by BADHEKAR & PITALE PROJECTS LLP · Ganeshkhind, Pune 411007Also near N.C.L. Pune, Range HillsRegistered on MahaRERA as “SANJEEVAN”
What’s in the report? →Possession date of Badhekar Sanjeevan (MahaRERA P52100050507): 30 April 2027, moved from 31 March 2026 (9 months later). It has 14 homes, 14% sold or booked. No complaints on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100050507, and currently active. Its completion date has moved from March 2026 to April 2027: 9 months at the builder's request, plus MahaRERA's automatic 4-month extension for all eligible projects.
Source: MahaRERA website — records for P52100050507, read and compiled by GharKundli. Facts as filed on MahaRERA, no opinions.
What do you want to know about Badhekar Sanjeevan?
Title report MahaRERA par nahi dikh rahi. Kya poochna hai?Tap a question. We’ll answer you on WhatsApp, free.
How the possession date of Badhekar Sanjeevan has moved
31 March 2026
Completion date given when the project was registered
31 December 2026
Extended at the builder's request (MahaRERA application EA11042620615)
Reason the builder gave MahaRERA: “Finishing activities and common areas of the building are yet to be completed. Thus we request you to please provide us with the mentioned extension.”
30 April 2027
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: Badhekar Sanjeevan’s extension records on MahaRERA (P52100050507), read by GharKundli in October 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on Badhekar Sanjeevan
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the April 2027 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P52100050507
- Status
- Registered and active
- Builder
- BADHEKAR & PITALE PROJECTS LLP
- Location
- Ganeshkhind, Pune · 411007
- Project type
- Residential / Group Housing
- Registered on
- 17 Apr 2023
- Completion date at registration
- March 2026
- Latest completion date
- April 2027
- Delay so far
- 9 months
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 14
- Sold or booked
- 14%
- Towers
- 1
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
Construction progress of Badhekar Sanjeevan, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in October 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| SANJEEVAN | 0% | 100% | 95% | 40% |
Commencement certificate (CC), as filed on MahaRERA
- SANJEEVAN: covers 8 floors
Latest CC order on MahaRERA: dated 20/06/2025.
Want to know when this changes? Kundli Watch sends a free WhatsApp update on Badhekar Sanjeevan every 1–2 months.
Badhekar Sanjeevan: buildings, flats and land, as filed on MahaRERA
- Buildings: SANJEEVAN (8 floors, 14 units)
- Car parking: 15 covered
- Land: 516 sq m (about 0.1 acres) · sanctioned built-up 1,602 sq m
- Land, as filed: S.NO.251/3/11+252/1/2
- Map: Get directions
The builder’s record and reviews
Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.
Read Google reviews of Badhekar Sanjeevan →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
Badhekar Sanjeevan: buyers & owners
Free: a construction progress update on WhatsApp every 1–2 months, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Watching needs only WhatsApp or your number. Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. Owners and the builder’s team sign in with a one-time code, then come straight back here.
Common questions about Badhekar Sanjeevan
What is the possession date of Badhekar Sanjeevan?
According to GharKundli's check of MahaRERA records (updated October 2026), the latest completion date filed on MahaRERA for Badhekar Sanjeevan in Ganeshkhind, Pune is 30 April 2027 — 9 months later than 31 March 2026, the date given at registration, plus MahaRERA's automatic 4-month extension for all eligible projects.
The date has already moved 9 months. Will it move again? Check the real pace of construction →
Is the builder's possession date different from the MahaRERA date for Badhekar Sanjeevan?
Builders and listing sites often quote an earlier "target" date for handover. The completion date Badhekar Sanjeevan's builder has filed on MahaRERA, the official one, is 30 April 2027, already 9 months later than the 31 March 2026 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of Badhekar Sanjeevan extended?
According to GharKundli's check of MahaRERA records (updated October 2026), Badhekar Sanjeevan's builder applied to MahaRERA to extend the completion date once: to 31 December 2026, giving the reason "Finishing activities and common areas of the building are yet to be completed. Thus we request you to please provide us with the mentioned extension.". MahaRERA also added its automatic 4-month extension for all eligible projects.
What is the RERA number of Badhekar Sanjeevan?
According to GharKundli's check of MahaRERA records (updated October 2026), the MahaRERA registration number of Badhekar Sanjeevan in Ganeshkhind, Pune is P52100050507.
Is Badhekar Sanjeevan registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Badhekar Sanjeevan is registered as P52100050507 and its status is "Registered and active".
What is the current construction status of Badhekar Sanjeevan? How much work is done?
According to GharKundli's check of MahaRERA records (updated October 2026), Badhekar Sanjeevan's status on MahaRERA is "Registered and active". As filed by the builder, slab work on SANJEEVAN is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.
Does Badhekar Sanjeevan have complaints on MahaRERA?
No complaints were listed on MahaRERA as of October 2026, per GharKundli's weekly check.
Is Badhekar Sanjeevan safe to buy?
According to GharKundli's check of MahaRERA records (updated October 2026), Badhekar Sanjeevan is registered on MahaRERA as P52100050507, its completion date has moved 9 months since registration and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How much GST is payable on a flat in Badhekar Sanjeevan?
Badhekar Sanjeevan is under construction, so GST applies to a new flat: 5% of the price, with no input tax credit. The lower 1% rate is only for "affordable" homes: carpet area up to 90 sq m (about 969 sq ft) outside the Mumbai region, and price up to ₹45 lakh. There is no GST on stamp duty or registration, and none once the occupancy certificate is issued.
What is the stamp duty and registration cost for a flat in Badhekar Sanjeevan?
In Maharashtra, stamp duty is between 3% and 7% of the agreement value (or the ready reckoner value, if higher), depending on the city's local cesses: about 6–7% in big cities, less in municipal-council and village areas. A woman buying in her own name pays 1% less. Registration is 1%, capped at ₹30,000. GharKundli's property cost calculator works it out for the price of a flat in Badhekar Sanjeevan: gharkundli.com/tools/property-cost-calculator
Has Badhekar Sanjeevan received its OC? Is it ready to move in?
Not yet. According to GharKundli's check of MahaRERA records (updated October 2026), Badhekar Sanjeevan is still under construction, with 30 April 2027 as the latest completion date filed on MahaRERA. A flat is ready to move in only once the occupancy certificate (OC) is issued, after construction is complete.
Has Badhekar Sanjeevan uploaded its title report on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), no title report for Badhekar Sanjeevan was found on MahaRERA. Builders are expected to upload one; before booking, ask the builder for the advocate's title certificate in writing.
No title report is on MahaRERA for this project. See which documents are missing →
How can I get updates if Badhekar Sanjeevan's possession date changes?
The latest dates are on Badhekar Sanjeevan's MahaRERA page (P52100050507). GharKundli's Kundli Watch sends a free WhatsApp update on Badhekar Sanjeevan every 1–2 months, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does Badhekar Sanjeevan have?
According to GharKundli's check of MahaRERA records (updated October 2026), Badhekar Sanjeevan has one building filed: SANJEEVAN with 8 floors and 14 units.
How much parking does Badhekar Sanjeevan have?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder has filed 15 covered car parking spaces for Badhekar Sanjeevan.
How big is the land of Badhekar Sanjeevan?
According to GharKundli's check of MahaRERA records (updated October 2026), Badhekar Sanjeevan stands on 516 sq m of land (about 0.1 acres), with 1,602 sq m of sanctioned built-up area.
What are the reviews of Badhekar Sanjeevan?
Google Maps has reviews of Badhekar Sanjeevan written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
What is the address and pincode of Badhekar Sanjeevan?
Badhekar Sanjeevan by BADHEKAR & PITALE PROJECTS LLP is in Ganeshkhind, Pune, pincode 411007 (near N.C.L. Pune, Range Hills), Maharashtra, and is registered on MahaRERA as P52100050507, per GharKundli's check of MahaRERA records. Its land is filed as S.NO.251/3/11+252/1/2. GharKundli lists all 88 MahaRERA projects in Aundh (411007).
How many flats are in Badhekar Sanjeevan, and how many are sold?
According to GharKundli's check of MahaRERA records (updated October 2026), Badhekar Sanjeevan has 14 homes in 1 tower registered on MahaRERA, and 14% of them are sold or booked.
When was Badhekar Sanjeevan registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated October 2026), Badhekar Sanjeevan was registered on MahaRERA on 17 April 2023. GharKundli did not find a title report on the land on file there.
Does Badhekar Sanjeevan have any legal issues or court cases?
No court cases are listed for Badhekar Sanjeevan on MahaRERA, per GharKundli's check of MahaRERA records (updated October 2026).
Who is the builder / developer of Badhekar Sanjeevan?
According to GharKundli's check of MahaRERA records (updated October 2026), the builder is BADHEKAR & PITALE PROJECTS LLP.
Check it yourself on MahaRERA
- How to check the possession date of Badhekar Sanjeevan
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2027 in Pune →
Other projects in Aundh (411007)
- Brain Matrix
- Toran
- Pant Sarathi Builders LLP
- Trinayan
- Aundh Renaissance
- Avanti Park
- The Crest
- Hrishikesh and Vasantili Apartment
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of October 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.