TULSIDHAM CHS

by SM & HAPPY HOME ASSOCIATES · Vile Parle West, MumbaiAlso near Vileparle West, Vileeparle East, Juhu

Possession date of TULSIDHAM CHS: 30 September 2026, moved from 30 December 2022 (45 months later). This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P51800021413. Status: Lapsed (registration period ended).

Source: GharKundli’s check of MahaRERA records, October 2026.

The latest completion date on MahaRERA (September 2026) has passed.

What do you want to know about TULSIDHAM CHS?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of TULSIDHAM CHS has moved

  1. 30 December 2022

    Completion date given when the project was registered

  2. 31 December 2025

    Extended at the builder's request (MahaRERA application EXT51800019305)

    Reason the builder gave MahaRERA:
    “As promoters of the project mentioned above, we must inform you that during the initial stages of redevelopment, we were in the process of acquiring additional Transfer of Development Rights (TDR). However, due to a sudden change in the rul…” Read the full reason“As promoters of the project mentioned above, we must inform you that during the initial stages of redevelopment, we were in the process of acquiring additional Transfer of Development Rights (TDR). However, due to a sudden change in the rules set by the Municipal Corporation of Greater Mumbai (MCGM) regarding road width and the loading of additional TDR, we have encountered obstacles in completing the TDR purchase process. According to the Development Control and Promotion Regulation (DCPR) - 2034 and the Notification of the Municipal Corporation of Greater Mumbai (MCGM), if the height of a…”
  3. 30 September 2026

    Extended at the builder's request (MahaRERA application EA01042620520)

    Reason the builder gave MahaRERA: “OC APPLIED ON 27.02.2025 AND RECEIVED ON 13.01.2026.HENCE WE NEED EXTENTION FOR UPLOADING COMPLETIION DETAILS,OC AND FORM 5.”

Source: TULSIDHAM CHS’s extension records on MahaRERA (P51800021413), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on TULSIDHAM CHS

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the September 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P51800021413
Status
Lapsed (registration period ended)
Builder
SM & HAPPY HOME ASSOCIATES
Location
Vile Parle West, Mumbai · 400056
Project type
Residential / Group Housing
Registered on
26 Jun 2019
Completion date at registration
December 2022
Latest completion date
September 2026
Delay so far
45 months
Homes
15
Sold or booked
83%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Construction progress of TULSIDHAM CHS, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
TULSIDHAM100%100%100%100%

Commencement certificate (CC), as filed on MahaRERA

  • TULSIDHAM: covers 6+1 stilt

Want to know when this changes? Kundli Watch sends a free WhatsApp update on TULSIDHAM CHS every month.

TULSIDHAM CHS: buildings, flats and land, as filed on MahaRERA

TypeCarpet area (sq ft)Units
1 BHK358 – 50111
3 BHK785 – 8542
2 BHK562 – 6172
  • Buildings: TULSIDHAM (7 floors, 15 units)
  • Land: 399 sq m (about 0.1 acres) · sanctioned built-up 808 sq m
  • Boundaries filed include: ANIDEEP HOSPITAL

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of TULSIDHAM CHS →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

TULSIDHAM CHS: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about TULSIDHAM CHS

What is the possession date of TULSIDHAM CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for TULSIDHAM CHS in Vile Parle West, Mumbai is 30 September 2026 — 45 months later than 30 December 2022, the date given at registration. That date has already passed.

Is the builder's possession date different from the MahaRERA date for TULSIDHAM CHS?

Builders and listing sites often quote an earlier "target" date for handover. The completion date TULSIDHAM CHS's builder has filed on MahaRERA, the official one, is 30 September 2026, already 45 months later than the 30 December 2022 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

Why was the possession date of TULSIDHAM CHS extended?

According to GharKundli's check of MahaRERA records (updated October 2026), TULSIDHAM CHS's builder applied to MahaRERA to extend the completion date 2 times: to 31 December 2025, giving the reason "As promoters of the project mentioned above, we must inform you that during the initial stages of redevelopment, we were in the process of acquiring additional Transfer of Development Rights (TDR). However, due to a sudden change in the rules set by the Municipal Corporation of Greater Mumbai (MCGM) regarding road width and the loading of additional TDR, we have encountered obstacles in completing the TDR purchase process. According to the Development Control and Promotion Regulation (DCPR) - 2034 and the Notification of the Municipal Corporation of Greater Mumbai (MCGM), if the height of a…"; to 30 September 2026, giving the reason "OC APPLIED ON 27.02.2025 AND RECEIVED ON 13.01.2026.HENCE WE NEED EXTENTION FOR UPLOADING COMPLETIION DETAILS,OC AND FORM 5.".

What is the RERA number of TULSIDHAM CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of TULSIDHAM CHS in Vile Parle West, Mumbai is P51800021413.

Is TULSIDHAM CHS registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), TULSIDHAM CHS is registered as P51800021413 and its status is "Lapsed (registration period ended)".

What is the construction status of TULSIDHAM CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), TULSIDHAM CHS's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on TULSIDHAM is 100% done and internal work 100%. GharKundli's full report compares construction progress with the deadline.

Does TULSIDHAM CHS have complaints on MahaRERA?

No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.

Is TULSIDHAM CHS safe to buy?

According to GharKundli's check of MahaRERA records (updated October 2026), TULSIDHAM CHS is registered on MahaRERA as P51800021413, its MahaRERA status is "Lapsed (registration period ended)", its completion date has moved 45 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if TULSIDHAM CHS's possession date changes?

The latest dates are on TULSIDHAM CHS's MahaRERA page (P51800021413). GharKundli's Kundli Watch sends a free WhatsApp update on TULSIDHAM CHS every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does TULSIDHAM CHS have?

According to GharKundli's check of MahaRERA records (updated October 2026), TULSIDHAM CHS has one building filed: TULSIDHAM with 7 floors and 15 units.

What are the flat sizes (carpet area) in TULSIDHAM CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed these homes for TULSIDHAM CHS: 1 BHK: 358 to 501 sq ft carpet (11 homes); 3 BHK: 785 to 854 sq ft carpet (2 homes); 2 BHK: 562 to 617 sq ft carpet (2 homes). Carpet area is the usable floor area inside the walls, as defined under RERA.

How big is the land of TULSIDHAM CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), TULSIDHAM CHS stands on 399 sq m of land (about 0.1 acres), with 808 sq m of sanctioned built-up area.

Where can I read reviews of TULSIDHAM CHS?

Google Maps has reviews of TULSIDHAM CHS written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is TULSIDHAM CHS?

TULSIDHAM CHS by SM & HAPPY HOME ASSOCIATES is in Vile Parle West, Mumbai (pincode 400056), near Vileparle West, Vileeparle East, Juhu, Maharashtra, and is registered on MahaRERA as P51800021413, per GharKundli's check of MahaRERA records. Its boundaries filed there include ANIDEEP HOSPITAL.

How many homes are in TULSIDHAM CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), TULSIDHAM CHS has 15 homes in 1 tower registered on MahaRERA, and 83% of them are sold or booked.

When was TULSIDHAM CHS registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated October 2026), TULSIDHAM CHS was registered on MahaRERA on 26 June 2019. GharKundli did not find a title report on the land on file there.

Are there court cases on TULSIDHAM CHS?

No court cases are listed for TULSIDHAM CHS on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).

Who is the builder of TULSIDHAM CHS?

According to GharKundli's check of MahaRERA records (updated October 2026), the builder is SM & HAPPY HOME ASSOCIATES.

All projects with possession due in 2026 in Mumbai Suburban →

Other projects in pincode 400056

All 88 projects in Vile Parle West (400056) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.