by JAWALESHWAR CONSTRUCTION · Vadgaon Maval, PuneAlso near Panshet, P.C.N.T

Possession date of EVEREST: 31 July 2026. This is the latest completion date the builder has filed on MahaRERA, and it has already passed. How to check it yourself

Registered on MahaRERA under P52100051215. Status: Lapsed (registration period ended). Its completion date is now July 2026, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

The latest completion date on MahaRERA (July 2026) has passed.

What do you want to know about EVEREST?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of EVEREST has moved

  1. 31 March 2026

    Completion date given when the project was registered

  2. 31 July 2026

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: EVEREST’s extension records on MahaRERA (P52100051215), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on EVEREST

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the July 2026 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay
MahaRERA registration
P52100051215
Status
Lapsed (registration period ended)
Builder
JAWALESHWAR CONSTRUCTION
Location
Vadgaon Maval, Pune · 412106
Project type
Others
Registered on
8 Jun 2023
Completion date at registration
March 2026
Latest completion date
July 2026
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
32
Sold or booked
78%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
2

Construction progress of EVEREST, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
EVEREST100%65%20%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on EVEREST every month.

EVEREST: buildings, flats and land, as filed on MahaRERA

  • Buildings: EVEREST (7 floors)
  • Land: 1,288 sq m (about 0.3 acres) · sanctioned built-up 2,879 sq m

The builder’s record and reviews

Jawaleshwar Construction has 5 projects on MahaRERA since 2023, this one included. Of the 3 GharKundli has checked: 2 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA.

Read Google reviews of EVEREST →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

EVEREST: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about EVEREST

What is the possession date of EVEREST?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for EVEREST in Vadgaon Maval, Pune is 31 July 2026, including MahaRERA's automatic 4-month extension for all eligible projects. That date has already passed.

Is the builder's possession date different from the MahaRERA date for EVEREST?

Builders and listing sites often quote an earlier "target" date for handover. The completion date EVEREST's builder has filed on MahaRERA, the official one, is 31 July 2026, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of EVEREST?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of EVEREST in Vadgaon Maval, Pune is P52100051215.

Is EVEREST registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), EVEREST is registered as P52100051215 and its status is "Lapsed (registration period ended)".

What is the construction status of EVEREST?

According to GharKundli's check of MahaRERA records (updated November 2026), EVEREST's status on MahaRERA is "Lapsed (registration period ended)". As filed by the builder, slab work on EVEREST is 65% done and internal work 20%. GharKundli's full report compares construction progress with the deadline.

Does EVEREST have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is EVEREST safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), EVEREST is registered on MahaRERA as P52100051215, its MahaRERA status is "Lapsed (registration period ended)", its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

How can I get updates if EVEREST's possession date changes?

The latest dates are on EVEREST's MahaRERA page (P52100051215). GharKundli's Kundli Watch sends a free WhatsApp update on EVEREST every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does EVEREST have?

According to GharKundli's check of MahaRERA records (updated November 2026), EVEREST has one building filed: EVEREST with 7 floors.

How big is the land of EVEREST?

According to GharKundli's check of MahaRERA records (updated November 2026), EVEREST stands on 1,288 sq m of land (about 0.3 acres), with 2,879 sq m of sanctioned built-up area.

What is the track record of EVEREST's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Jawaleshwar Construction has 5 projects on MahaRERA since 2023, this one included. Of the 3 GharKundli has checked: 2 still being built, none past the promised date yet; 1 lapsed. No complaints on MahaRERA. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of EVEREST?

Google Maps has reviews of EVEREST written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is EVEREST?

EVEREST by JAWALESHWAR CONSTRUCTION is in Vadgaon Maval, Pune (pincode 412106), near Panshet, P.C.N.T, Maharashtra, and is registered on MahaRERA as P52100051215, per GharKundli's check of MahaRERA records.

How many homes are in EVEREST?

According to GharKundli's check of MahaRERA records (updated November 2026), EVEREST has 32 homes in 1 tower registered on MahaRERA, and 78% of them are sold or booked.

When was EVEREST registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), EVEREST was registered on MahaRERA on 8 June 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on EVEREST?

No court cases are listed for EVEREST on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of EVEREST?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is JAWALESHWAR CONSTRUCTION, which has 2 other projects registered on MahaRERA.

All projects with possession due in 2026 in Pune →

Other projects in pincode 412106

All 75 projects in Vadgaon (412106) →

Other projects by JAWALESHWAR CONSTRUCTION

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.