Possession: 127 UPPER EAST is marked completed on MahaRERA. How to check it yourself
Registered on MahaRERA under P51800000454. Status: Completed. MahaRERA has issued a regulatory order on this project. 1 complaint is listed against it on MahaRERA.
Source: GharKundli’s check of MahaRERA records, November 2026.
What do you want to know about 127 UPPER EAST?
How the possession date of 127 UPPER EAST has moved
31 December 2019
Completion date given when the project was registered
30 December 2020
Extended at the builder's request (MahaRERA application EXT51800005073)
Reason the builder gave MahaRERA: “The Promoter is applying for extension of Project as he is in the process of procuring TDR /FSI.”
31 October 2022
Extended at the builder's request (MahaRERA application EXT51800011195)
Reason the builder gave MahaRERA: “The promoter has procured FSI for the project and hence to complete the construction needed the extension”
30 June 2024
Extended at the builder's request (MahaRERA application EXT51800016904)
Reason the builder gave MahaRERA: “In accordance with Oder no 40 dated 27/12/2022 we are applying for Extension without majority consents of the allotees. The project is nearing completion, we require extension for a period of ONE year in order to close the project smoothly.”
Source: 127 UPPER EAST’s extension records on MahaRERA (P51800000454), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.
What builders tell MahaRERA when they’re late: 14,973 applications analysed →GharKundli’s full report on 127 UPPER EAST
Read from every filing on MahaRERA when you open it
- Risk & trust score, every point explained
- What the title report says about the land
- Each of the 1 complaint, and how it ended
- Construction pace against the June 2024 deadline
- Agreement clauses weaker than the RERA model
- Escrow audit, loans and the builder's record
- Questions to get answered in writing before you pay
- MahaRERA registration
- P51800000454
- Status
- Completed
- Builder
- PARANJAPE SCHEMES (CONSTRUCTION) LTD
- Location
- Andheri, Mumbai · 400055
- Project type
- Residential / Group Housing
- Registered on
- 18 Jul 2017
- Completion date at registration
- December 2019
- Latest completion date
- June 2024
- Delay so far
- 54 months
- Homes
- 28
- Towers
- 2
- Complaints on MahaRERA
- 1
- Court cases listed
- 0
- MahaRERA regulatory orders
- 1
- Title report on file
- Not found
- Builder's other MahaRERA projects
- 25
Construction progress of 127 UPPER EAST, as filed by the builder
What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.
| Tower / wing | Plinth | Slabs (structure) | Internal work | Lifts, fire & electrical |
|---|---|---|---|---|
| BUILDING A | 100% | 80% | 30% | 0% |
| BUILDING B | 100% | 80% | 30% | 0% |
Want to know when this changes? Kundli Watch sends a free WhatsApp update on 127 UPPER EAST every month.
127 UPPER EAST: buildings, flats and land, as filed on MahaRERA
- Buildings: BUILDING A (11 floors) · BUILDING B (11 floors)
- Land: 1,808 sq m (about 0.4 acres) · sanctioned built-up 5,330 sq m · recreational space 262 sq m
- Boundaries filed include: Western Express Highway, Prabhat Colony Road No 2
- Map: the location the builder filed on MahaRERA
The builder’s record and reviews
Paranjape Schemes Construction (a group of 3 linked companies) has 34 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 7 finished, 1 within the promised date and 6 needed more time (typically 32 months); 10 still being built, 5 past the promised date (typically 6 months late); 1 lapsed. 88 complaints on MahaRERA across 10 projects.
Read Google reviews of 127 UPPER EAST →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.
Kundli Watch
127 UPPER EAST: buyers & owners
Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.
Be the first to watch this project.
How are you connected to this project?
Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.
Common questions about 127 UPPER EAST
What is the possession date of 127 UPPER EAST?
According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for 127 UPPER EAST in Andheri, Mumbai is 30 June 2024 — 54 months later than 31 December 2019, the date given at registration.
Is the builder's possession date different from the MahaRERA date for 127 UPPER EAST?
Builders and listing sites often quote an earlier "target" date for handover. The completion date 127 UPPER EAST's builder has filed on MahaRERA, the official one, is 30 June 2024, already 54 months later than the 31 December 2019 given at registration, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.
Why was the possession date of 127 UPPER EAST extended?
According to GharKundli's check of MahaRERA records (updated November 2026), 127 UPPER EAST's builder applied to MahaRERA to extend the completion date 3 times: to 30 December 2020, giving the reason "The Promoter is applying for extension of Project as he is in the process of procuring TDR /FSI."; to 31 October 2022, giving the reason "The promoter has procured FSI for the project and hence to complete the construction needed the extension"; to 30 June 2024, giving the reason "In accordance with Oder no 40 dated 27/12/2022 we are applying for Extension without majority consents of the allotees. The project is nearing completion, we require extension for a period of ONE year in order to close the project smoothly.".
What is the RERA number of 127 UPPER EAST?
According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of 127 UPPER EAST in Andheri, Mumbai is P51800000454.
Is 127 UPPER EAST registered with MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), 127 UPPER EAST is registered as P51800000454 and its status is "Completed".
What is the construction status of 127 UPPER EAST?
According to GharKundli's check of MahaRERA records (updated November 2026), 127 UPPER EAST's status on MahaRERA is "Completed". As filed by the builder, slab work is 80% done across 2 towers. GharKundli's full report compares construction progress with the deadline.
Does 127 UPPER EAST have complaints on MahaRERA?
1 complaint was listed on MahaRERA as of October 2026, per GharKundli's weekly check. GharKundli's full report explains each case and how it ended.
Is 127 UPPER EAST safe to buy?
According to GharKundli's check of MahaRERA records (updated November 2026), 127 UPPER EAST is registered on MahaRERA as P51800000454, its MahaRERA status is "Completed", its completion date has moved 54 months since registration and 1 complaint is listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.
How can I get updates if 127 UPPER EAST's possession date changes?
The latest dates are on 127 UPPER EAST's MahaRERA page (P51800000454). GharKundli's Kundli Watch sends a free WhatsApp update on 127 UPPER EAST every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.
How many floors does 127 UPPER EAST have?
According to GharKundli's check of MahaRERA records (updated November 2026), 127 UPPER EAST has 2 buildings filed: BUILDING A with 11 floors; BUILDING B with 11 floors.
How big is the land of 127 UPPER EAST?
According to GharKundli's check of MahaRERA records (updated November 2026), 127 UPPER EAST stands on 1,808 sq m of land (about 0.4 acres), with 5,330 sq m of sanctioned built-up area and 262 sq m of recreational open space.
What is the track record of 127 UPPER EAST's builder?
According to GharKundli's check of MahaRERA records (updated November 2026), Paranjape Schemes Construction (a group of 3 linked companies) has 34 projects on MahaRERA since 2017, this one included. Of the 18 GharKundli has checked: 7 finished, 1 within the promised date and 6 needed more time (typically 32 months); 10 still being built, 5 past the promised date (typically 6 months late); 1 lapsed. 88 complaints on MahaRERA across 10 projects. GharKundli's full report covers the builder's record in detail.
Where can I read reviews of 127 UPPER EAST?
Google Maps has reviews of 127 UPPER EAST written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: 1 complaint is listed on MahaRERA, and Kundli Watch shows verified owners of the project.
Where is 127 UPPER EAST?
127 UPPER EAST by PARANJAPE SCHEMES (CONSTRUCTION) LTD is in Andheri, Mumbai (pincode 400055), near Santacruz East, Santacruz West, Vakola, Maharashtra, and is registered on MahaRERA as P51800000454, per GharKundli's check of MahaRERA records. Its boundaries filed there include Western Express Highway, Prabhat Colony Road No 2.
How many homes are in 127 UPPER EAST?
According to GharKundli's check of MahaRERA records (updated November 2026), 127 UPPER EAST has 28 homes in 2 towers registered on MahaRERA.
When was 127 UPPER EAST registered on MahaRERA?
According to GharKundli's check of MahaRERA records (updated November 2026), 127 UPPER EAST was registered on MahaRERA on 18 July 2017. GharKundli did not find a title report on the land on file there.
Are there court cases on 127 UPPER EAST?
No court cases are listed for 127 UPPER EAST on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).
Who is the builder of 127 UPPER EAST?
According to GharKundli's check of MahaRERA records (updated November 2026), the builder is PARANJAPE SCHEMES (CONSTRUCTION) LTD, which has 25 other projects registered on MahaRERA.
Check it yourself on MahaRERA
- How to check the possession date of 127 UPPER EAST
- How to find and verify a MahaRERA number
- How to check construction status on MahaRERA
- Occupancy certificate (OC): what to check before possession
- Possession delayed? Work out the interest the builder owes
- How to file a MahaRERA complaint against a builder
- Where MahaRERA complaints are: the data
- Why builders ask MahaRERA for more time: the data
Other projects in Andheri
- MESACON HARMONY
- M.K Heritage
- Royal Fantasy Phase III
- LUMA TOWERS A & B
- Pearl 2
- Royal Fantasy Phase II
- State Bank Of India Employees Sakar Swapna CHSL
- Luma Tower C
Other projects by PARANJAPE SCHEMES (CONSTRUCTION) LTD
Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.