (updated October 2026), 56 PARK AVENUE stands on 920 sq m of land (about 0.2 acres), with 1,922 sq m of sanctioned built-up area.
Where can I read reviews of 56 PARK AVENUE?
Google Maps has reviews of 56 PARK AVENUE written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is 56 PARK AVENUE?
56 PARK AVENUE by KRISHANG INFRA PRIVATE LIMITED is in Vile Parle West, Mumbai (pincode 400056), near Vile Parle East, Andheri, Borivali West, Maharashtra, and is registered on MahaRERA as P51800052268, per GharKundli's check of MahaRERA records. Its boundaries filed there include Nav Bahar Society.
How many homes are in 56 PARK AVENUE?
According to GharKundli's check of MahaRERA records (updated October 2026), 56 PARK AVENUE has 37 homes in 1 tower registered on MahaRERA, and 100% of them are sold or booked.
When was 56 PARK AVENUE registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), 56 PARK AVENUE was registered on MahaRERA on 9 August 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on 56 PARK AVENUE?
No court cases are listed for 56 PARK AVENUE on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder of 56 PARK AVENUE?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is KRISHANG INFRA PRIVATE LIMITED.
Check it yourself on MahaRERA
- How to check the possession date of 56 PARK AVENUE
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2026 in Mumbai Suburban →
Other projects in pincode 400056
- TULSIDHAM CHS
- DURGA GAYATRI
- PARSHWA DARSHAN CO OPERATIVE HOUSING SOCIETY LIMITED
- AVANT PARK WEST
- PRAMUKH SHRINIKET APARTMENTS
- ARAVE
- MESACON BLISS
- VEER ELEGANCE
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.