BASIL MAXIMUS WING C

by BASIL AVANTE LLP · Punawale, PuneAlso near Tathawade

Possession date of BASIL MAXIMUS WING C: 30 April 2027. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100050916, and currently active. Its completion date is now April 2027, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about BASIL MAXIMUS WING C?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of BASIL MAXIMUS WING C has moved

  1. 31 December 2026

    Completion date given when the project was registered

  2. 30 April 2027

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: BASIL MAXIMUS WING C’s extension records on MahaRERA (P52100050916), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on BASIL MAXIMUS WING C

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the April 2027 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100050916
Status
Registered and active
Builder
BASIL AVANTE LLP
Location
Punawale, Pune · 411033
Project type
Commercial
Registered on
15 May 2023
Completion date at registration
December 2026
Latest completion date
April 2027
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
0
Sold or booked
96%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
4

Construction progress of BASIL MAXIMUS WING C, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
BASIL MAXIMUS WING C100%100%95%40%

Commencement certificate (CC), as filed on MahaRERA

  • BASIL MAXIMUS WING C: covers 7 floors

Want to know when this changes? Kundli Watch sends a free WhatsApp update on BASIL MAXIMUS WING C every month.

BASIL MAXIMUS WING C: buildings, flats and land, as filed on MahaRERA

The builder’s record and reviews

Basil Avante (a group of 3 linked companies) has 9 projects on MahaRERA since 2022, this one included. Of the 9 GharKundli has checked: 1 finished, all within the promised date; 8 still being built, none past the promised date yet. No complaints on MahaRERA.

Read Google reviews of BASIL MAXIMUS WING C →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

BASIL MAXIMUS WING C: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about BASIL MAXIMUS WING C

What is the possession date of BASIL MAXIMUS WING C?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for BASIL MAXIMUS WING C in Punawale, Pune is 30 April 2027, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for BASIL MAXIMUS WING C?

Builders and listing sites often quote an earlier "target" date for handover. The completion date BASIL MAXIMUS WING C's builder has filed on MahaRERA, the official one, is 30 April 2027, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of BASIL MAXIMUS WING C?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of BASIL MAXIMUS WING C in Punawale, Pune is P52100050916.

Is BASIL MAXIMUS WING C registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), BASIL MAXIMUS WING C is registered as P52100050916 and its status is "Registered and active".

What is the construction status of BASIL MAXIMUS WING C?

According to GharKundli's check of MahaRERA records (updated November 2026), BASIL MAXIMUS WING C's status on MahaRERA is "Registered and active". As filed by the builder, slab work on BASIL MAXIMUS WING C is 100% done and internal work 95%. GharKundli's full report compares construction progress with the deadline.

Does BASIL MAXIMUS WING C have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is BASIL MAXIMUS WING C safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), BASIL MAXIMUS WING C is registered on MahaRERA as P52100050916, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does BASIL MAXIMUS WING C have other wings or phases?

Yes. MahaRERA lists 4 other registrations of the same project, each with its own possession date: BASIL MAXIMUS WING D AND E (P52100051323, possession 30 Apr 2028); BASIL MAXIMUS WING F (P52100056356, possession 30 Apr 2029); BASIL MAXIMUS WING G (P52100080092, possession 30 Apr 2030); Basil Maximus Wing H (PR1260002503019, possession 30 Apr 2030). Check that your agreement names the registration of your own wing.

How can I get updates if BASIL MAXIMUS WING C's possession date changes?

The latest dates are on BASIL MAXIMUS WING C's MahaRERA page (P52100050916). GharKundli's Kundli Watch sends a free WhatsApp update on BASIL MAXIMUS WING C every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does BASIL MAXIMUS WING C have?

According to GharKundli's check of MahaRERA records (updated November 2026), BASIL MAXIMUS WING C has one building filed: BASIL MAXIMUS WING C with 7 floors and 48 units.

How big is the land of BASIL MAXIMUS WING C?

According to GharKundli's check of MahaRERA records (updated November 2026), BASIL MAXIMUS WING C stands on 2,117 sq m of land (about 0.5 acres), with 2,117 sq m of sanctioned built-up area and 2,582 sq m of recreational open space.

What is the track record of BASIL MAXIMUS WING C's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Basil Avante (a group of 3 linked companies) has 9 projects on MahaRERA since 2022, this one included. Of the 9 GharKundli has checked: 1 finished, all within the promised date; 8 still being built, none past the promised date yet. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of BASIL MAXIMUS WING C?

Google Maps has reviews of BASIL MAXIMUS WING C written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is BASIL MAXIMUS WING C?

BASIL MAXIMUS WING C by BASIL AVANTE LLP is in Punawale, Pune (pincode 411033), near Tathawade, Maharashtra, and is registered on MahaRERA as P52100050916, per GharKundli's check of MahaRERA records.

How many homes are in BASIL MAXIMUS WING C?

According to GharKundli's check of MahaRERA records (updated November 2026), BASIL MAXIMUS WING C has 0 homes in 1 tower registered on MahaRERA, and 96% of them are sold or booked.

When was BASIL MAXIMUS WING C registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), BASIL MAXIMUS WING C was registered on MahaRERA on 15 May 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on BASIL MAXIMUS WING C?

No court cases are listed for BASIL MAXIMUS WING C on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of BASIL MAXIMUS WING C?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is BASIL AVANTE LLP, which has 4 other projects registered on MahaRERA.

All projects with possession due in 2027 in Pune →

Other projects in pincode 411033

All 442 projects in Chinchwadgaon (411033) →

Other projects by BASIL AVANTE LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.