24K Altura - Tower A and B
by KOLTE-PATIL DEVELOPERS LIMITED · Baner, Pune
Possession date of 24K Altura - Tower A and B: 31 July 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself
Registered on MahaRERA under P52100051316, and currently active. Its completion date is now July 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about 24K Altura - Tower A and B?
How the possession date of 24K Altura - Tower A and B has moved
31 March 2028
Completion date given when the project was registered
31 July 2028
MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request
Source: 24K Altura - Tower A and B’s extension records on MahaRERA (P52100051316), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on 24K Altura - Tower A and B
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each complaint and court case, and how it ended
- Construction pace against the July 2028 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
Other wings and phases of this project
Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.
- 24K Altura - Tower CP52100077098 · possession 30 Apr 2031
- 24K Altura - Tower DP52100054175 · possession 31 Jul 2029
- MahaRERA registration
- P52100051316
- Status
- Registered and active
- Builder
- KOLTE-PATIL DEVELOPERS LIMITED
- Location
- Baner, Pune · 411045
- Project type
- Residential / Group Housing
- Registered on
- 8 Jun 2023
- Completion date at registration
- March 2028
- Latest completion date
- July 2028
- MahaRERA's automatic extension
- +4 months (force majeure, all eligible projects)
- Homes
- 264
- Sold or booked
- 96%
- Towers
- 2
- Complaints on MahaRERA
- 0
- Court cases listed
- 0
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 63
Construction progress of 24K Altura - Tower A and B, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| Tower A | 100% | 86% | 54% | 0% |
| Tower B | 100% | 89% | 53% | 0% |
Commencement certificate (CC), as filed on MahaRERA
- Tower A: covers 32 floors
- Tower B: covers 30 floors
Want to know when this changes? Kundli Watch sends a free WhatsApp update on 24K Altura - Tower A and B every month.
24K Altura - Tower A and B: buildings, flats and land, as filed on MahaRERA
- Buildings: Tower A (32 floors, 109 units) · Tower B (30 floors, 155 units)
- Land: 2,740 sq m (about 0.7 acres) · sanctioned built-up 48,989 sq m · recreational space 2,859 sq m
- Boundaries filed include: 12 Mtr Service Road
The builder’s record and reviews
Kolte-patil Developers has 64 projects on MahaRERA since 2017, this one included. Of the 55 GharKundli has checked: 11 finished, 6 within the promised date and 5 needed more time (typically 9 months); 40 still being built, 2 past the promised date (typically 8 months late); 4 lapsed. 29 complaints on MahaRERA across 19 projects.
Read Google reviews of 24K Altura - Tower A and B →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
24K Altura - Tower A and B: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about 24K Altura - Tower A and B
What is the possession date of 24K Altura - Tower A and B?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for 24K Altura - Tower A and B in Baner, Pune is 31 July 2028, including MahaRERA's automatic 4-month extension for all eligible projects.
Is the builder's possession date different from the MahaRERA date for 24K Altura - Tower A and B?
Builders and listing sites often quote an earlier "target" date for handover. The completion date 24K Altura - Tower A and B's builder has filed on MahaRERA, the official one, is 31 July 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
What is the RERA number of 24K Altura - Tower A and B?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of 24K Altura - Tower A and B in Baner, Pune is P52100051316.
Is 24K Altura - Tower A and B registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), 24K Altura - Tower A and B is registered as P52100051316 and its status is "Registered and active".
What is the construction status of 24K Altura - Tower A and B?
According to GharKundli's check of MahaRERA records (updated November 2026), 24K Altura - Tower A and B's status on MahaRERA is "Registered and active". As filed by the builder, slab work ranges from 86% to 89% across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does 24K Altura - Tower A and B have complaints on MahaRERA?
No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.
Is 24K Altura - Tower A and B safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), 24K Altura - Tower A and B is registered on MahaRERA as P52100051316, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
Does 24K Altura - Tower A and B have other wings or phases?
Yes. MahaRERA lists 2 other registrations of the same project, each with its own possession date: 24K Altura - Tower C (P52100077098, possession 30 Apr 2031); 24K Altura - Tower D (P52100054175, possession 31 Jul 2029). Check that your agreement names the registration of your own wing.
How can I get updates if 24K Altura - Tower A and B's possession date changes?
The latest dates are on 24K Altura - Tower A and B's MahaRERA page (P52100051316). GharKundli's Kundli Watch sends a free WhatsApp update on 24K Altura - Tower A and B every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does 24K Altura - Tower A and B have?
According to GharKundli's check of MahaRERA records (updated November 2026), 24K Altura - Tower A and B has 2 buildings filed: Tower A with 32 floors and 109 units; Tower B with 30 floors and 155 units.
How big is the land of 24K Altura - Tower A and B?
According to GharKundli's check of MahaRERA records (updated November 2026), 24K Altura - Tower A and B stands on 2,740 sq m of land (about 0.7 acres), with 48,989 sq m of sanctioned built-up area and 2,859 sq m of recreational open space.
What is the track record of 24K Altura - Tower A and B's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Kolte-patil Developers has 64 projects on MahaRERA since 2017, this one included. Of the 55 GharKundli has checked: 11 finished, 6 within the promised date and 5 needed more time (typically 9 months); 40 still being built, 2 past the promised date (typically 8 months late); 4 lapsed. 29 complaints on MahaRERA across 19 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of 24K Altura - Tower A and B?
Google Maps has reviews of 24K Altura - Tower A and B written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is 24K Altura - Tower A and B?
24K Altura - Tower A and B by KOLTE-PATIL DEVELOPERS LIMITED is in Baner, Pune (pincode 411045), Maharashtra, and is registered on MahaRERA as P52100051316, per GharKundli's check of MahaRERA records. Its boundaries filed there include 12 Mtr Service Road.
How many homes are in 24K Altura - Tower A and B?
According to GharKundli's check of MahaRERA records (updated November 2026), 24K Altura - Tower A and B has 264 homes in 2 towers registered on MahaRERA, and 96% of them are sold or booked.
When was 24K Altura - Tower A and B registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), 24K Altura - Tower A and B was registered on MahaRERA on 8 June 2023. GharKundli did not find a title report on the land on file there.
Are there court cases on 24K Altura - Tower A and B?
No court cases are listed for 24K Altura - Tower A and B on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of 24K Altura - Tower A and B?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is KOLTE-PATIL DEVELOPERS LIMITED, which has 63 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of 24K Altura - Tower A and B
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
All projects with possession due in 2028 in Pune →
Other projects in Baner
- ONE SPACE
- TEJELEVIA BUILDING D & TEJONE BANER
- 24K Manor - Tower B
- 24K Altura - Tower C
- One Place Baner Phase III
- GEN1
- Shivay Residency
- Solitaire Business Hub Baner
Other projects by KOLTE-PATIL DEVELOPERS LIMITED
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.