by Mohar Projects LLP · Near Katraj dairy, Pune

Possession date of Mohar Srushti: 30 April 2031. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100051231, and currently active. Its completion date is now April 2031, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about Mohar Srushti?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of Mohar Srushti has moved

  1. 31 December 2030

    Completion date given when the project was registered

  2. 30 April 2031

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: Mohar Srushti’s extension records on MahaRERA (P52100051231), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on Mohar Srushti

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2031 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100051231
Status
Registered and active
Builder
Mohar Projects LLP
Location
Near Katraj dairy, Pune · 410405
Project type
Plotted
Registered on
8 Jun 2023
Completion date at registration
December 2030
Latest completion date
April 2031
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found

Mohar Srushti: buildings, flats and land, as filed on MahaRERA

  • Land: 51,130 sq m (about 12.6 acres) · recreational space 4,386 sq m

The builder’s record and reviews

Not enough of this builder’s other MahaRERA projects have reached their promised date to judge yet.

Read Google reviews of Mohar Srushti →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

Mohar Srushti: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about Mohar Srushti

What is the possession date of Mohar Srushti?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for Mohar Srushti in Near Katraj dairy, Pune is 30 April 2031, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for Mohar Srushti?

Builders and listing sites often quote an earlier "target" date for handover. The completion date Mohar Srushti's builder has filed on MahaRERA, the official one, is 30 April 2031, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of Mohar Srushti?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of Mohar Srushti in Near Katraj dairy, Pune is P52100051231.

Is Mohar Srushti registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Mohar Srushti is registered as P52100051231 and its status is "Registered and active".

What is the construction status of Mohar Srushti?

According to GharKundli's check of MahaRERA records (updated November 2026), Mohar Srushti's status on MahaRERA is "Registered and active". GharKundli's full report compares construction progress with the deadline.

Does Mohar Srushti have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is Mohar Srushti safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), Mohar Srushti is registered on MahaRERA as P52100051231, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if Mohar Srushti's possession date changes?

The latest dates are on Mohar Srushti's MahaRERA page (P52100051231). GharKundli's Kundli Watch sends a free WhatsApp update on Mohar Srushti every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How big is the land of Mohar Srushti?

According to GharKundli's check of MahaRERA records (updated November 2026), Mohar Srushti stands on 51,130 sq m of land (about 12.6 acres) and 4,386 sq m of recreational open space.

Where can I read reviews of Mohar Srushti?

Google Maps has reviews of Mohar Srushti written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is Mohar Srushti?

Mohar Srushti by Mohar Projects LLP is in Near Katraj dairy, Pune (pincode 410405), Maharashtra, and is registered on MahaRERA as P52100051231, per GharKundli's check of MahaRERA records.

When was Mohar Srushti registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), Mohar Srushti was registered on MahaRERA on 8 June 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on Mohar Srushti?

No court cases are listed for Mohar Srushti on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of Mohar Srushti?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Mohar Projects LLP.

All projects with possession due in 2031 in Pune →

Other projects in Mawal

All 23 projects in Kamshet (410405) →

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.