The Balmoral Hillside-Tower A, Phase II

by Kanika Infracon LLP · Baner, Pune

Possession date of The Balmoral Hillside-Tower A, Phase II: 30 October 2029. This is the latest completion date the builder has filed on MahaRERA. How to check it yourself

Registered on MahaRERA under P52100052022, and currently active. Its completion date is now October 2029, including MahaRERA's automatic 4-month extension for all eligible projects; the builder hasn't asked for more time.

Source: GharKundli’s check of MahaRERA records, November 2026.

What do you want to know about The Balmoral Hillside-Tower A, Phase II?

Ask us on WhatsAppNo login needed. A real person replies.

How the possession date of The Balmoral Hillside-Tower A, Phase II has moved

  1. 30 June 2029

    Completion date given when the project was registered

  2. 30 October 2029

    MahaRERA's automatic 4-month extension for all eligible projects, not the builder's request

Source: The Balmoral Hillside-Tower A, Phase II’s extension records on MahaRERA (P52100052022), read by GharKundli in November 2026. The builder’s reasons are quoted as filed. Your own possession date is the one in your agreement for sale.

What builders tell MahaRERA when they’re late: 14,973 applications analysed →

GharKundli’s full report on The Balmoral Hillside-Tower A, Phase II

Read from every filing on MahaRERA when you open it

  • Risk & trust score, every point explained
  • What the title report says about the land
  • Each complaint and court case, and how it ended
  • Construction pace against the October 2029 deadline
  • Agreement clauses weaker than the RERA model
  • Escrow audit, loans and the builder's record
  • Questions to get answered in writing before you pay

Other wings and phases of this project

Each is registered on MahaRERA separately, with its own possession date. Check the one your flat is in.

MahaRERA registration
P52100052022
Status
Registered and active
Builder
Kanika Infracon LLP
Location
Baner, Pune · 411045
Project type
Residential / Group Housing
Registered on
19 Jul 2023
Completion date at registration
June 2029
Latest completion date
October 2029
MahaRERA's automatic extension
+4 months (force majeure, all eligible projects)
Homes
136
Sold or booked
36%
Towers
1
Complaints on MahaRERA
0
Court cases listed
0
Title report on file
Not found
Builder's other MahaRERA projects
3

Construction progress of The Balmoral Hillside-Tower A, Phase II, as filed by the builder

What the builder has reported to MahaRERA, as GharKundli read it in November 2026. GharKundli’s full report compares it with the deadline.

Tower / wingPlinthSlabs (structure)Internal workLifts, fire & electrical
The Balmoral Hillside-Tower A, Phase II0%0%0%0%

Want to know when this changes? Kundli Watch sends a free WhatsApp update on The Balmoral Hillside-Tower A, Phase II every month.

The Balmoral Hillside-Tower A, Phase II: buildings, flats and land, as filed on MahaRERA

  • Buildings: The Balmoral Hillside-Tower A, Phase II (39 floors)
  • Land: 1,019 sq m (about 0.3 acres) · sanctioned built-up 37,048 sq m · recreational space 1,828 sq m

The builder’s record and reviews

Kasturi Spaces (a group of 3 linked companies) has 12 projects on MahaRERA since 2022, this one included. Of the 10 GharKundli has checked: 10 still being built, none past the promised date yet. 5 complaints on MahaRERA across 3 projects.

Read Google reviews of The Balmoral Hillside-Tower A, Phase II →Reviews on Google are opinions by Google users; GharKundli doesn’t check them.

Kundli Watch

The Balmoral Hillside-Tower A, Phase II: buyers & owners

Free: a WhatsApp update every month on this project, and straight away when anything changes on MahaRERA — a later completion date, new complaints, a red flag. Your number stays private: never shown to other members or the builder.

Be the first to watch this project.

How are you connected to this project?

Bought here? No document needed now. From the builder’s team? Join to answer buyers’ questions; you never see members’ details. You’ll sign in with a one-time code, then come straight back here.

Common questions about The Balmoral Hillside-Tower A, Phase II

What is the possession date of The Balmoral Hillside-Tower A, Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), the latest completion date filed on MahaRERA for The Balmoral Hillside-Tower A, Phase II in Baner, Pune is 30 October 2029, including MahaRERA's automatic 4-month extension for all eligible projects.

Is the builder's possession date different from the MahaRERA date for The Balmoral Hillside-Tower A, Phase II?

Builders and listing sites often quote an earlier "target" date for handover. The completion date The Balmoral Hillside-Tower A, Phase II's builder has filed on MahaRERA, the official one, is 30 October 2029, per GharKundli's check of MahaRERA records. If possession is late, what counts under RERA (Section 18) is the possession date written in your agreement for sale.

What is the RERA number of The Balmoral Hillside-Tower A, Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), the MahaRERA registration number of The Balmoral Hillside-Tower A, Phase II in Baner, Pune is P52100052022.

Is The Balmoral Hillside-Tower A, Phase II registered with MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), The Balmoral Hillside-Tower A, Phase II is registered as P52100052022 and its status is "Registered and active".

What is the construction status of The Balmoral Hillside-Tower A, Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), The Balmoral Hillside-Tower A, Phase II's status on MahaRERA is "Registered and active". As filed by the builder, slab work on The Balmoral Hillside-Tower A, Phase II is 0% done and internal work 0%. GharKundli's full report compares construction progress with the deadline.

Does The Balmoral Hillside-Tower A, Phase II have complaints on MahaRERA?

No complaints were listed on MahaRERA as of November 2026, per GharKundli's weekly check.

Is The Balmoral Hillside-Tower A, Phase II safe to buy?

According to GharKundli's check of MahaRERA records (updated November 2026), The Balmoral Hillside-Tower A, Phase II is registered on MahaRERA as P52100052022, its completion date has not been moved by the builder and no complaints are listed against it. GharKundli doesn't call a project safe or unsafe from these numbers alone: its full report gives a risk & trust score with every point explained.

Does The Balmoral Hillside-Tower A, Phase II have other wings or phases?

Yes. MahaRERA lists 1 other registration of the same project, each with its own possession date: The Balmoral Hillside - Tower B , Phase I (P52100046444, possession 30 Apr 2029). Check that your agreement names the registration of your own wing.

How can I get updates if The Balmoral Hillside-Tower A, Phase II's possession date changes?

The latest dates are on The Balmoral Hillside-Tower A, Phase II's MahaRERA page (P52100052022). GharKundli's Kundli Watch sends a free WhatsApp update on The Balmoral Hillside-Tower A, Phase II every month, and straight away when anything changes on MahaRERA: a later completion date, new complaints or a red flag. Your number is never shown to the builder.

How many floors does The Balmoral Hillside-Tower A, Phase II have?

According to GharKundli's check of MahaRERA records (updated November 2026), The Balmoral Hillside-Tower A, Phase II has one building filed: The Balmoral Hillside-Tower A, Phase II with 39 floors.

How big is the land of The Balmoral Hillside-Tower A, Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), The Balmoral Hillside-Tower A, Phase II stands on 1,019 sq m of land (about 0.3 acres), with 37,048 sq m of sanctioned built-up area and 1,828 sq m of recreational open space.

What is the track record of The Balmoral Hillside-Tower A, Phase II's builder?

According to GharKundli's check of MahaRERA records (updated November 2026), Kasturi Spaces (a group of 3 linked companies) has 12 projects on MahaRERA since 2022, this one included. Of the 10 GharKundli has checked: 10 still being built, none past the promised date yet. 5 complaints on MahaRERA across 3 projects. GharKundli's full report covers the builder's record in detail.

Where can I read reviews of The Balmoral Hillside-Tower A, Phase II?

Google Maps has reviews of The Balmoral Hillside-Tower A, Phase II written by Google users; GharKundli links to them on this page but doesn't check them. For facts rather than opinions: no complaints are listed on MahaRERA, and Kundli Watch shows verified owners of the project.

Where is The Balmoral Hillside-Tower A, Phase II?

The Balmoral Hillside-Tower A, Phase II by Kanika Infracon LLP is in Baner, Pune (pincode 411045), Maharashtra, and is registered on MahaRERA as P52100052022, per GharKundli's check of MahaRERA records.

How many homes are in The Balmoral Hillside-Tower A, Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), The Balmoral Hillside-Tower A, Phase II has 136 homes in 1 tower registered on MahaRERA, and 36% of them are sold or booked.

When was The Balmoral Hillside-Tower A, Phase II registered on MahaRERA?

According to GharKundli's check of MahaRERA records (updated November 2026), The Balmoral Hillside-Tower A, Phase II was registered on MahaRERA on 19 July 2023. GharKundli did not find a title report on the land on file there.

Are there court cases on The Balmoral Hillside-Tower A, Phase II?

No court cases are listed for The Balmoral Hillside-Tower A, Phase II on MahaRERA, per GharKundli's check of MahaRERA records (updated November 2026).

Who is the builder of The Balmoral Hillside-Tower A, Phase II?

According to GharKundli's check of MahaRERA records (updated November 2026), the builder is Kanika Infracon LLP, which has 3 other projects registered on MahaRERA.

All projects with possession due in 2029 in Pune →

Other projects in Baner

All 425 projects in Baner (411045) →

Other projects by Kanika Infracon LLP

Data compiled by GharKundli (gharkundli.com) from MahaRERA public records, as of November 2026. Check the project’s MahaRERA page for the latest filings. Not legal advice.