Skip to content
GharKundli

Abhiruchi MHADA 3

by PARANJAPE SCHEMES (CONSTRUCTION) LTD · Dhayari, Pune

Possession date of Abhiruchi MHADA 3: 1 September 2028. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100051322, and currently active. Its completion date is now September 2028, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Abhiruchi MHADA 3?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Abhiruchi MHADA 3 has moved

  1. 1 May 2028

    Completion date given when the project was registered

  2. 1 September 2028

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Abhiruchi MHADA 3’s extension records on MahaRERA (P52100051322), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Abhiruchi MHADA 3

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each of the 2 court cases, and how it ended
  • Construction pace against the September 2028 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100051322
Status
Registered and active
Builder
PARANJAPE SCHEMES (CONSTRUCTION) LTD
Location
Dhayari, Pune · 411041
Project type
Residential / Group Housing
Registered on
8 Jun 2023
Completion date at registration
May 2028
Latest completion date
September 2028
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
110
Sold or booked
53%
Towers
1
Complaints on MahaRERA
0
Court cases listed
2
Title report on file
Not found
Builder's other MahaRERA projects
25

Construction progress of Abhiruchi MHADA 3, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
M3100%90%20%0%

Commencement certificate (CC), as filed on MahaRERA

  • M3: covers 6 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on Abhiruchi MHADA 3 every month.

Abhiruchi MHADA 3: buildings, flats and land, as filed on MahaRERA

  • Buildings: M3 (6 floors, 110 units)
  • Land: 1,497 sq m (about 0.4 acres) · sanctioned built-up 6,599 sq m

The builder’s record and reviews

Paranjape Schemes Construction (a group of 3 linked companies) has 34 projects on MahaRERA since 2017, this one included. Of the 17 GharKundli has checked: 7 finished, 1 within the promised date and 6 needed more time (typically 32 months); 9 still being built, 4 past the promised date (typically 5 months late); 1 lapsed. 86 complaints on MahaRERA across 9 projects.

Read Google reviews of Abhiruchi MHADA 3 →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Abhiruchi MHADA 3: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Abhiruchi MHADA 3

What is the possession date of Abhiruchi MHADA 3?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Abhiruchi MHADA 3 in Dhayari, Pune is 1 September 2028, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Abhiruchi MHADA 3?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Abhiruchi MHADA 3's builder has filed on MahaRERA, the official one, is 1 September 2028, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Abhiruchi MHADA 3?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Abhiruchi MHADA 3 in Dhayari, Pune is P52100051322.

Is Abhiruchi MHADA 3 registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Abhiruchi MHADA 3 is registered as P52100051322 and its status is "Registered and active".

What is the construction status of Abhiruchi MHADA 3?

According to GharKundli's check of MahaRERA records (updated November 2026), Abhiruchi MHADA 3's status on MahaRERA is "Registered and active". As filed by the builder, slab work on M3 is 90% done and internal work 20%. GharKundli's full report compares construction progress with the deadline.

Does Abhiruchi MHADA 3 have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Abhiruchi MHADA 3 safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Abhiruchi MHADA 3 is registered on MahaRERA as P52100051322, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Abhiruchi MHADA 3's possession date changes?

The latest dates are on Abhiruchi MHADA 3's MahaRERA page (P52100051322). GharKundli's Kundli Watch sends a free WhatsApp update on Abhiruchi MHADA 3 every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does Abhiruchi MHADA 3 have?

According to GharKundli's check of MahaRERA records (updated November 2026), Abhiruchi MHADA 3 has one building filed: M3 with 6 floors and 110 units.

How big is the land of Abhiruchi MHADA 3?

According to GharKundli's check of MahaRERA records (updated November 2026), Abhiruchi MHADA 3 stands on 1,497 sq m of land (about 0.4 acres), with 6,599 sq m of sanctioned built-up area.

What is the track record of Abhiruchi MHADA 3's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Paranjape Schemes Construction (a group of 3 linked companies) has 34 projects on MahaRERA since 2017, this one included. Of the 17 GharKundli has checked: 7 finished, 1 within the promised date and 6 needed more time (typically 32 months); 9 still being built, 4 past the promised date (typically 5 months late); 1 lapsed. 86 complaints on MahaRERA across 9 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of Abhiruchi MHADA 3?

Google Maps has reviews of Abhiruchi MHADA 3 written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Abhiruchi MHADA 3?

Abhiruchi MHADA 3 by PARANJAPE SCHEMES (CONSTRUCTION) LTD is in Dhayari, Pune (pincode 411041), Maharashtra, and is registered on MahaRERA as P52100051322, per GharKundli's check of MahaRERA records.

How many homes are in Abhiruchi MHADA 3?

According to GharKundli's check of MahaRERA records (updated November 2026), Abhiruchi MHADA 3 has 110 homes in 1 tower registered on MahaRERA, and 53% of them are sold or booked.

When was Abhiruchi MHADA 3 registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Abhiruchi MHADA 3 was registered on MahaRERA on 8 June 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Abhiruchi MHADA 3?

2 court cases are listed for Abhiruchi MHADA 3 on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026). GharKundli's full report explains each case and how it ended.

Who is the builder of Abhiruchi MHADA 3?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PARANJAPE SCHEMES (CONSTRUCTION) LTD, which has 25 other projects registered on MahaRERA.

All projects with possession due in 2028 in Pune →

Other projects in Dhayari

All 171 projects in Dhayari (411041) →

Other projects by PARANJAPE SCHEMES (CONSTRUCTION) LTD

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.